full-cycle project management: CRM & System integration
MonieFi Project Closure Report
Component
Details
Project Overview
MonieFi CRM Implementation Project aimed to deploy
a scalable and integrated Customer Relationship
Management system (Microsoft Dynamics 365) to
improve lead management, customer service,
reporting, and business process automation.
Objective and Scope
To drive operational efficiency and improve customer
experience.
Deliverables Summary
Implemented a fully functional CRM System integrated
with MonieFi financial and transaction platform.
Status: Complete
Centralised lead and contact data
Status: Complete
Verified migrated data
Status: Complete
Custom dashboard for sales and customer support
efficiency and to display custom reports.
Status: Complete
Automated processes for MonieFi’s payment
processes.
Status: Complete
Integration with microsoft apps and 3rd party tools
Status: Complete
Training of end users.
Status: Complete
Budget Performance
Planned Budget: £10,000.00
Actual Budget: £10,000.00
Timeline Performance
Project was completed within the 8 week timeframe
given.
Key Success Factor
● 100% Migration of lead and customer data
without errors.
● 80% User adoption rate within the first month.
● 25% Lead conversion efficiency in the first
quarter.
● Reduction in customer response time by 30%.
● Integration with MonieFi payment systems
Stakeholder Feedback
The stakeholders expressed enthusiasm regarding the
delivery of the project; however, they requested that
training sessions should also be conducted in a
classroom setting.
Challenges faced
User resistance to adoption-mitigated by
Change management and early training
Timeline pressure-mitigated by
Daily stand-ups and strict task tracking
Lessons Learned
Effective Team Collaboration is essential for the
successful implementation of future projects
Handover Details
MonieFi Sales /Marketing department has been
handed over the CRM management.
Close out Action
Finalised all vendor contract, achieved project
documentation and released resources
The project outcome has been measured against its acceptance criteria and has been formally
accepted by the project owner and / or customer.
Signatures: The signatures of the people below, document approval of the formal project closure
Signature
Date
Project Manager:
O.O
16/6/2025
Project Sponsor:
C.U
16/06/2025
Signing off on this project closure by the project owner indicates that the project is complete and the outcome is
acceptable
Documents Uploaded to The Project Repository
1. Project Brief
2. Stakeholder and Their Expectation
3. Work Breakdown Structure
4. RACI Matrix
5. Project Scope Statement
6. Selection of The Project Approach
7. Requirement Documentation
8. Solution Evaluation Comparisons
9. Cost/Benefit analysis
10. Business Case
11. Project Charter
12. Project Plan Table
13. Project Plan using Project Libre
14. Product Backlog
15. Use Case and Use Case diagram
16. Test Plan/Test Scenario and Test Cases
17. Move Project Backlog to Jira
18. Sprint Planned and Executed
19. Manual Testing User Stories
20. RAID Closure Log
21. Lessons Learned Document
22. Client Acceptance Form