Noyes Elementary Work Project
NOYES ELEMENTARY WORK PROJET
Project description
Project Name: Noyes Elementary School
Companies: Office Team / Richard & Richard Construction
Contractor: Pasadena School District
Duration of project: 3 weeks.
For this project, I was responsible for administrating and collecting all extra materials from
subcontractors. This is called the “closeout stage’ which is the pre-final stage of the
construction project at Noyes Elementary School located in Altadena, CA. While the
Superintendent was busy supervising the work of the contractors, before the subcontractors
completed the project, it was required by the contract for them to leave additional materials
in case of damage or wear/tear in the project area. My job was to make an inventory of
such items and deliver them to the Pasadena School District to be examined and approved.
After finishing that pre-last stage my work was done and I needed to pack and have the
office trailer picked up. I cleaned the office, put all the files and media in storage boxes, and
presented them to the operations manager so he could take back all project details to
headquarters. I also called the company responsible for picking up the trailer so that it
would give the contractors the space necessary to complete the area (Landscaping) and
thus the project.