SKETCH OF DISTR. LINES RE-ROUTING
Along Old Hrb mn Rd., to pass toff at Amity Hall then to end of
feeder at Open Jumpers
RHODENS PEN 210 NEW LINE RE-ROUTING
BETWEEN EP 2366 AND EP 2359, ALONG OLD HARBOUR ROAD, IN THE VICINITY OF THE TOLL ROAD HIGHWAY OVERPASS NEAR GUTTERS
Install 100lb Steel Rail, preset in
reinforced concrete, attached to O/Head
Guy
PP10, 10th pole loc fr FiWi
Place, TDE.2 3ph 45-4
Existing pole position and existing line to be shifted as
shown; plant 40' pole infront of existing.
CAUTION: Transfer/inter-connection will be done during
scheduled de-energized/planned outage. NOTE: New Line
must be commissioned before energized.
EP2365 Pole # 227991,
Existing pole position and existing line to be
shifted as shown; plant 45' pole infront of
existing.
CAUTION: Transfer will be done during
scheduled de-energized/planned outage
Line routed along trainline, that
runs parallel to Toll road/highway
in bushes behind Grove Scheme
PP04, 4th pole loc fr FiWi
Place, TA 3ph 40-4
PP08, 8th pole loc fr FiWi
Place, T 3ph 40-4
PP07, 7th pole loc fr FiWi
Place, TA 3ph 40-4
PP09, 9th pole loc fr FiWi
Place, TA 3ph 40-4
NOTES
PP06, 6th pole loc fr FiWi
Place, TA 3ph 45-2
EP2366A, Pole # 156170,
Opp entr to FiWi Place, to
be retired and replaced
with PP 01, TDE 3ph
PP03, 3d pole loc fr FiWi
Place, TA 3ph 40-4
PP05, 5th pole loc fr FiWi
Place, TA 3ph 45-2
TOTAL REPLACEMENT OF EXISTING POLES........2
TOTAL NEW/PROPOSED POLES.........................9
LEGEND
EXISTING POLE SHOWN AS............................................
PP02, 2nd pole loc fr
FiWi Place, TA 3ph 40-4
EXISTING 12kV (TO BE UPGRADED TO 24kV)..................
PROPOSED 12kV (TO BE DESIGNED AT 24kV).................
Outer limbs of large/tall tree need
Tall bucket to remove
DOWN GUY...................................................................
OVER-HEAD GUY ON STEEL RAIL...................................
PROPOSED POLE, 40-4 OR 45-2, SHOWN AS.................
CONSTRUCTION NOTES
1. DIG HOLES FOR POLES & GUY POSITIONS
2. ERECT POLES AND GUYS AS REQUIRED
3. STRING 3PH & NEUTRAL COND, USING 394.5 AAA FOR PHASE
4. RETENSION GUYS, PHASE AND NEUTRAL COND
5. SUSPEND COND. AT EACH END UNTIL SCHEDULED DE-ENERGIZED
PLANNED WORKS
6. UNDER PTW, INTERCONNECT DE-ENERGIZED/ISOL AND SHORT&
GROUNDED LINES TO EXISTING 3PH PRIM & NEUTRAL
7. COMPLETE COMMISSIONING. CLEARANCE PROCEDURES TO RE-ENERGIZE
EXISTING LINE AND ENERGIZE NEW LINE SECTION