Time Schedule Using Primavera
Work Sample
Activity ID
Activity Name
Original Start
Duration
EGPC New Building Contr
Contract BaseLine
Construction
EGPC Building Phase ( 1 ) Works
Wor
Excavation
Soil Nailing
1st Stop
2nd Stop
3rd Stop
Replacement
EGPC Building Phase ( 2 ) wor
works
General Concrete Skeleton W
Works
Raft Works
General Raft Works
Plain Concrete
Isolation Works
Foundation works
Foundation Works For
Fo Zone ( 1 )
Foundation Works For
Fo Zone ( 2 )
Foundation Works For
Fo Zone ( 3 )
Foundation Works For
Fo Zone ( 4 )
Foundation Works For
Fo Zone ( 5 )
Foundation Works For
Fo Zone ( 6 )
Foundation Works For
Fo Zone ( 7 )
Foundation Works For
Fo Zone ( 8 )
Foundation Works For
Fo Zone ( 9 )
Foundation Works For
Fo Zone ( 10 )
Foundation Works For
Fo Zone ( 11 )
Foundation Works For
Fo Zone ( 12 )
Third Basement Works
Concrete Works For Third
Th Basement Zone ( 1 )
Installation of columns
column ( B 3 ) ( Z 1 )
Installation of Internal
Interna walls ( B 3 ) ( Z 1 )
Installation of External
Extern walls ( B 3 ) ( Z 1 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 1 )
Concrete Works For Third
Th Basement Zone ( 2 )
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 1 of 30
Finish
-
28-12-25
4
2710
Budgeted Labor udgeted
Units
onlabor-
-
28-12-25
4
2710
321243
4460
-
13-12-22
0
12
2322
3017
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Date
Total Float
Activity
Count
Revision
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 2 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Installation of columns
column ( B 3 ) ( Z 2 )
Installation of Internal
Interna walls ( B 3 ) ( Z 2 )
Installation of External
Extern walls ( B 3 ) ( Z 2 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 2 )
Concrete Works For Third
Th Basement Zone ( 3 )
Installation of columns
column ( B 3 ) ( Z 3 )
Installation of Internal
Interna walls ( B 3 ) ( Z 3 )
Installation of External
Extern walls ( B 3 ) ( Z 3 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 3 )
Concrete Works For Third
Th Basement Zone ( 4 )
Installation of columns
column ( B 3 ) ( Z 4 )
Installation of Internal
Interna walls ( B 3 ) ( Z 4 )
Installation of External
Extern walls ( B 3 ) ( Z 4 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 4 )
Concrete Works For Third
Th Basement Zone ( 5 )
Installation of columns
column ( B 3 ) ( Z 5 )
Installation of Internal
Interna walls ( B 3 ) ( Z 5 )
Installation of External
Extern walls ( B 3 ) ( Z 5 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 5 )
Concrete Works For Third
Th Basement Zone ( 6 ) P1
Installation of columns
column ( B 3 ) ( Z 6 ) P1
Installation of Internal
Interna walls ( B 3 ) ( Z 6 ) P1
Installation of External
Extern walls ( B 3 ) ( Z 6 ) P1
Installation of R.C Slab
Sla ( B 3 ) ( Z 6 ) P1
Concrete Works For Third
Th Basement Zone ( 7 )
Installation of columns
column ( B 3 ) ( Z 7 )
Installation of Internal
Interna walls ( B 3 ) ( Z 7 )
Installation of External
Extern walls ( B 3 ) ( Z 7 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 7 )
Concrete Works For Third
Th Basement Zone ( 8 )
Installation of columns
column ( B 3 ) ( Z 8 )
Installation of Internal
Interna walls ( B 3 ) ( Z 8 )
Installation of External
Extern walls ( B 3 ) ( Z 8 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 8 )
Concrete Works For Third
Th Basement Zone ( 9 )
Installation of columns
column ( B 3 ) ( Z 9 )
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 3 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 4 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Installation of Internal
Interna walls ( B 3 ) ( Z 9 )
Installation of External
Extern walls ( B 3 ) ( Z 9 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 9 )
Concrete Works For Third
Th Basement Zone ( 10 )
Installation of columns
column ( B 3 ) ( Z 10 )
Installation of Internal
Interna walls ( B 3 ) ( Z 10 )
Installation of External
Extern walls ( B 3 ) ( Z 10 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 10 )
Concrete Works For Third
Th Basement Zone ( 11 )
Installation of columns
column ( B 3 ) ( Z 11 )
Installation of Internal
Interna walls ( B 3 ) ( Z 11 )
Installation of R.C Slab
Sla ( B 3 ) ( Z 11 )
Concrete Works For Third
Th Basement Zone ( 12 ) P1
Installation of columns
column ( B 3 ) ( Z 12 ) P1
Installation of Internal
Interna walls ( B 3 ) ( Z 12 ) P1
Installation of External
Extern walls ( B 3 ) ( Z 12 ) P1
Installation of R.C Slab
Sla ( B 3 ) ( Z 12 ) P1
Second Basement Works
Concrete Works For Second
Se
Basement Zone ( 1 )
Installation of columns
column ( B 2 ) ( Z 1 )
Installation of Internal
Interna walls ( B 2 ) ( Z 1 )
Installation of External
Extern walls ( B 2 ) ( Z 1 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 1 )
Concrete Works For Second
Se
Basement Zone ( 2 )
Installation of columns
column ( B 2 ) ( Z 2 )
Installation of Internal
Interna walls ( B 2 ) ( Z 2 )
Installation of External
Extern walls ( B 2 ) ( Z 2 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 2 )
Concrete Works For Second
Se
Basement Zone ( 3 )
Installation of columns
column ( B 2 ) ( Z 3 )
Installation of Internal
Interna walls ( B 2 ) ( Z 3 )
Installation of External
Extern walls ( B 2 ) ( Z 3 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 3 )
Concrete Works For Second
Se
Basement Zone ( 4 )
Installation of columns
column ( B 2 ) ( Z 4 )
Installation of Internal
Interna walls ( B 2 ) ( Z 4 )
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 5 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 6 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Installation of External
Extern walls ( B 2 ) ( Z 4 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 4 )
Concrete Works For Second
Se
Basement Zone ( 5 )
Installation of columns
column ( B 2 ) ( Z 5 )
Installation of Internal
Interna walls ( B 2 ) ( Z 5 )
Installation of External
Extern walls ( B 2 ) ( Z 5 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 5 )
Concrete Works For Second
Se
Basement Zone ( 6 ) P1
Installation of columns
column ( B 2 ) ( Z 6 ) P1
Installation of Internal
Interna walls ( B 2 ) ( Z 6 ) P1
Installation of External
Extern walls ( B 2 ) ( Z 6 ) P1
Installation of R.C Slab
Sla ( B 2 ) ( Z 6 ) P1
Concrete Works For Second
Se
Basement Zone ( 7 )
Installation of columns
column ( B 2 ) ( Z 7 )
Installation of Internal
Interna walls ( B 2 ) ( Z 7 )
Installation of External
Extern walls ( B 2 ) ( Z 7 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 7 )
Concrete Works For Second
Se
Basement Zone ( 8 )
Installation of columns
column ( B 2 ) ( Z 8 )
Installation of Internal
Interna walls ( B 2 ) ( Z 8 )
Installation of External
Extern walls ( B 2 ) ( Z 8 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 8 )
Concrete Works For Second
Se
Basement Zone ( 9 )
Installation of columns
column ( B 2 ) ( Z 9 )
Installation of Internal
Interna walls ( B 2 ) ( Z 9 )
Installation of External
Extern walls ( B 2 ) ( Z 9 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 9 )
Concrete Works For Second
Se
Basement Zone ( 10 )
Installation of columns
column ( B 2 ) ( Z 10 )
Installation of Internal
Interna walls ( B 2 ) ( Z 10 )
Installation of External
Extern walls ( B 2 ) ( Z 10 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 10 )
Concrete Works For Second
Se
Basement Zone ( 11 )
Installation of columns
column ( B 2 ) ( Z 11 )
Installation of Internal
Interna walls ( B 2 ) ( Z 11 )
Installation of R.C Slab
Sla ( B 2 ) ( Z 11 )
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 7 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 8 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Concrete Works For Second
Se
Basement Zone ( 12 ) P1
Installation of columns
column ( B 2 ) ( Z 12 ) P1
Installation of Internal
Interna walls ( B 2 ) ( Z 12 ) P1
Installation of External
Extern walls ( B 2 ) ( Z 12 ) P1
Installation of R.C Slab
Sla ( B 2 ) ( Z 12 ) P1
First Basement Works
Concrete Works For First
Fir Basement Zone ( 1 )
Installation of columns
column ( B 1 ) ( Z 1 )
Installation of Internal
Interna walls ( B 1 ) ( Z 1 )
Installation of External
Extern walls ( B 1 ) ( Z 1 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 1 )
Concrete Works For First
Fir Basement Zone ( 2 )
Installation of columns
column ( B 1 ) ( Z 2 )
Installation of Internal
Interna walls ( B 1 ) ( Z 2 )
Installation of External
Extern walls ( B 1 ) ( Z 2 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 2 )
Concrete Works For First
Fir Basement Zone ( 3 )
Installation of columns
column ( B 1 ) ( Z 3 )
Installation of Internal
Interna walls ( B 1 ) ( Z 3 )
Installation of External
Extern walls ( B 1 ) ( Z 3 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 3 )
Concrete Works For First
Fir Basement Zone ( 4 )
Installation of columns
column ( B 1 ) ( Z 4 )
Installation of Internal
Interna walls ( B 1 ) ( Z 4 )
Installation of External
Extern walls ( B 1 ) ( Z 4 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 4 )
Concrete Works For First
Fir Basement Zone ( 5 )
Installation of columns
column ( B 1 ) ( Z 5 )
Installation of Internal
Interna walls ( B 1 ) ( Z 5 )
Installation of External
Extern walls ( B 1 ) ( Z 5 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 5 )
Concrete Works For First
Fir Basement Zone ( 6 ) P1
Installation of columns
column ( B 1 ) ( Z 6 ) P1
Installation of Internal
Interna walls ( B 1 ) ( Z 6 ) P1
Installation of External
Extern walls ( B 1 ) ( Z 6 ) P1
Installation of R.C Slab
Sla ( B 1 ) ( Z 6 ) P1
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 9 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 10 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Concrete Works For First
Fir Basement Zone ( 7 )
Installation of columns
column ( B 1 ) ( Z 7 )
Installation of Internal
Interna walls ( B 1 ) ( Z 7 )
Installation of External
Extern walls ( B 1 ) ( Z 7 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 7 )
Concrete Works For First
Fir Basement Zone ( 8 )
Installation of columns
column ( B 1 ) ( Z 8 )
Installation of Internal
Interna walls ( B 1 ) ( Z 8 )
Installation of External
Extern walls ( B 1 ) ( Z 8 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 8 )
Concrete Works For First
Fir Basement Zone ( 9 )
Installation of columns
column ( B 1 ) ( Z 9 )
Installation of Internal
Interna walls ( B 1 ) ( Z 9 )
Installation of External
Extern walls ( B 1 ) ( Z 9 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 9 )
Concrete Works For First
Fir Basement Zone ( 10 )
Installation of columns
column ( B 1 ) ( Z 10 )
Installation of Internal
Interna walls ( B 1 ) ( Z 10 )
Installation of External
Extern walls ( B 1 ) ( Z 10 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 10 )
Concrete Works For First
Fir Basement Zone ( 11 )
Installation of columns
column ( B 1 ) ( Z 11 )
Installation of Internal
Interna walls ( B 1 ) ( Z 11 )
Installation of R.C Slab
Sla ( B 1 ) ( Z 11 )
Concrete Works For First
Fir Basement Zone ( 12 ) P1
Installation of columns
column ( B 1 ) ( Z 12 ) P1
Installation of Internal
Interna walls ( B 1 ) ( Z 12 ) P1
Installation of External
Extern walls ( B 1 ) ( Z 12 ) P1
Installation of R.C Slab
Sla ( B 1 ) ( Z 12 ) P1
TEMP. Ramp Works
HDPE
Third Basement
Concrete Works For Third Basement Zone ( 6 ) P2
Concrete Works For Third Basement Zone ( 12 ) P2
Second Basement
Concrete Works For Second Basement Zone ( 6 ) P2
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 11 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 12 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Concrete Works For Second Basement Zone ( 12 ) P2
First Basement
Concrete Works For First Basement Zone ( 6 ) P2
Concrete Works For First Basement Zone ( 12 ) P2
Work for S.O.G
Ground Level Works
Concrete Works For Ground
Gr
Level Northern Zone
Installation of columns
column ( G ) ( N.Z )
Installation of Internal
Interna walls ( G ) ( N.Z )
Installation of R.C Slab
Sla ( G ) ( N.Z )
Concrete Works For Ground
Gr
Level Southern Zone
Installation of columns
column ( G ) ( S.Z )
Installation of Internal
Interna walls ( G ) ( S.Z )
Installation of R.C Slab
Sla ( G ) ( S.Z )
Mezzanine Level Works
Concrete Works For Mezzanine
Me
Level Northern Zone
Installation of columns
column ( M ) ( N.Z )
Installation of Internal
Interna walls ( M ) ( N.Z )
Installation of R.C Slab
Sla ( M ) ( N.Z )
Concrete Works For Mezzanine
Me
Level Southern Zone
Installation of columns
column ( M ) ( S.Z )
Installation of Internal
Interna walls ( M ) ( S.Z )
Installation of R.C Slab
Sla ( M ) ( S.Z )
First Floor Level Works
Concrete Works For First
Fir Floor Northern Zone
Installation of columns
column ( F.F ) ( N.Z )
Installation of Internal
Interna walls ( F.F ) ( N.Z )
Installation of R.C Slab
Sla ( F.F ) ( N.Z )
Concrete Works For First
Fir Floor Southern Zone
Installation of columns
column ( F.F ) ( S.Z )
Installation of Internal
Interna walls ( F.F ) ( S.Z )
Installation of R.C Slab
Sla ( F.F ) ( S.Z )
Steel Works
Second Floor Level Works
Work
Concrete Works For Second
Se
Floor Northern Zone
Installation of columns
column ( S.F ) ( N.Z )
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 13 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 14 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Installation of Internal
Interna walls ( S.F ) ( N.Z )
Installation of R.C Slab
Sla ( S.F ) ( N.Z )
Concrete Works For Second
Se
Floor Southern Zone
Installation of columns
column ( S.F ) ( S.Z )
Installation of Internal
Interna walls ( S.F ) ( S.Z )
Installation of R.C Slab
Sla ( S.F ) ( S.Z )
Steel Works
Third Floor Level Works
Concrete Works For Third
Th
Floor Northern Zone
Installation of columns
column ( 3rd.F ) ( N.Z )
Installation of Internal
Interna walls ( 3rd.F ) ( N.Z )
Installation of R.C Slab
Sla ( 3rd.F ) ( N.Z )
Concrete Works For Third
Th Floor Southern Zone
Installation of columns
column ( 3rd.F ) ( S.Z )
Installation of Internal
Interna walls ( 3rd.F ) ( S.Z )
Installation of R.C Slab
Sla ( 3rd.F ) ( S.Z )
Steel Works
Roof Floor Level Works
Concrete Works For Roof
Ro Floor
Installation of R.C Slab
Sla ( Roof.F )
Work for S.O.G
General Finishing Work
Third Basement finishing W
Works
First Fix Works For Third
Thi Basement
First Fix Works For T
Third Basement Zone (1)
First Fix Works For T
Third Basement Zone (2)
First Fix Works For T
Third Basement Zone (3)
First Fix Works For T
Third Basement Zone (4)
First Fix Works For T
Third Basement Zone (5)
First Fix Works For T
Third Basement Zone (6) P1
First Fix Works For T
Third Basement Zone (7)
First Fix Works For T
Third Basement Zone (8)
First Fix Works For T
Third Basement Zone (9)
First Fix Works For T
Third Basement Zone (10)
First Fix Works For T
Third Basement Zone (11)
First Fix Works For T
Third Basement Zone (12) P1
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 15 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 16 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Finishing Works For Thi
Third Basement (N.Z) P1
Arch Works #B3.#N.Z P1
MEP Works #B3.#N.Z P1
Finishing Works For Thi
Third Basement (S.Z)
Arch Works #B3.#S.Z
MEP Works #B3.#S.Z
Second Basement finishing Works
First Fix Works For Second
Sec
Basement
First Fix Works For S
Second Basement Zone (1)
First Fix Works For S
Second Basement Zone (2)
First Fix Works For S
Second Basement Zone (3)
First Fix Works For S
Second Basement Zone (4)
First Fix Works For S
Second Basement Zone (5)
First Fix Works For S
Second Basement Zone (6) P1
First Fix Works For S
Second Basement Zone (7)
First Fix Works For S
Second Basement Zone (8)
First Fix Works For S
Second Basement Zone (10)
First Fix Works For S
Second Basement Zone (9)
First Fix Works For S
Second Basement Zone (11)
First Fix Works For S
Second Basement Zone (12) P1
Finishing Works For Se
Sec Basement (S.Z)
Arch Works #B2.#S.Z
MEP Works #B2.#S.Z
Finishing Works For Se
Sec Basement (N.Z) P1
Arch Works #B2.#N.Z P1
MEP Works #B2.#N.Z P1
First Basement Finishing W
Works
First Fix Works For Firs
First Basement
First Fix Works For F
First Basement Zone (1)
First Fix Works For F
First Basement Zone (2)
First Fix Works For F
First Basement Zone (3)
First Fix Works For F
First Basement Zone (4)
First Fix Works For F
First Basement Zone (5)
First Fix Works For F
First Basement Zone (6) P1
First Fix Works For F
First Basement Zone (7)
First Fix Works For F
First Basement Zone (8)
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 17 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 18 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
First Fix Works For F
First Basement Zone (9)
First Fix Works For F
First Basement Zone (10)
First Fix Works For F
First Basement Zone (11)
First Fix Works For F
First Basement Zone (12) P1
Finishing Works For Fir
First Basement (S.Z)
Arch Works #B1.#S.Z
MEP Works #B1.#S.Z
Finishing Works For Fir
First Basement (N.Z) P1
Arch Works #B1.#N.Z P1
MEP Works #B1.#N.Z P1
TEMP. Ramp Works
Work for S.O.G P2
Third Basement Works P2
First Fix Works For T
Third Basement P2
Finishing Works For Third Basement (N.Z) P2
Sec Basement Works P2
First Fix Works For S
Second Basement P2
Finishing Works For Sec Basement (N.Z) P2
First Basement Works P
P2
First Fix Works For F
First Basement P2
Finishing Works For First Basement (N.Z) P2
Ground Level Finishing Works
Wo
Finishing Works For Ground
Gro
Floor (S.Z)
First Fix Works For #
#G.F.#S.Z
Arch Works #G.F.#S.Z
#G.F.#S.
MEP Works #G.F.#S.Z
.#S.
Finishing Works For Ground
Gro
Floor (N.Z)
First Fix Works For #
#G.F.#N.Z
Arch Works #G.F.#N.Z
#G.F.#N.
MEP Works #G.F.#N.Z
.#N.
Mezzanine Level Finishing Works
Finishing Works For Mezzanine
Me
Floor (S.Z)
First Fix Works For #
#M.F.#S.Z
Arch Works #M.F.#S.Z
#M.F.#S.
MEP Works #M.F.#S.Z
.#S.
Finishing Works For Mezzanine
Me
Floor (N.Z)
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 19 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 20 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
First Fix Works For #
#M.F.#N.Z
Arch Works #M.F.#N.Z
#M.F.#N.
MEP Works #M.F.#N.Z
.#N.
First Floor Level Finishing Works
Finishing Works For First
Fir Floor (S.Z)
First Fix Works For #
#1st.F.#S.Z
Arch Works #1st.F.#S.Z
#1st.F.#S
MEP Works #1st.F.#S.Z
#1st.F.#S
Finishing Works For First
Fir Floor (N.Z)
First Fix Works For #
#1st.F.#N.Z
Arch Works #1st.F.#N.Z
#1st.F.#N
MEP Works #1st.F.#N.Z
#1st.F.#N
Second Floor Level Finishing
Finish
Works
Finishing Works For Sec
Se Floor (S.Z)
First Fix Works For #
#2nd.F.#S.Z
Arch Works #2nd.F.#S.Z
#2nd.F.#
MEP Works #2nd.F.#S.Z
#2nd.F.#
Finishing Works For Sec
Se Floor (N.Z)
First Fix Works For #
#2nd.F.#N.Z
Arch Works #2nd.F.#N.Z
#2nd.F.#
MEP Works #2nd.F.#N.Z
#2nd.F.#
Third Floor Level Finishing Works
Finishing Works For Third
Thi Floor (S.Z)
First Fix Works For #
#3rd.F.#S.Z
Arch Works #3rd.F.#S.Z
#3rd.F.#S
MEP Works #3rd.F.#S.Z
#3rd.F.#S
Finishing Works For Third
Thi Floor (N.Z)
First Fix Works For #
#3rd.F.#N.Z
Arch Works #3rd.F.#N.Z
#3rd.F.#N
MEP Works #3rd.F.#N.Z
#3rd.F.#N
Roof Floor Level Finishing Works
Finishing Works For Roof
Ro Floor
First Fix Works For #
#R.F.
Arch Works #R.F.
MEP Works #R.F
Work for S.O.G P1
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 21 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 22 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration
Basements Roads Finishing
Finishin
EGPC Building Phase ( 3 ) wor
works
General Finishing Work
Third Basement finishing W
Works
Finishing Works For Thi
Third Basement (S.Z)
Arch Works #B3.#S.Z
MEP Works #B3.#S.Z
Finishing Works For Thi
Third Basement (N.Z)
Arch Works #B3.#N.Z
MEP Works #B3.#N.Z
Elec. Systems For Third Basment
General Systems For Third Basment
Ligth Current Systems
System For Third Basment
Second Basement finishing Works
Finishing Works For Se
Sec Basement (S.Z)
Arch Works #B2.#S.Z
MEP Works #B2.#S.Z
Finishing Works For Se
Sec Basement (N.Z)
Arch Works #B2.#N.Z
MEP Works #B2.#N.Z
Elec. Systems For Sec B
Basment
General Systems For Sec Basment
Ligth Current Systems
System For Sec Basment
First Basement Finishing W
Works
Finishing Works For Fir
First Basement (S.Z)
Arch Works #B1.#S.Z
MEP Works #B1.#S.Z
Finishing Works For Fir
First Basement (N.Z)
Arch Works #B1.#N.Z
MEP Works #B1.#N.Z
Elec. Systems For First Basment
General Systems For First Basment
Ligth Current Systems
System For First Basment
Ground Level Finishing Works
Wo
Finishing Works For Ground
Gro
Floor (S.Z)
Arch Works #G.F.#S.Z
#G.F.#S.
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 23 of 30
-
-
2
4
3
1645
Budgeted Labor udgeted
Units
onlabor-
-
-
-
-
-
-
Finish
Date
Total Float
Activity
Count
Revision
-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 24 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
MEP Works #G.F.#S.Z
.#S.
Finishing Works For Ground
Gro
Floor (N.Z)
Arch Works #G.F.#N.Z
#G.F.#N.
MEP Works #G.F.#N.Z
.#N.
Elec. Systems For Grou
Ground Floor
General Systems For Ground Floor
Ligth Current Systems
System For Ground Floor
Mezzanine Level Finishing Works
Finishing Works For Mezzanine
Me
Floor (S.Z)
Arch Works #M.F.#S.Z
#M.F.#S.
MEP Works #M.F.#S.Z
.#S.
Finishing Works For Mezzanine
Me
Floor (N.Z)
Arch Works #M.F.#N.Z
#M.F.#N.
MEP Works #M.F.#N.Z
.#N.
Elec. Systems For Mezz
Mezzanine Floor
General Systems For Mezzanine Floor
Ligth Current Systems
System For Mezzanine Floor
First Floor Level Finishing Works
Finishing Works For First
Fir Floor (S.Z)
Arch Works #1st.F.#S.Z
#1st.F.#S
MEP Works #1st.F.#S.Z
#1st.F.#S
Finishing Works For First
Fir Floor (N.Z)
Arch Works #1st.F.#N.Z
#1st.F.#N
MEP Works #1st.F.#N.Z
#1st.F.#N
Elec. Systems For First Floor
General Systems For First Floor
Ligth Current Systems
System For First Floor
Second Floor Level Finishing
Finish
Works
Finishing Works For Sec
Se Floor (S.Z)
Arch Works #2nd.F.#S.Z
#2nd.F.#
MEP Works #2nd.F.#S.Z
#2nd.F.#
Finishing Works For Sec
Se Floor (N.Z)
Arch Works #2nd.F.#N.Z
#2nd.F.#
MEP Works #2nd.F.#N.Z
#2nd.F.#
Elec. Systems For Sec F
Floor
General Systems For Sec Floor
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 25 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 26 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Ligth Current Systems
System For Sec Floor
Third Floor Level Finishing Works
Finishing Works For Third
Thi Floor (S.Z)
Arch Works #3rd.F.#S.Z
#3rd.F.#S
MEP Works #3rd.F.#S.Z
#3rd.F.#S
Finishing Works For Third
Thi Floor (N.Z)
Arch Works #3rd.F.#N.Z
#3rd.F.#N
MEP Works #3rd.F.#N.Z
#3rd.F.#N
Elec. Systems For Third Floor
General Systems For Third Floor
Ligth Current Systems
System For Third Floor
Roof Floor Level Finishing Works
Finishing Works For Roof
Ro Floor
Arch Works #R.F.
MEP Works #R.F
Elec. Systems For Roof Floor
General Systems For Roof Floor
Ligth Current Systems
System For Roof Floor
Installation Of External & In
Internal Facades
Conving System For Bulding
Buldin
FURNITURE Works
Overhead Crane Works
Basements Roads Finishing
Finishin
General Elec. Works For All B
Bulding
Generators Works
R.M.U Pannals
M.V Switch Pannals
UPS System Works
KNX System
Lighting Protection System
M.V Transformar
Earthing Electrical System Works
General External Works
Landscape Work
Utilities Buildings
Irrigation Work
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 27 of 30
-
Finish-
Date
Total Float
Activity
Count
-
-
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
-
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 28 of 30
Date
Revision
Checked Approved
Work Sample
Activity ID
Activity Name
Original Start
Duration-
Fountain Works
Plumbing Works
Fence
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 29 of 30
Finish-
Date
Total Float
Activity
Count
14
16
37
11
3
13
Revision
Budgeted Labor udgeted
Units
onlabor-
Checked Approved
Work Sample
ted Nonlabor
Units
June 2022
July 2022
25
02
0
0
240
Actual Work
Critical Remaining Work
Remaining Work
Milestone
Page 30 of 30