Project Management
Profit Strategies
SARC 362
Samuel Pendreigh
6-9-2017
Contents
1.0 Objectives.................................................................................................................................... 1
2.0 Initial Profit Calculations .............................................................................................................. 1
3.0 Estimation and Scheduling the Job ............................................................................................... 2
3.1 Change Orders ......................................................................................................................... 2
3.2 Construction Phases ................................................................................................................ 2
3.2.1 Application in Project ........................................................................................................ 3
4.0 Workforce Investment ................................................................................................................. 3
4.1 BIM .......................................................................................................................................... 3
5.0 Vendors, Tenders and Key Resources ........................................................................................... 3
5.1 Early Pay Discounts .................................................................................................................. 3
5.1.1 Application in project ........................................................................................................ 3
5.2 Higher Pay Discounts ............................................................................................................... 4
6.0 Managing Equipment and Inventory ............................................................................................ 4
6.1 Buy for the Job, Not for Inventory ............................................................................................ 4
6.1.1 Application in Project ........................................................................................................ 4
7.0 Accounting and Finance ............................................................................................................... 5
7.1 Embezzlement ......................................................................................................................... 5
7.2 Overhead and Profit................................................................................................................. 5
7.2.1 Application in the Project .................................................................................................. 5
7.3 Retention ................................................................................................................................. 5
7.3.1 Application in Project ........................................................................................................ 6
8.0 Sales Analysis............................................................................................................................... 6
9.0 Investment .................................................................................................................................. 6
10.0 Individual Present Value Profit ................................................................................................... 7
11.0 References................................................................................................................................. 7
12.0 Appendices ................................................................................................................................ 9
See brief for improvement examples
1.0 Objectives
The following report assess general economic construction strategies in methods In hopes of
increasing initial project profit by 20%. Concepts and strategies revolve around the concept of value
engineering which looks to increase value by either improving function or lowering the cost.
2.0 Initial Profit Calculations
The initial construction calculations and profit of the project are as follows;
Description of Sum
Income
Apartments
Penthouses
10 year Retail Lease
Final Construction Costs
Residential
Retail
Hospitality
General
Fees, Tax, Inflation & Site Cost
Net Profit Value
Amount
$47,075,904.34
$28,080,000.00
$5,400,000.00
$10,682,305.51
$43,843,437.25
$16,327,020.00
$2,534,475.00
$1,797,500.00
$3,917,912.35
$20,143,291.75
$3,028,665.24
3.0 Estimation and Scheduling the Job
The construction will take 25months. This was concluded after a previous job of a similar
construction of 7200m2 took 16months to complete. We can say that this was completed at a rate of
450m2 per month. Our final construction was 11,250m 2. If this same rate is applied we will finish at
the end of 25 months.
3.1 Change Orders
Charging fees for change orders could potentially be utilized. Doing this would reduce the
attractiveness of changing un-important items which would essentially speed up the construction
phase. This is due to less time needing to be dedicated to re-scheduling construction phases which
would be changed by change orders. Fees would be small enough not to stop essential change
orders such as ones relating to structure but large enough to stop orders such as specification of
light bulbs (Sage Software).
3.2 Construction Phases
During the initial proposal sale of units did not occur during construction which meant that the
development was at a negative ROI during the total construction. By adapting the construction
phases and starting to sell units during the 25months we were able to generate an average ROI of
still only -7.2% due to a NPV of -$15,636,973. However after 10 years of rent and taking account of
rising inflation of prices this was increased to 18.69% ROI
When planning the construction phases it was decided to complete each module singularly and to
not multi-task on any as by doing so average organizations can see a 27.5% drop in productivity and
a rise in 32% of labour costs (Realization). Phases were split into the following;
CP1 – Marketing
CP2 – Carpark
CP3 – West Block
CP4 – Landscape
CP5 – East Block
CP6 - Tavern
A DCF (discount cash flow) was created to simulate economic performance during the phases and
show where possible improvements could be made.
CP3 (construction phase 3) – West Block was analysed as having the potential to improve profit
through being able to compete construction quicker. This Block held most of the retail stores and
48% of the units. By completing construction earlier the developer would be able to sell and lease
the available spaces earlier and hence break even on their investment earlier too. The phase was
initially was estimated to take 8 months in total and spend a total of $1,065,942.50 per month. By
using a project management strategy such as crashing this process could be reduced to 6 months at
best. This process works by reviewing the critical path and seeing which activities can be completed
earlier through adding extra resources (Usmani).
3.2.1 Application in Project
Through using this method an extra $500,000 was invested over 6 months which increased
construction costs over those 6 months to $1,149,275.83. Although this initially increased
construction costs it ended up saving $1,631,885.00 which could either be invested elsewhere in the
project or invested conservatively. In terms of a percentage this will increase construction profit by
6.8%.
On top of this the completion of the block two months early will guarantee 2 extra months of the
retail lease income for the 6 stores which are located in that block which will wind up to be
$46,704.52 per month, $93,409.05 in total, and 0.4% of the total cost if not chosen to invest back
into construction immediately.
4.0 Workforce Investment
4.1 BIM
By investing in your work force you can reduce communication delays and hence work force hours
(Sage Software). In a past case study the engineering company “GHD” included automated
construction systems which eliminated paper hardcopies and 800 staff hours for a 42million USD (58
million NZD) project in Guam (GHD) (Bentley Systems Inc). If this is applied to our project at a similar
rate of 1 hour being equal to $72,500 then we could potentially reduce administrative staff hours by
600 hours. A typical hourly rate in NZ is $27.76 (ENZ) which calculates out to being approximately
$16,656 or a decrease of 0.07% of initial construction costs.
5.0 Vendors, Tenders and Key Resources
5.1 Early Pay Discounts
By finding vendors who offer 1% - 2% early pay discounts for materials the project could potentially
generate an “annualized income” of 18% - 36% per year through interest. This concept would work
by paying the vendor 10 days in advance compared to 30 meaning that by loaning a vendor your
money for 20 days a continuous bonus could be generated every 20 days in terms of interest on the
loan as exchange for guaranteeing them purchase of their product and paying before the due date
(Sage Software);
((365 days / 20 days) x 1% - 2%) = 18.25% - 36.5%
5.1.1 Application in project
Expenses were calculated through use of the elemental costs supplied by Rawlinson’s 2012
(Rawlinsons). Elemental costs work through providing a general percentage of costs of the total cost
for certain elements such as structure or drainage. If for the following calculations we say, as general
rule of thumb, that 35% of these elemental costs are associated with labour costs and the rest
associated with materials will be 65% which is where savings could be seen (Gichui).
The following table simulates cost decrease(s) for the most expensive materials used in the
development if an early pay discount was utilized for 1 year.
The element costs below are the sum of the total of Retail, Hospitality and Residential cost.
Material
Element
Elemental
Cost
Material Cost
Lower Yield Limit
Early Pay Discount
Roof
Exterior Walls
Electrical
Services
Mechanical
Services
Floor Finishes
Sanitary
Plumbing
$537,133.87
$991,565.16
$1,004,299.23
$349,137.02
$644,517.35
$652,794.50
$63,717.51
$117,624.42
$119,135.00
Higher Yield
Limit
Early Pay
Discount
$127,435.01
$235,248.83
$238,269.99
$947,506.39
$615,879.15
$112,397.95
$224,795.89
$779,544.73
$1,897,342.99
$506,704.07
$1,233,272.94
$92,473.49
$225,072.31
$184,946.99
$450,144.62
Total
$730,420.67
Total
Higher Yield
Lower Yield
Initial Cost (non-tax
and fee inclusive)
$23,903,947.35
$23,903,947.35
Cost After Early Pay
Discount
$22,443,106.01
$23,173,526.68
$1,460,841.34
Percentage Change
6.1%
3.05%
Discount on materials, if an early discount is given, will range from 3.05% - 6.1% of the Total Costs
(not including inflation or fees).
5.2 Higher Pay Discounts
If the above is achieved you may potentially be liable to negotiate higher discount rates with
suppliers and subcontractors than the ones stated above in return for earlier pay. The same Method
of Pay Discount would be achieved but just at a higher rate such as 3 – 5% per early pay.
6.0 Managing Equipment and Inventory
6.1 Buy for the Job, Not for Inventory
Construction companies usually stock inventory with more materials than need. This can prove cost
ineffective as if the materials are not used within a certain time period they can depreciate in value
and become inoperative during that period due to better versions or options of inventory being
released (Sage Software). By employing a QS (quantity surveyor) or someone who is able to monitor
your inventory your initial investment will create return from wastage.
6.1.1 Application in Project
A QS can decrease wastage and improve the value of a project by approximately 3% (Hiew). In the
case of this project our materials cost was 65% of the total elemental cost which works out to be
$16,102,285.78. 3% savings of this figure equates to $483,068.57 which is approximately 2% of the
total construction costs.
7.0 Accounting and Finance
7.1 Embezzlement
Embezzlement or theft, misappropriation of funds is not uncommon to see in construction business
and can end up costing investors large amounts of their investment. Buy initially employing someone
other than a book keeper to handle deposits you can lower the risk of this occurring (Sage Software).
By providing an initial investment in the form of the cost to employee someone to do this you could
ensure a positive ROI.
Although this is not as common in New Zealand as in other countries it is not an essential strategy to
be consider first although would be worth taking action on with clients you are new to dealing with
or higher risk projects due to the risk and greater chance of embezzlement occurring.
7.2 Overhead and Profit
Ensure that contractors profit and overhead is calculated as one figure instead of calculating
overhead and then profit separately. By ensuring this you could save additional 1% per contractor of
what you owe them;
Situation 1: $100 x 20% (10% Overhead + 10% Profit) = $20
Situation 2: $100 x 10% (10% Overhead) = $10; $110 (Job cost including Overhead) x 10% (Profit) =
$11 $11 + $10 = $21 owed to worker.
7.2.1 Application in the Project
As stated before 35% of Elemental costs are associated with labour fees. On a project of this
magnitude you would expect 260 workers to be involved over the 25month span. This was based off
a past case which used 39 workers to complete a project over 4 months to which I added 20 workers
to make up for the retail and increased technicality in terms of services (Plumbers).
If total construction costs are $23,650,191.32 then 35% of that, $8,277,566, will labour costs. If we
assume all workers are paid equally then from this job that should be receiving $31,836.80 which
includes mark-up for profit. If overhead and profit is calculated together this would be increased
$6,367.36 compared to increases of $9,869.40 which for 260 workers turns out to be $2,566,044.00
for the whole project, or 12% of total construction costs.
If Overhead and Profit is not calculated as one figure ensure that contractor keep overhead at a low
percentage
7.3 Retention
Retention, or a performance bond, of a construction project is normally about 5% and is essentially a
down payment held in security to ensure performance of the contractor which is usually returned
after the project is complete (Retention in Construction Projects). By reducing this cost on large scale
projects from 5% to 0-2% extra money could be freed up during the project. This move would need
to me assessed using risk matrixes as it could lead to a risker project due to contractors not ensuring
performance. However in some cases collection of retention money does not always happens,
therefore by not providing it in the first place it could be seen as a positively economic choice.
If Retention is collected it could be held in a separate bank account and used to invest or buy shares
in certain products as to then sell after a period of time and then gain profit.
7.3.1 Application in Project
Currently the performance bond sits at 5% of the “Total Costs” (See Appendices – Figure 1) which is
$1,195,197.36. If this is reduce to 2% the project will be able to gain $717,118.41 or 3% of the total
budget.
8.0 Sales Analysis
Initially the apartment units were sold at a rate of $520,000. This figure took into consideration
distance from the CBD, Floor area,
Amenities and Current Competition
which were all researched in the initial
market research of the area as to
create a competitive and affordable
product. Currently Wellington region
house prices are averaging a value of
$600,000 (Stuff). After further analysis
this price, $520,000, could essentially
be increased to an upper limit of
$535,000 and still be competitive and
affordable for a couple (See Figure 2)
due to the average savings being
$65,000 which is more than the
average yearly income for an individual
of the Wellington region, $49,192
(Wellington facts & figures).
Figure 2: Affordability Measure of a Mortgage
This increase in price would create a
gain in profit of $810,000 which could
then be invested in other projects or
used to speed up other construction
phases close to the critical path
through crashing (Usmani).
9.0 Investment
Over the course of the construction project these indicated savings will be invested conservatively
into a trust account with a minimum credit rating of a BB+. Over a 2 year period a 3.9% return per
anum is expected which should increase our savings from $7,778,021.96 to $8,093,294.44 (Term
Deposits).
Area of Increased Profit
Rent
Work Force
Construction Phases
Early Paid Discounts
Managing Inventory
Over Head
Retention
Sales Analysis
Saving
$93,409.05
$16,656.00
$1,631,885.00
$1,460,841.34
$483,068.57
$2,566,044.00
$717,118.00
$810,000.00
Return over 2 Year Investment
TOTAL
$7,779,021.96
$8,093,294.44
10.0 Individual Present Value Profit
By analysing the DCF and then certain profit strategies I have found to increase the profit compared
to the previous group profit by 81.5%. What was required initially in terms of increasing profit was
20% of the group profit which ends up being $605,733.05. This situation is based off a positive
situation where all profit strategies could be utilized. In more realistic situations you may only be
able to utilize 1 – 3 of these methods at best due to constraints of the project which would mean
that you may only be able to in fact generate 20% of your initial profit.
Profit Comparison
$9,000,000.00
$8,093,294.44
$8,000,000.00
$7,000,000.00
$6,000,000.00
$5,000,000.00
$4,000,000.00
$3,028,665.25
$3,000,000.00
$1,176,621.00
$2,000,000.00
$1,000,000.00
$Indiviudal
Group
Developer
11.0 References
Bentley Systems Inc, Tech Talk: 3 Ways to Increase construction Profits, YouTube, 17/02/2017
< https://www.youtube.com/watch?v=nQyg0AXQjIA >
ENZ, New Zealand Average Hourly earnings March 2017, Salaries and Wages in New Zealand, 2017
< https://www.enz.org/new-zealand-salaries.html >
GHD, Ordot Dump Closure, GHD Inc, Bentley, 2016
< https://www.bentley.com/en/project-profiles/ghd_ordot-dump >
Gichuhi. Francis, Percentage of Cost Breakdown Between Labour, Materials and Contractor Profit in
Construction, a4architect, 26/04/2013
< http://www.a4architect.com/2013/04/percentage-of-cost-breakdown-between-labour-materialsand-contractor-profit-in-construction/ >
Hiew. Hubert, How the QS Can Create Values in the Procurement of Construction Works in Hong
Kong, 2007
<
https://www.fig.net/resources/proceedings/fig_proceedings/fig2007/papers/ts_5g/ts05g_04_hiew_
lee_1665.pdf >
Sage Software, 101 Practical Strategies to Help Make Your Construction Business More Profitable.
Sage Master Builder, 2006
< http://www.synergy-group.com.au/downloads-synergy-information-systems/101-Ways-toIncrease-Your-Construction-Profits.pdf >
Term deposits 1 to 5 years, interest.co.nz, 2017
< http://www.interest.co.nz/saving/term-deposits-1-to-5-years >
Plumbers Disposal Service, The Average Number of Workes Involved on a Construction Site, Plumber
Disposal Serivce
< http://www.plummersdisposal.com/michigan/pdf/new-loss_revenuAvg_numb_workers_construction_site.aspx >
Rawlinson’s, Rawlinson’s New Zealand Construction Handbook, 26th Edition, 2012
Retention in Construction Projects, Designing Buildings Wiki, 06/01/2017
< https://www.designingbuildings.co.uk/wiki/Retention_in_construction_contracts >
Realization, The Effects of Multitasking on Organizations
< http://www.realization.com/pdf/Effects_of_Multitasking_on_Organizations.pdf >
Stuff, Average house price hits $600,000 across Wellington region, Stuff, 03/05/2017
< http://www.stuff.co.nz/dominion-post/news/-/average-house-price-hits-600000-acrosswellington-region >
Usmani. Fahad, Fast Tracking and Crashing – Schedule Compression Techniques in Time
Management, pmstudycircle, 2012
< https://pmstudycircle.com/2012/09/fast-tracking-crashing-schedule-compression-techniques-intime-management/ >
Wellington facts & figures, Wellington, 2017
< https://www.wellingtonnz.com/life-in-wellington/facts-and-figures/ >
12.0 Appendices
Figure 1: Detailed Profit Calculation of Project