Project Proposal: Philippine Water Utility Scoping Study
Background
A scoping study on the Philippine water utility has to be undertaken to determine the technical
assistance and financing needs of selected water utilities. Findings of the study will aid in providing direction
as to the assistance that should be extended to water utilities that can uplift the poor state of the water
supply sector.
Studies on the Philippine water sector showed that the water needs of the population has not been
met and many poor households remained unconnected to water supply systems despite the fact that the
Philippines is endowed with abundant water resources. The access of the population to water supply
services and sanitation facilities even declined due to rapid population growth, economic development,
urbanization, and industrialization. According to the National Economic and Development Authority
(NEDA)1, the water sector’s failure to meet the water needs of the population are due to the fragmented
institutional environment, weak regulatory framework, inadequate support for service providers and utilities,
lack of access to financing and investments, low levels of tariffs and cost recovery, and lack of technical
and managerial capacity. These resulted to slow capacity expansion, low quality of services and inefficient
operations of water utilities.
There is no national government department or an apex body that has overall responsibility for
water sector policy and coordination. No specific government agency is tasked to prioritize investment on
water and sanitation. Water supply investments of the government remained significantly low relative to
overall public infrastructure spending.
The poor performance of many water utilities is due to limited access to affordable long-term
investment capital that impedes the ability of water utilities to expand and improve services. Many small
public sector water service providers (water districts and LGU-run water utilities) are suffering from low
profitability, high levels of non-revenue water, weak institutional capacity, and limited technical capacity.
Water districts do not receive subsidies from local government units (LGUs) and are compelled to generate
enough income to cover operating and maintenance costs, debt service, and essential capital expenditure.
Economies of scale is an issue as the Local Water Utilities Administration (LWUA) reported that more than
half of the 502 operational water districts in 2011 had less than 3,000 service connections.
Many LGUs have also shown little interest in pursuing water supply projects due to local leadership
uncertainties brought about by the three-year electoral terms. If ever the LGU decided to establish a water
supply project, there is an observed absence of commercial practices in most LGU-run water utilities and
lack of ability to service loans. In 2005, a World Bank study assessed that water utilities under direct LGU
management are poorly operated because of the lack of technical, financial, and management capabilities
at the local level.
The performance of community-managed systems is also constrained by a lack of technical and
management capabilities, although less pronounced than in LGU-run utilities. In the 2005 benchmarking
study funded by the World Bank’s Water and Sanitation Program, the Rural Waterworks and Sanitation
Associations (RWSAs), cooperatives, and private operators were found to generally perform better than
LGU-run water utilities.
The government remains the major source of grant or debt financing for water districts and LGUs
through the LWUA and the Municipal Development Fund Office, but both have limited funds or capacity.
1 NEDA, The Philippine Water Supply Sector Roadmap, 2nd Edition, 2013
Objectives
To gather information about the technical assistance and financing needs of a sample of water
utilities in the Philippines;
To improve the internal systems of the water utilities such as billing system, inventory control,
business planning and financial management;
To determine the needs of utilities for technical assistance and for financing to repair, improve,
upgrade and expand their water and sewage facilities, including treatment plants, conveyance pipes,
water tanks, meters, control valves and distribution lines;
To identify the obstacles, hindrances or reasons why the utilities are not able to obtain the technical
assistance and financing that they need;
To identify some solutions to overcome the obstacles and hindrances.
Scope
The project will undergo the following phases:
Phase 1: Establishment of a data base
Past studies on the water sector were limited by lack of up-to-date, integrated, harmonized, and
comprehensive data on the water sector. There is also no validated statistics for Level III (water piped into
private premises) water service providers (WSPs). There are also no comprehensive sector statistics on
water distribution service levels and quality among WSPs. Thus it is necessary to undertake the following
steps to establish data base for the surveys:
1. Only the list of water districts is available from the Water Districts Directory of the LWUA. The
directory provides the address, telephone number, name of the General Manager and e-mail
address. Classification of water district is not available. Fieldwork to LWUA is necessary to
gather information on classification of the water district and what other information are available
for the study.
2. Fieldwork to NEDA is also necessary to check if the updated and reliable data on water supply
and sanitation provision, including access and coverage, has been gathered and made available
for public use
3. Fieldwork to the Department of Interior and Local Government to check for the list of LGUs that
established their own water utility. Otherwise, the research team will check the website of each
selected LGUs.
4. There is no comprehensive information on the private sector undergoing water projects. These
have to be searched from NEDA or the internet.
5. Majority of the RWSAs are not registered with the National Water Resources Board nor are they
attached to a national agency. Source of this information has to be searched.
Phase 2: Selection of water utilities that will be included in the Mail Survey and Utility Managers
Interview
1. For the Mail survey, 160 water districts will be selected from the Water Districts Directory of the
LWUA that belong to class B, C and D and; 160 LGU-run water utilities, 40 private water
operators; and 40 Rural Water Supply Associations (RWSAs) from the existing 500 RWSAs and
also water service cooperatives. All of these water utilities should be located in towns and cities
with at least 30,000 population based on the Census of Population by cities and towns. The
Water Districts directory contains the addresses of the water districts and the names of their
General Manager.
2. For the Utility Managers Interview, 48 water districts will be selected from the Water Districts
Directory of the LWUA that belong to class B, C and D; 48 LGU-run water utilities; 12 private
water operators; and 12 RWSAs and water service cooperatives. The Water Districts Directory
has the name, email, and telephone number of the General Manager as well as the website of
some WDs.
Phase 3: Develop the detailed questions the Mail Survey and formulate the Interview Guide for
the Utility Manager Interview. Then produce detailed draft questionnaire for the Mail Survey
and for the Utility Manager Interviews.
Phase 4: Conduct of Mail Survey and Utility Manager Interview after field tests.
Phase 5: Process all collected data and analyze the results of the Mail Survey and the Utility
Manager Interviews and come up with observations of trends or common facts.
Phase 6: Presentation of Results
Timeframe
Description of Work
Start and End Dates
Phase 1
Establishment of a data base
June 2019
Phase 2
Selection of water utilities that
will be included in the Mail
Survey and Utility Managers
Interview
Develop the questionnaire for
the Mail Survey and the
Interview Guide for the Utility
Manager Interview
Conduct of Mail Survey and
Utility Manager Interview
Process all collected data and
analyze the results
Presentation of results
June 2019
Phase 3
Phase 4
Phase 5
Phase 6
July 2019
July 2019
August 2019
September 2019
Project Budget
Description of Work
Phase One
Phase Two
Phase Three
Anticipated Costs
…
…
…
…
Total
$ 0.00
Key Stakeholders
Client
Sponsor
Project manager
[name]
[name]
[name]
Monitoring and Evaluation
[Describe how progress will be evaluated throughout and at the end of the project. Formulate clear
indicators for objectives and result.]
Approval Signatures
[Name], Project Client
[Name], Project Sponsor
[Name], Project Manager