Sample Weekly Project Status Report
Weekly Status Report
(Date)
afdigital.com |-
Agenda
1.
Summary of Tasks, Action Items and
Next Steps
2.
Review of Budget Utilisation
3.
TeamX Process Review
4.
Important Links and Key Dates
Jira board
DX and
What We’ve Done
●
●
●
●
●
●
Project Kickoff on 16-Feb
StoreConnect Discovery Call on 23-Feb
DX Workshop on 23-Feb
Pardot health check recommendations (AFD) on 9-Mar
StoreConnect requirements & user stories (AFD)
Digital Marketing Platform access (reinteractive)
What We’re Doing
●
●
●
●
●
StoreConnect Blueprint (AFD) - ongoing review
Campaign & content calendar (AFD)
Monthly newsletter (AFD & reinteractive)
YouTube article series (AFD)
Pardot health check doc review (AFD)
Platinum
Next Steps:
●
●
●
●
●
DX workshop playback (AFD)
Digital advertising strategy (AFD)
LinkedIn prospecting strategy (AFD)
Team spotlight series strategy (AFD)
Heroku App workshop webinar (AFD)
Action Items:
✓
✓
✓
✓
❏
Schedule call with Monique and Gavin to run through the
Monthly Newsletter content (AFD) -> initiated by Tom
Schedule the Heroku App workshop webinar (AFD) ->
scheduled next week, 3/23
Move the weekly status call to an earlier time (AFD) ->
moved to every Friday, 10:45am SYD time
Schedule an internal call with Jeremy to gather feedback for
StoreConnect blueprint review, so the Dev team can start
working on the StoreConnect user stories (AFD) ->
scheduled next week, 3/22
Add budget burn for StoreConnect work in succeeding
status reports (AFD) -> to reflect in succeeding reports once
actual work have started
Agenda
1.
Summary of Tasks, Action Items and
Next Steps
2.
Review of Budget Utilisation
3.
TeamX Process Review
4.
Important Links and Key Dates
Review of Budget Utilisation
TeamX Platinum Starting Budget
$ AUD 120,000.00
Budget Used Last Week
$ AUD 1,497.72
Total Budget Used (as of 11-Mar)
$ AUD 5,263.02
Total Budget Remaining
$ AUD 114,736.98
Budget Report here.
Budget Utilisation per Week
*report based on “week start date”
Budget Report here.
Budget Utilisation per Month
*Will show succeeding months as data becomes available
Budget Report here.
Agenda
1.
Summary of Tasks, Action Items and
Next Steps
2.
Review of Budget Utilisation
3.
TeamX Process Review
4.
Important Links and Key Dates
Streamlined TeamX Process
1
CLIENT
Send task request to-Or add in our Jira board
2
PROJECT
MANAGER
Analyse and assign Task*
*If Task is >1 hour - subject to Client Approval
3
CONSULTANT
Execute and Test
4
PROJECT
MANAGER
Asks for client’s feedback & Finalise
Task
Agenda
1.
Summary of Tasks, Action Items and
Next Steps
2.
Review of Budget Utilisation
3.
TeamX Process Review
4.
Important Links and Key Dates
Important Links
Project Tools
Link
JIRA Board
https://afdigital.atlassian.net/jira/software/projects/RDTX/boards/174
Miro board
https://miro.com/app/board/uXjVOMrCPYE=/?invite_link_id=-
Key Dates
Date/s
Event
Who
Contingency/Notes
3 Mar - 11 Mar
Annual Leave/s + Training
Cam Tait
Built into timeline.
4-Mar, 11-Mar
Annual Leave/s
JR Gelpe
Built into timeline.
25 Apr - 29 Apr
Annual Leave/s
Kimi Buenafe
Built into timeline.
14-15 Apr
Public Holidays (PH):
Maundy Thursday, Good Friday
Global Delivery
Centre
Built into timeline. AU team is BAU
14 Mar
Public Holidays (AU):
Adelaide Cup Day/Labour Day
AU Team
SA/VIC only. Build into timeline.
AU/GDC is BAU.
15-Apr, 18, Apr, 25-Apr
Public Holidays (AU):
Good Friday, Easter Monday, Anzac Day
AU Team
Built into timeline. GDC is BAU
Questions?