Asphalt Plant Economics
Pre-Feasibility Report
(ASPHALT PLANT)
January 2021
Pre-Feasibility Report
Asphalt Plant
Table of Contents
1
EXECUTIVE SUMMARY............................................................................................................................. 1
2
BACKGROUND…………………. .................................................................................................................... 2
3
PROJECT PROFILE...................................................................................................................................-
4
OPPORTUNITY RATIONALE .......................................................................................................................
PROJECT BRIEF..........................................................................................................................................
PROPOSED BUSINESS LEGAL STATUS........................................................................................................
PROJECT CAPACITY AND RATIONALE........................................................................................................
3.4
3.4.1 Raw Material Sourcing
2
3
3
3
3
PRODUCTION PROCESS ……..................................................................................................................
The Manufacturing Process …...............................................................................................................
4.1
4.1.1 Plant Diagram
RAW MATERIAL REQUIREMENT…………….............................................................................................
4.2.1 BITUMEN
4.2
4.2.2 AGGREGATE
4.2.3 DIESEL/ FUEL
3
-
5.2
-
9
PLANT & MACHINARY REQUIREMENT................................................................................................ 6
PLANT & BMACHNERY MAINTENANCE ……………………………..…………… ................................................ 7
VEHICLE FOR SUPPORT AND MAINTENANCE SERIVES………………………………………………………..…………. 7
LAND & BUILDING REQUIRMENT......................................................................................................... 7
5.1
8
4
5
5
5
5
SITE DEVLOPMENT………………………………………………………………………………………………………………………… 7
LAND & BUILDING REQUIREMENT...................................................................................................... 7
5.2.1 SELECTING A SITE
7
5.2.2 ESTABLISHING THE SITE
7
5.2.2.1 AGGREGATE STORAGE
7
5.2.2 .2 BITUMEN STORAGE
8
5.2.2.3 PRODUCDTION AREA
8
5.2.2.4 CONSTRUCTION OF FOUNDATION
8
HUMAN RESOURCE REQUIREMENT.................................................................................................... 8
FINANCIAL ANALYSIS & KEY ASSUMPTINS……………………………………………………………………………………. 9
LAND AND BUILDING ………………………………………………………………………………………………………………….. 9
FURNITURE AND FIXTURE……………………………………………………………………………………………………………. 9
DEPRICEIATION TREATMENT………………………………………………………………………………………………...
10
PROJECT INVESTMENT DETAILS…………………………………………………………………………………………..
10
PROJECT OVERHEAD DETAILS……………………………………………………………………………………………..
10
SELLING & DISTRIBUTION EXPENSES……………………………………………………………………………………………. 10
MISCELLANEOUS EXPENSES…………………………………………………………………………………………………………. 10
REVENUE PROJECTION ………………………………………………………………………………………………………………. 11
11
ACCOUNT RECEIVABLES………………….………………………………………………………………………………..
SOURCE OF CAPITAL…………………………………………………………………………………………………………………… 11
OWNER’S WITHDRAWAL…………………………………………………………………………………………………………….. 11
ESTIMATED PLANT PRODUCTION……................................................................................................ 11
ESTIMATED REVNUE …...................................................................................................................... 12
ESTIMATED COST OF SLAES, RAW MATERIAL PROCUREMENT & RAW MATERIAL INVENTORY…... 12
10
CREDIT FACILITY…………………………………………………………………………………………………………………………. 14
11
BREAK EVEN ANALYSES ……………………………………………………………………………………………………………… 15
12
INCOME STATEMENT…………………………………………………………………………………………………………………. 16
12
BALANCE SHEET…………………………………………………………………………………………………………………………. 17
13
CASH FLOW STATEMENT……………………………………………………………………………………………………………. 18
Pre-Feasibility Asphalt Plant
1 EXECUTIVE SUMMARY
An asphalt mixture plant is an assembly of mechanical and electronic equipment where
aggregates, recycled materials or other additives are blended, heated, dried and mixed with
binder to produce asphalt mixture meeting specified requirements. The plant may be
stationary (located at a permanent location) or portable (moved from contract to contract).
There are numerous types of plants, including batch plants, continuous mix plants, parallelflow drum plants, counter flow drum plants, and double barrel drum plants to name a few. In
general, however, the majority of plants may be categorized as either a batch plant or a drum
mix plant.
In the batch-type mixing plant, hot aggregate, recycled materials and binder are added in
designated amounts to make up one batch. After mixing, the asphalt mixture is discharged
from the hot bin in one batch. In the drum-type mixing plant, the aggregate and other
materials are dried, heated, and mixed with the binder in the drum in a continuous process.
Regardless of the type of mixing plant, the basic purpose is the same. That purpose is to
produce an asphalt mixture containing proportions of binder and aggregate that meets all of
the specification requirements.
Certain plant operations are common to both the batch plant and drum mix plants. These
operations include:
1. Cold aggregate storage and feeding.
2. Dust control and collection) Mix storage.
3. Recycled materials storage and feeding.
Also common to all plants is the importance of uniformity and balance, both in materials
used and in plant operations. Uniformity encompasses uniformity of materials, uniformity of
material proportioning, and continuous, uniform operation of all plant components. Changes
in material characteristics, proportions, and intermittent stops and starts in plant operations
make producing an asphalt mixture meeting Specifications extremely difficult. Balance
requires careful coordination of all elements of production. Balancing material quantities to
plant production, and balancing plant production and pavement placing operations
guarantee a continuous, uniform production and placement effort. Uniformity and balance
are best ensured by careful preparation. Materials are required to be sampled and tested and
plant components carefully inspected and calibrated before production begins.
Three used plant is considered which have following cost from dismantling to installation and
commissioning.
DESCRIPTION
Plant -1
Plant -2
Plant -2
Capital Cost for used Plant.
50,735,980
50,735,980
33,235,980
NPV
298,182,200
298,182,200
315,682,200
63%
63%
69%
8.75 Months
8.75 Months
5.73 Months
IRR
Payback Period
1
Pre-Feasibility Asphalt Plant
2 BACKGROUND
While asphalt can still be found in its natural state, today’s asphalt is typically processed from
petroleum. Oil wells supply petroleum to oil refineries, where it is separated into various
factions, one of which – from the heaviest part of petroleum– is asphalt.
Asphalt may then be modified in a variety of ways, including “cutting back” (adding a cutting
agent) to make it malleable enough for use, or emulsified or pulverized to gain the right
consistency. Asphalt for paving goes through a mixing process in either a drum mix plant,
which is a large-output and continuously operating facility, or a batch plant, which is a
smaller-output plant that mixes in batches.
There are a few different ways to mix asphalt, the most popular of which are hot and
cold. Hot-mix asphalt is made by heating aggregates to decrease the viscosity of the binding
agents and make the whole more fluid, then drying it to remove any remaining moisture. It is
mixed hot at 200-350 degrees Fahrenheit. It is called hot-mix because not only because it is
mixed hot, it must also remain hot for the paving and compaction for repair or installation.
This need for the asphalt to remain warm while paving and compaction is performed is one
of the reasons so much paving is done in the summer.
Completed asphalt is evaluated for its quality in terms of consistency or viscosity, and purity.
These are important for the asphalt to be properly controlled, transported and used in paving
projects.
Cold-mix asphalt is made of quarter inch chip and proprietary oil. This specific make-up keeps
the asphalt soft and helps it repel water. As its name suggests, cold-mix asphalt does not
need to be warm to be used in asphalt repair. Additives in the oil keep the mixture soft all
year long to allow for pothole patching in different types of weather. Even in cold or wet
weather, cold-mix asphalt stays soft and repels water, making it perfect for pothole repair in
winter and early spring. It will drive water out of the pothole, adhere to the surface
underneath and remain flexible, keeping a pothole patched all year long.
3 PROJECT PROFILE
3.1 OPPORTUNITY RATIONALE
Construction sector is growing each year due to development and infrastructure is needed in
government
and
private
sector.
This
sub-sector
(Road
Construction)
is in rapid growth as enormous project is underway due to priority of government,
metropolitan development bodies and CPEC project. Execution of work on various projects
which increased the demand of asphalt plant in country to cope the supply and demand
difference.
3.2 PROJECT BRIEF
The asphalt plants or asphalt mixing plant is one plant that is used for mixing the dry warm
aggregate, padding and Asphalt for homogeneous mixture at the required temperature. And
it is widely used to the construction of highway, city road and parking lot.
Then comes the cost estimation based on various methods of production and output. Factors
which influence unit cost include:
2
Pre-Feasibility Asphalt Plant
•
•
•
•
•
•
Cost of Plant Acquisition and Installation
Cost of Site Acquisition
Cost of Site Development
Cost of Raw Material
Cost of Furniture and Fixture for Plant
Labor Cost
3.3 PROPOSED BUSINESS LEGAL STATUS
The legal status of business will be part of Construction Company and will be declare a fixed
asset of company.
3.4 PROJECT CAPACITY AND RATIONALE
Production capacity of the plant will be depend on project in progress and future project.
Further, also the plant could be outsourced and order can be take from other builder or
construction contractor. Total production capacity is 16 hours in two shifts @ 70 tons per
hours productivity. It is estimated that daily eight hours for 20 days per month which has 34%
capacity will be operated for 1st year and then 10% production increment will be assumed for
subsequent year.
3.4.1 RAW MATERIAL SOURCING
Raw material for this project is available locally from Pakistan. A number of suppliers are
available for bitumen, stone power, sand and aggregate crush in each region of Pakistan and
could easily be contacted, whereas, bitumen could be procured from any well-known
supplier or direct from oil refinery.
4 PRODUCTION PROCESS
Bitumen plant, also called asphalt mixer plant, is a factory type complete set of equipment,
which can mix heating aggregates with different sizes, filler and bitumen in a proper
proportion at designed temperature. Bitumen mixing plant mainly consists of mechanical
part, electrical part, fuel piping part, which are cold aggregates system, drying and heating
system, lifting screening system, finished products storage system, dust removal system,
asphalt heating system, control room and other systems in details. And there are many types
of asphalt plant, such stationary asphalt mixing plant for sale, mobile asphalt plant, and plant.
With many systems, operation process of asphalt batch mix plant is a little difficult.
4.1
The Manufacturing Process
The operation process can divide into three periods, pre-work, when- work and after-work.
And users need to know the operation maters and rules well of each period..
3
Pre-Feasibility Asphalt Plant
4.1.1 PLANT DIAGRAM
Asphalt - with Batching Plant
4
Pre-Feasibility Asphalt Plant
Asphalt - with Drum
4.2 RAW MATERIAL REQUIREMENT
4.2.1 BITUMEN
Asphalt is a sticky, black, and highly viscous liquid or semi-solid form of petroleum. It is
commonly found in deep natural deposits or can be obtained after fractional distillation of
crude oil when boiling at 525 °C (997 °F). The primary use of bitumen (70%) is for road
surfaces where it is primarily used as a binder combined with aggregates. The utilization of
the remaining bitumen (30%) is for a number of vital applications such as in building
construction, industry as a primary constituent of products. Generally, bitumen is composed
of hydrocarbon compounds and is effectively used as a waterproofing agent in paving and
roofing applications. The optimal binder percentage was 7% and the 60/70 grade of bitumen
is used for asphalt.
Normally 40 kg of Bitumen is required for one ton ready mix. Less than 40 KG Bitumen will
be considered quality compromised work and more than 40 KG Bitumen in one ton ready mix
will be considered qualitative work with more strength for long lasting result. The bitumen
should be heated about 15-160 C temperature when it is mixed with aggregate.
Batch cycle of raw material mixing with bitumen should be for 40 second but it can be
fluctuate from 35 second to 45 second to keep in view the quality, cost and time.
4.2.2 AGGREGATES
The aggregate / crush stone requirement is based on asphalt demand. For multiple asphalt
layer, the first layer upon bed is required mix of 38mm, 20mm and 10mm crush and a
reduced quantity of stone dust or sand. In 2nd layer a combination of 20mm and 10mm crush
pane and stone powder.
4.2.3 Diesel / Fuel
Diesel / Crude oil is used for heating the bitumen as per requirement of Plant and also diesel will
require for the operation of Electric Generator. Diesel also will be need for Bitumen Heating on
daily basis.
5
Pre-Feasibility Asphalt Plant
4.3 PLANT & ACHINERY REQUIREMENT
Asphalt ready mix are available from already installed plant in every city. Although it has huge
cost for installation and operation yet it is cost effective for mega road project to reduce the
procurement cost of ready mix and later it can be used for multiple rod project.
Used Machinery with the following specification are available in Punjab.
Technical Specifications
Specification Plant-1
Specification Plant-2
Specification Plant-2
Make: Tanaka Asphalt Plant,
Make: Nikko Asphalt Plant ,
Make: Parker Asphalt Plant.
Model: TAP 1000, with Big Size Mixer Model:NAP 1000
Capacity: 1 Ton per batch. 60 - 80
Drum of 1500 Kg per Batch,
Capacity: 80 TPH,
TPH,
Capacity: 80 Ton P/Hour
Type : Stationary or Mobile / Stationery Type : Drum / Stationery
Type: Stationary or Mobile ? Stationery
Made: Japan
Made: England
Made: Japan
Year of Manufacturer: 1998
Year of Manufacturer: 1993
Year of Manufacturer: 1997 Rebuilt in Hoppers: 4 Nos
Generators: 2 Nos. 1 x 150KVA and 1
2001
Conveyors : Belt Type
x 350KVA
Hoppers: 4 Nos
Dryer : 1
Hoppers: 4 Nos
Conveyors: Belt Type
Screen: Vibrating
Dryer : 1
dryer: 1
Bin : 1
Screen : 1 x Vibrating
Screen: Vibrating
Mixer Drum : 1
LDU Tank: 1
Bin: Hot 4
Frame condition: Good
Computerized cabin: 1
Scale: Scale
Cyclone :Fixed in Dust Collector
Frame condition: Good
Mixer Drum : 1
Filler Bag Filler Yes
Burner : 1
Frame Good
Bitumen Tanks : 1 No. of 50 Ton
Bitumen Drum: 2 No. 50 Ton Each
Cyclone: Yes
Crude / LDO Oil Tank : 1 No. of 30000 Mixer Drum : 1
Filler: Bag Filler Yes
Liters
Frame condition: Good
Bitumen Tanks : 2 Nos. 30 Ton and 40 Ton
Plant Weight:
80 Ton
Crude Oil Tank : 1 No. of 15000 Liters
Plant Location: Sheikhupura.
Available with complete accessories.
Diesel Oil Tank : 1 No. of 10000 Liters
Plant Location: Sialkot
Plant Location: Sheikhupura
Status: Operational
Status: Operational
Status: Operational
Test Run: Will be done
Test Run: Will be done
Test Run: Will be done
Plant and Machinery
Plant -1
Amount
Price of Plant-1 Tanaka 35,000,000/Japan (1997)
Dismantling of plant
100,000/Transportation of Plant
100,000/Foundation
500,000/Installation
100,000/Misc. Cost
100,000/Misc. Tools and Equipment 200,000/Total Plant Cost
36,100,000/-
Plant -2
Amount
Price of Plant-2 Nikko 35,000,000/Japan (1998)
Dismantling of plant
100,000/Transportation of Plant 100,000/Foundation
500,000/Installation
100,000/Misc. Cost
100,000/Misc.
Tools
and 200,000/Equipment
Total Plant Cost
36,100,000/-
Plant -3
Amount
Price of Plant-3 Parker 22,500,000/England (1993)
Dismantling of plant
100,000/Transportation of Plant 100,000/Foundation
500,000/Installation
100,000/Misc. Cost
100,000/Misc.
Tools
and 200,000/Equipment
Total Plant Cost
23,600,000
Diesel Generator
Description
Diesel Generator 300kva
Electric & Mechanics
Supplies
Total Vehicle Costs
Quantity
1
1
Amount
4,500,000
500,000
5,000,000
6
Pre-Feasibility Asphalt Plant
4.4 PLANT AND MACHINERY MAINTENANCE
A used plant will be installed which is expected to be serviced on time to time on a monthly
basis. During the operation, maintenance expenses are estimated to be around 5% of the
total cost of machine.
4.5 VEHICLE FOR SUPPORT AND MAINTENANCE SERVICES
Loader / Shawal is needed on rent or need to purchase for loading aggregate into plant cold
material bin. A bike may be required for delivering and plant routine operation requirement.
Proposed Vehicles Costs
Description
Used Shawal Loader
Motorcycle
tools & Parts
Quantity
1
1
1
Amount
8,000,000
50,000
50,000
8,100,000
5 LAND & BUILDING REQUIREMENT
5.1 SITE DEVELOPMENT
The Asphalt Plant Project is estimated to require a total area of 8-10 Kanal which will be used
for installation plant, storage of raw material, Crush aggregates, Bitumen and diesel or crude
oil in tanks. Subsequently heavy machinery and vehicles i.e. dumper, fork lifters etc. would be
used which require open space for the movement as well as there will be frequent
movement of heavy transportation and delivery vehicles; therefore, large land requirement is
being recommended. Moreover, the space would also be used for vehicle parking and
different services necessary for the project.
5.2 LAND & BUILDING REQUIREMENTS
Land is supposed to hire on lease / rent for the period of project completion date. Because it
may be possible that next project is different place and transportation cost will be increased
significantly. Then the current location will ne be profitable and need to shift the plant near
to the project work in progress.
5.2.1 Selecting a site
Selecting a site to be considered on following grounds.
The location of plant would be considered which should be balanced in distance approach
towards raw material and road project to serve. Also security of area should be good.
The site must be accessible for truck and dumper for transportation of raw material and
finished goods and ground level should be plain so that there is no difficulty in operation and
vehicle movement.
5.2.2 Establishing the site
The site should have enough provision for installation of plant and machinery, storing of raw
material, camp office and movement of vehicles. The following are the main requirement for
development of plant site.
5.2.2.1 Aggregate storage
7
Pre-Feasibility Asphalt Plant
The aggregate / crush stone should be stored on a possibly concrete made flour with rain
water drainage slope but for temporary project it not recommended so only compacted bed
should be made. The developed stockyard level should be higher than the normal flour level
of plant site so that rain water should be drained easily to avoid any contamination in raw
material. Also it is needed to avoid contamination by soil, leaves, etc. The layer of aggregates
in contact with the soil should not be used for production. Partitions should be erected
between different types of aggregate / Crush Stones.
5.2.2.2 Bitumen Storage
The Bitumen would be stored in Bitumen Tank and the tank location should be near to plant so that there is no
difficulty for taking the bitumen in ready mix manufacturing process. Bitumen will need to be stored warm.
5.2.2.3 Production area
Production area is depend on plant covered area. One ton asphalt plant normally covered 19
meter (W) x 31 meter (L) installation area (6340 sft). It required some modification for
operation requirement as some component need to install near and some require distance
which may take slightly broader area. For this purpose the required area should be increased
30% more for better productivity, labor and vehicle movement.
5.2.2.4 Construction of a foundation
Foundation should be design and build according to proposed plant machines and equipment
with concrete base to avoid any vibration which lead to less productivity and frequent failure
and increasing maintenance cost of plant.
Site Development Cost
Description
Plant Installation/Foundation
Area
Unit
8242 Sft
Rate
Total Cost
Included in Plant Cost
Stockyard space (Compacted Bed)
10880 Sft
50
544,000
Plant Office
Staff Room
Remaining Site and Misc.
Development Cost
Total
200 sft
400 sft
23,798 sft
1,000
1,000
10
200,000
400,000
237,980
43,520 sft
1,381,980
6 HUMAN RESOURCE REQUIREMENT
Construction and allied industry is a labor intensive industry; therefore, a total 21 persons will
be required to handle the production operations of Asphalt Plant. The business unit will work
on two shift basis (16 hours daily). Technical staff with relevant experience will be required
for operating plant. Total approximate manpower required for the business operations along
with the respective salaries are given in the table below:
8
Pre-Feasibility Asphalt Plant
Salaries & Wages.
Staff Title
No. of Staff Monthly Salary Yearly Salary
Yearly Salary
(PKR)
(PKR)
Plant Incharge
1
80000
80000
960000
Plant Supervisor
1
40,000
40000
480000
Account Officer
1
40,000
40000
480000
Operators
2
35,000
70000
840000
Electrician
1
25,000
25000
300000
Mechanic
1
35,000
35000
420000
Welder
1
35,000
35000
420000
Labor
6
20,000
240000
-
Security Guards
2
18,000
36000
432000
Total Salary
22
5,722,000
7 FINANCIAL ANALYSIS & KEY ASSUMPTIONS
The project cost estimates for the proposed “Asphalt Plant” have been formulated on the
basis of discussions with different persons in market. The projections cover the cost of land
rent, Plant cost, installation and development cost including office equipment, fixtures etc.
Assumptions regarding machinery have been provided, however, the specific assumptions
relating to individual cost components are given as under.
7.1 LAND & BUILDING
Land for setting up the proposed Asphalt Plant would be hired on rent @ Rs. 100,000 which
will incur a cost of approximately Rs. 1.2 million. Construction and development of site will
cost around Rs. 1.26 million which has been assumed to depreciate at 10% per annum using
straight line method. if there is a vacant place available nearby a project or allowed to install
a plant on vacant place for the period of that specific project completion than the rental cost
can be avoided.
7.2 FURNITURE & FIXTURE
A provision of Rs. 154,000 for procurement of site furniture and fixture is assumed. This
would include table, desk, chairs, staff charpai and electric and sanitary work. The breakup of
site Furniture & Fixtures is as follows:
Cost of Furniture and Fixture
Description
Tables and Chairs
Waiting Chairs
Charpai for Labor
Electric and Sanitary Work & Misc. Work
Misc. Supplies
Total Cost
Quantity
1 No.
4 Nos.
2 Nos.
1 Nos.
1 No.
9
Cost per Unit
12,000
2,000
3,500
100,000
20,000
Total Cost
12,000
8,000
14,000
100,000
20,000
154,000
Pre-Feasibility Asphalt Plant
7.3 DEPRECIATION TREATMENT
The treatment of depreciation would be on a straight line method perr annum on the
following assets.
• Plant & machinery (10%)
• Building Construction and Renovation (10%)
• Furniture and Fixtures etc. (10%)
7.4 PROJECT INVESTMENT DETAILS
Cost of Plant Acquisition to commissioning Stage.
Plant -1
Reference
DESCRIPTION
Page No.
(PKR)
Plant cost
6 (4.3)
36,100,000
Vehicles Cost
7 (4.5)
8,100,000
Used Gen Set Cost
6 (4.3)
5,000,000
Site Development Cost 8 (5.2.2.4)
1,381,980
Furniture and Fixture
9 (7.2)
154,000
Total Capital Cost
50,735,980
Working Capital
Cash
500,000
Raw Material
500,000
Inventory
12 (9)
51,735,980
Plant -2
(PKR)
36,100,000
8,100,000
5,000,000
1,381,980
154,000
50,735,980
Plant -3
(PKR)
23,600,000
8,100,000
1,381,980
154,000
33,235,980
500,000
500,000
500,000
500,000
51,735,980
34,235,980
7.5 POJECT OVERHEAD DETAILS.
Operating Expenses
These below expenditure is plant operating costs which will be incurred though out the year
once plant is installed at site.
Reference
Plant -1 & 2
Plant -3
DESCRIPTION
Page No
(PKR)
(PKR)
Site Hiring Cost
9 (7.1)
1,200,000
1,200,000
Staff Salary
9 (6)
5,772,000
5,772,000
Depreciation Expenses
10 (7.3)
5,073,598
3,323,598
Maintenance Exp. 5% of P.
7 (4.4)
1,805,000
1,180,000
Cost
Admin and Misc. Cost
11(7.7)
2,738,198
2,738,198
Total Operating Cost
16,588,796
14,213,796
7.6 SELLING & DISTRIBUTION EXPENSES
For the purpose of this plant installation, it has been assumed that the asphalt ready mix
would be used for own project(s) and also for the sale of ready mix to other contractor who
have road projects but not have plant installed.
10
Pre-Feasibility Asphalt Plant
7.7 ADMIN & MISCELLANEOUS EXPENSES
Miscellaneous expenses of running the plant are assumed to be 0.5% per anum and are
expected to increase at a nominal rate of 10% per annum.
7.8 REVENUE PROJECTIONS
The Asphalt plant is expected to operate eight hours and 20 days per month on 50% capacity
per day in first year and 34% monthly capcity and will be increased 10% subsequently years.
7.9 ACCOUNTS RECEIVABLES
Considering the industry norm, the finished good material would be mainly used in owned
project. For idol time plant will be run for other contractor at agreed ready mix rate. It is
assumed that 90% of the sales will be on cash. Whereas, remaining 10% sales will be on
credit to the builders and construction contractors. A collection period of 60 days is assumed
for the credit sales.
7.10 Source of Capital
The source of capital is presented in the following table:
Debts
0%
Equity
100%
7.11 OWNER’S WITHDRAWAL
It is assumed that the owner will draw funds from the business once the desired profitability
is
reached
from
the
start
of
operations.
8. ESTIMATED PLANT PRODUCTION
Plant is expected to operate on daily 8 hours capacity. So production would be produced on
50% capacity on daily and 34% capacity on monthly basis which is as follow;
Plant Production
DESCRIPTION
(PKR)
Plant Production capacity per hour in tons (TPH)
Per day operational hour (Single Shifts)
70
8
Per day Production Capacity in tons (TPD)
560
Monthly Operational Days
20
Expected Production. Per month in ton
11,200
1st Year Production in tons
134,400
2nd Year Production in tons
147,840
11
Pre-Feasibility Asphalt Plant
3rd Year Production in tons
162,624
4th Year Production in tons
178,886
5th Year Production in tons
196,775
9. ESTIMATED REVENUE
The ready mix (Finished Goods) will be used at own project(s) and also would be sold to
different clients (construction contractors and builders). Further, price of ready mix would be
increased 10% annually.
Based on 8 hours & 20 days operational Capacity with
10% Increment of every each year
Annual
Production
Average Rate
Annual Revenue
Year
1st Year Production
134,400
5,000
672,000,000
2nd
Year Production
147,840
5,500
813,120,000
3rd Year Production
162,624
6,050
983,875,200
4th
Year Production
178,886
6,655
1,190,488,992
5th Year Production
196,775
7,321
1,440,491,680
ESTIMATED COST OF SALES, RAW MATERIAL PROCUREMENT and RAW MATERIAL INVENTORY
Component of Direct Cost is Bitumen, Aggregate High Speed Diesel and Low Speed Diesel
which expected to increase 10% each year. The diagram also suggest the cost of sales, each
year procurement and raw material inventory in units quantity and in currency as well. Below
are the details for five years.
Year-0
Aggregate
(CFT)
22
22%
Description
Per ton Material Require
Cost of Sale Ratio
Material Consumed (COS)
Material in Units Procured
Raw Material Inventory C/F
40
74%
2
4%
LS Diesel
(Liters)
0.3
1%
107,983
368,125
20,983
2,908
500,000
2,700
2,700
4,908
4,908
184
184
37
37
500,000
Year-1
Description
Raw Material Inventory
B/F
Procurement in Units
Total Procurement in
Units
Consumed in Production
Raw Material Inventory
C/F
Cost of Raw Material
Cost of Raw Material B/F
Per unit cost of Raw
Material (PKR)
Procurement Cost
Total Procurement
Cost of Sales
Aggregate
(CFT)
Bitumen (KG)
HS. Diesel
(Liters)
Annual Production
HS. Diesel
Bitumen (KG)
(Liters)
134,400 Tons
LS Diesel
Amount
(Liters)
(PKR)
2,700
3,000,000
4,908
5,390,000
184
210,000
37
45,000
3,002,700
2,956,800
5,394,908
5,376,000
210,184
201,600
45,037
40,320
45,900
18,908
8,584
4,717
PKR
PKR
PKR
Amount
(PKR)
500,000
100%
PKR
107,983
368,125
20,983
2,908
500,000
40
120,000,000
120,107,983
118,272,000
75
404,250,000
404,618,125
403,200,000
114
23,940,000
23,960,983
22,982,400
79
3,555,000
3,557,908
3,185,280
551,745,000
552,245,000
547,639,680
12
Pre-Feasibility Asphalt Plant
Raw Material Inventory
C/F
1,835,983
Year-2
Description
R. Material Inventory B/F
Procurement in Units
Total Procurement in
Units
Consumed in Production
R. Material Inventory C/F
Cost of Raw Material
Cost of Raw Material B/F
Per unit cost of R.
Material
Procurement Cost
Total Procurement
Cost of Sales
R. M. Inventory C/F
Year-3
Description
Raw Material Inventory B/F
Procurement in Units
Total Procurement in Units
Consumed in Production
Raw Material Inventory C/F
Cost of Raw Material
Cost of Raw Material B/F
Per unit cost of R. Material
Procurement Cost
Total Procurement
Cost of Sales
R. M. Inventory C/F
Aggregate
(CFT)
45,900
3,250,000
1,418,125
Annual Production
HS. Diesel
Bitumen (KG)
(Liters)
18,908
8,584
5,915,000
225,000
3,295,900
3,252,480
43,420
PKR
5,933,908
5,913,600
20,308
PKR
372,628
147,840 Tons
LS Diesel
Amount
(Liters)
(PKR)
4,717
45,000
233,584
221,760
11,824
PKR
49,717
44,352
5,365
PKR
1,418,125
978,583
372,628
4,605,320
44
143,000,000
144,835,983
143,109,120
1,726,863
83
487,987,500
489,405,625
487,872,000
1,533,625
125
28,215,000
29,193,583
27,808,704
1,384,879
87
3,910,500
4,283,128
3,854,189
428,939
663,113,000
667,718,320
662,644,013
5,074,307
Annual Proudction
162,624 Tons
Aggregate
HS. Diesel
LS Diesel
Amount
Bitumen (KG)
(CFT)
(Liters)
(Liters)
(PKR)
43,420
20,308
11,824
5,365
3,600,000
6,505,000
240,000
50,000
3,643,420
6,525,308
251,824
55,365
3,577,728
6,504,960
243,936
48,787
65,692
20,348
7,888
6,578
PKR
PKR
PKR
PKR
1,726,863
1,533,625
1,384,879
428,939
5,074,-,240,000
590,328,750
33,105,600
4,779,500
802,453,850
175,966,863
591,862,375
34,490,479
5,208,439
807,528,157
173,162,035
590,325,120
33,648,532
4,663,568
801,799,255
2,804,828
1,537,255
841,947
544,871
5,728,902
Annual Production
Aggregate
(CFT)
R. Material Inventory B/F
Bitumen (KG)
HS. Diesel
(Liters)
178,886 Tons
LS Diesel
(Liters)
65,692
20,348
7,888
6,578
Procurement in Units
Total Procurement in
Units
4,000,000
7,156,000
270,000
55,000
4,065,692
7,176,348
277,888
61,578
Consumed in Production
3,935,501
7,155,456
268,330
53,666
R. Material Inventory C/F
130,191
20,892
9,558
7,912
Cost of Raw Material
Cost of Raw Material B/F
Per unit cost of R.
Material
4,605,320
1,835,983
Year-4
Description
978,583
PKR
PKR
PKR
Amount
(PKR)
PKR
2,804,828
1,537,255
841,947
544,871
53
100
152
105
Procurement Cost
212,960,000
714,347,700
40,968,180
5,783,195
974,059,075
Total Procurement
215,764,828
715,884,955
41,810,127
6,328,066
979,787,977
13
5,728,902
Pre-Feasibility Asphalt Plant
Cost of Sales
209,526,063
714,293,395
40,714,724
5,642,918
970,177,099
6,238,766
1,591,560
1,095,404
685,148
9,610,878
R. M. Inventory C/F
Year-5
Aggregate
(CFT)
Description
R. Material Inventory
B/F
Procurement in Units
Total Procurement in
Units
Consumed in Production
R. Material Inventory
C/F
Cost of Raw Material
Cost of Raw Material B/F
Per unit cost of R.
Material
Procurement Cost
Total Procurement
Cost of Sales
R. M. Inventory C/F
Annual Proudction
HS. Diesel
Bitumen (KG)
(Liters)
196,775 Tons
LS Diesel
Amount
(Liters)
(PKR)
130,191
4,350,000
20,892
7,875,000
9,558
295,000
7,912
60,000
4,480,191
4,329,051
7,895,892
7,871,002
304,558
295,163
67,912
59,033
151,140
24,891
9,396
8,879
PKR
PKR
PKR
PKR
6,238,766
1,591,560
1,095,404
59
254,753,400
260,992,166
253,526,536
7,465,630
110
864,734,063
866,325,623
864,295,008
2,030,614
167
49,237,683
50,333,087
49,264,815
1,068,271
685,148
9,610,878
116
6,939,834 1,175,664,980
7,624,982 1,185,275,857
6,827,931 1,173,914,290
797,052
11,361,567
10. CREDIT FACILITY:
Consideration a business norm. It is expected that 10% of sale (to other contractors) would
be on credit for 30 days terms. On the other hand, procurement from different suppliers or
manufacturer is expected to be sourced on credit of 20% for 30 days term. The details are as
under.
Account Receivable.
Years
Annual Sales
Credit Sales %
Credit Sales
Value
Debtor's Age in
Days
Account
Receivable C/F
Year - 1
672,000,000
10%
67,200,000
30
5,523,288
Year - 2
813,120,000
10%
81,312,000
30
6,683,178
Year - 3
983,875,200
10%
98,387,520
30
8,086,645
Year - 4
1,190,488,992
10%
119,048,899
30
9,784,841
Year - 5
1,440,491,680
10%
144,049,168
30
11,839,658
Account Payable
Years
Annual
Procurement
Credit
Purchase
Value
Credit
Purchase %
Debtor's Age
in Days
Account
Payable C/F
Year - 1
551,745,000
20%
110,349,000
30
9,069,781
Year - 2
663,113,000
20%
132,622,600
30
10,900,488
Year - 3
802,453,850
20%
160,490,770
30
13,191,022
Year - 4
974,059,075
20%
194,811,815
30
16,011,930
14
Pre-Feasibility Asphalt Plant
Year - 5
1,175,664,980
20%
235,132,996
11. BREAK EVEN ANALYSES
Annual Costs & Revenue
Sale
Value Cost
Contribution
Fixed Cost
Operating Profit
672,000,000
547,639,680
124,360,320
16,588,796
107,771,524
PV Ratio
19%
Break Even Point Sale
89,640,097
Break Even Point Sales & Costs
Sale (BEP)
Value Cost
Contribution
Fixed Costs
Profit
89,640,097
73,051,301
16,588,796
16,588,796
-
BEP In Units Sales
Unit to be Sold
Revenue
Less Cost of Sales
Aggregate
Bitumen
HS. Diesel
LS. Diesel
Cost of Sales
Gross Profit
Operating Cost
Profit / Loss / BEP
17,928
89,640,097
15,776,657
53,784,058
3,065,691
424,894
73,051,301
16,588,796
16,588,796
-
15
30
19,326,000
Pre-Feasibility Asphalt Plant
12. INCOME STATEMENT
Description
Revenue
Less Cost of Sales
Aggregate Costs
Bitumen Cost
High Speed
Diesel Cost
Low Speed Diesel
Cost
Cost of sales
Gross Profit
Operating Cost
Site Hiring Cost
Staff Salary
Depreciation
Expenses
Maintenance Exp.
Admin & Misc.
Exp.
Subtotal
Operating Income
Tax 35%
NET
PROFIT/(LOSS)
AFTER TAX
Balance brought
forward
Total profit
available for
appropriation
Balance carried
forward
Year 1
672,000,000
Year 2
813,120,000
Year 3
Year 4
Year 5
983,875,200 1,190,488,992 1,440,491,680
118,272,000
403,200,000
143,109,120
487,872,000
173,162,035
590,325,120
209,526,063
714,293,395
253,526,536
864,295,008
22,982,400
27,808,704
33,648,532
40,714,724
49,264,815
3,185,280
3,854,189
4,663,568
5,642,918
6,827,931
547,639,680
124,360,320
662,644,013
150,475,987
801,799,255
182,075,945
1,200,000
5,772,000
1,200,000
6,349,200
1,200,000
6,984,120
1,200,000
7,682,532
1,200,000
8,450,785
5,073,598
5,073,598
5,073,598
5,073,598
5,073,598
2,536,799
2,536,799
2,536,799
2,536,799
2,536,799
2,738,198
3,012,018
3,313,220
3,644,542
4,008,996
17,320,595
107,039,725
37,463,904
18,171,615
132,304,372
46,306,530
19,107,737
162,968,207
57,038,873
20,137,471
200,174,422
70,061,048
21,270,178
245,307,212
85,857,524
69,575,821
85,997,842
105,929,335
130,113,374
159,449,688
69,575,821
85,997,842
105,929,335
130,113,374
69,575,821
85,997,842
105,929,335
130,113,374
159,449,688
69,575,821
85,997,842
105,929,335
130,113,374
159,449,688
970,177,099 1,173,914,290
220,311,893
266,577,390
Note:
•
•
•
Depreciation charged 10% using straight line method, no residual value / scrap value
is accounted as plant is expected to run for subsequent years.
Maintenance Cost is 5% of plant value including plant, vehicles, generators and
buildings and furniture’s & fixtures which serve direct production activities.
Admin and Misc. Expenses are expected to incur0.5% of cost of sale on activity
procurement, operation, transportation will start and also carriage, entertainment,
insurance, office and staff fuel etc will require.
16
Pre-Feasibility Asphalt Plant
13. BALANCE SHEET
Description
Year 0
Year 1
500,000
77,892,395
Year 2
Year 3
Year 4
Year 5
Current Assets
Cash & Bank
Accounts
receivable
Raw material
inventory
Total Current
Assets
500,000
1,000,000
99,589,843 124,827,407 151,325,780 185,244,256
5,523,288
6,683,178
8,086,645
9,784,841
11,839,658
4,605,320
5,074,307
5,728,902
9,610,878
11,361,567
88,021,003 111,347,328 138,642,954 170,721,499 208,445,480
Fixed Assets
Plant cost
36,100,000
32,490,000
28,880,000
25,270,000
21,660,000
18,050,000
8,100,000
7,290,000
6,480,000
5,670,000
4,860,000
4,050,000
5,000,000
4,500,000
4,000,000
3,500,000
3,000,000
2,500,000
1,381,980
1,243,782
1,105,584
967,386
829,188
690,990
154,000
138,600
123,200
107,800
92,400
77,000
Total Fixed
Assets
50,735,980
45,662,382
40,588,784
35,515,186
30,441,588
25,367,990
Total Assets
51,735,980 133,683,385 151,936,112 174,158,140 201,163,087 233,813,470
Vehicles Cost
Used Gen Set
Cost
Site
Development
Cost
Furniture and
Fixture
Liabilities & Shareholders' Equity
Accounts
payable
Total Liabilities
9,069,781
10,900,488
13,191,022
16,011,930
19,326,000
-
9,069,781
10,900,488
13,191,022
16,011,930
19,326,000
51,735,980
55,037,783
55,037,783
55,037,783
55,037,783
55,037,783
69,575,821
85,997,842 105,929,335 130,113,374 159,449,688
Shareholders'
equity
Capital
Retained
earnings
Total Equity
51,735,980 124,613,604 141,035,625 160,967,118 185,151,157 214,487,471
Total Capital &
Liabilities.
51,735,980 133,683,385 151,936,112 174,158,140 201,163,087 233,813,470
17
Pre-Feasibility Asphalt Plant
14. CASH FLOW STATEMENT
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
Net profit
69,575,821
85,997,842
105,929,335
130,113,374
159,449,688
Add:
depreciation
expense
5,073,598
5,073,598
5,073,598
5,073,598
5,073,598
9,069,781
10,900,488
13,191,022
16,011,930
19,326,000
83,719,200
101,971,927
124,193,955
151,198,902
183,849,285
5,523,288
6,683,178
8,086,645
9,784,841
11,839,658
500,000
4,605,320
5,074,307
5,728,902
9,610,878
11,361,567
-500,000
73,590,592
90,214,442
110,378,408
131,803,184
160,648,061
51,735,980
-
-
-
-
-
52,235,980
-
-
-
-
-
51,735,980
-
-
-
-
-
51,735,980
-
-
-
-
-
500,000
73,590,592
90,214,442
110,378,408
49,401,804
67,897,844
500,000
74,090,592
164,305,034
274,683,442
324,085,246
500,000
74,090,592
164,305,034
274,683,442
324,085,246
391,983,090
500,000
74,090,592
164,305,034
274,683,442
324,085,246
391,983,090
Operating
activities
Account Payable
Total
Accounts
receivable
Raw material
inventory
Cash provided by
operations
0
Financing activities
Issuance of
Funds
Cash provided by /
(used for)
financing activities
Investing activities
Capital
expenditure
Cash (used for) /
provided by
investing activities
NET CASH
Cash balance
brought forward
Cash available for
appropriation
Cash carried
forward
18