Data Entry
Summary of Rates
S.N.
Norms No
1
9.4.I.B.iii
2
3
9.4.I.B.ii
9.4.I.B.i
Specification
Clause No.
907
907
Description
Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and
other deleterious matter and backfilling with approved Material as per Drawing and Technical Specifications by Mechanical
Means.[Depth above 6m]. For ordinary soil.
Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and
other deleterious matter and backfilling with approved Material as per
Drawing and Technical Specifications by Mechanical Means.[Depth 3- 6m]. For ordinary soil.
907
Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and
other deleterious matter and backfilling with approved Material as per Drawing and Technical Specifications by Mechanical
Means.[Depth upto 3m]. For ordinary soil.
Providing, Boring and installing bored cast-in-situ RCC Pile excluding Reinforcement and Concrete in all types of soil
including Bentonite and other consumable and removal of excavated earth with necessary lifts and lead all complete as per
Drawing and Technical Specifications.
[dia 1000]
4
16.01.D
1612
5
20.2 (A)
2000
Providing and laying of Plain/ Reinforced cement concrete PCC Grade M15 in sub-structure for upto
height 5m complete as per drawing and Technical Specifications.
6
20.2 C
2000
Providing and laying of Plain/ Reinforced cement concrete RCC Grade M20 in sub-structure complete
as per drawing and Technical Specifications.
7
20.2.E
2000
Providing and placing machine mixed cement concrete of M25/20 for the founation and footing etc. including
compaction,curing,testing and lead 30m etc all complete as per specification
Unit
Rate ( NRs.)
344.53
m3
m3
281.43
m3
242.01
Rm
15,006.51
m3
11,122.34
m3
12,622.22
m3
13,784.67
Summary of Rates
S.N.
8
Norms No
20.5
Specification
Clause No.
2014
Description
Unit
Providing and laying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
Drawing and Technical Specifications including cutting, bending, shifting to site, tying and placing in position.
Mt
115,990.29
Mt
118,336.29
Providing and laying, fitting and placing HYSD bar reinforcement in super-structure complete as per
Drawing and Technical Specifications including cutting, bending, shifting to site, tying and placing in position.
9
20.9
2014
10
18.2.b.iii
1804 & 1805
Providing,preparing and installing formwork including necessary supports and removing after
complection for substructures. For 6-9 m
11
24.5
2404
Providing and laying of a geo-textile filter fabric between pitching and embankment slopes as specified
in drawing and Technical Specifications.
12
9.12
909, 910
13
9.11 (A)
908
Providing suitable material and backfilling behind abutment and return wall complete as per Drawing
and Technical Specifications using granular material.
14
20.8.(A)
2000
Providing and laying Reinforced cement concrete M20 in superstructure as per drawing as per
drawing and Technical Specification.
15
20.8.(B)
2000
Providing and laying Reinforced cement concrete M25 in superstructure as per drawing as per
drawing and Technical Specification.
16
18.7 b
1804, 1805
Providing, Preparing and Installing formwork including necessary supports and removing after
completion for the super structure, deckslab, girder. Using steel. Class F2 finish.
Providing and filling with graded gravel filter material in layers with necessary watering and compaction.lead 30m,lift 1.5m.
Rate ( NRs.)
m2
872.09
m2
137.52
m3
3,344.20
m3
735.60
m3
12,568.95
m3
14,342.46
m2
933.95
Summary of Rates
S.N.
Norms No
Specification
Clause No.
Description
Unit
m3
17
18.7 c
1804, 1805
Providing, Preparing and Installing formwork including necessary supports and removing after completion for the super
structure, deckslab, girder. Using shutter ply. Class F2 finish.
18
18.9.I.a
1804, 1805
Providing, Preparing and Installing formwork including necessary supports, and removing after completion for pre-cast
elements. Class F3 finish. Using timber. For rectangular / Square section
19
18.11.b.i,ii,iii
1803
20
21
Providing and assembling in position falsework for the construction of RCC super structure and
removing after completion including design and drawings as per specification.
1902
Providing and installing different types of Bearing including all necessary axilliary and incidental works
etc. complete as per drawing and specification.
Providing and laying of compression seal joint consisting of steel armored nosing at two edges of the joint gap suitably
anchored to the deck concrete and preformed chloroprene elastomer or closed cell formed joint sealer compressed and
fixed into the joint gap with special adhesive binder to cater for a horizontal movement and vertical movement all complete
as per drawing and technical specifications.
1,047.19
m3
1,212.47
m2
-For RCC beam. Using Steel. Height upto 3m.
19.6
Rate ( NRs.)
1,692.75
Nos
47,989.49
Rm
6,669.22
22
19.9
1901
23
19.10
1901
Providing and laying of strip seal expansion joint catering to maximum horizontal movement upto
70mm complete as per approved drawing and technical specifications.
Rm
32,746.25
3105
Providing, fencing and erecting 50mm dia painted steel pipe railing in 3 rows 50 mm dia for pipe
complete as per Drawing and Technical Specifications.
Rm
1,572.82
3105
Providing and fixing Drainage Spouts complete as per Drawing and Technical specifications.
no.
6,079.97
24
25
-
Summary of Rates
S.N.
Norms No
26
26
28
31
32
33
34
Specification
Clause No.
-.b
-.a ,
24.02.01.a ,-.b ,
24.02.01.b ,-.d ,
24.02.01.d ,-.j ,
24.02.01.j ,
24.02.04
905
909,910
2401
2401
2401
2401
Description
Unit
Painting Two Coats on Concrete Surfaces
Providing and Painting two coats after filling the surface with synthetic enamel paint in all shades on concrete/plaster surfaces
as per Drawing and Technical Specifications.
m2
714.84
m3
113.10
m3
1,006.23
m3
7,499.27
m3
7,569.39
m3
7,901.89
m3
8,874.99
Road way excavation in Hard soil/Gravells/Boulder mixed soil including disposal upto 10m and lift
upto 1.5 m etc. all complete as per specification.
Construction of embankment with material obtained from borrow pits. Providing, laying, spreading and compacting
embankment with borrow material as per drawing and Technical specifications.
Fabrication of Gabion boxes / mattresses with diapharagms including rolling, cutting and weaving as
per specification, placing and supply of stone, filling all complete. Mesh size : 100×120,mesh Wire: 10 selvedge wire:7 binding
wire: 12swg [3m×1m×1m]
Fabrication of Gabion boxes / mattresses with diapharagms including rolling, cutting and weaving as per specification, placing
and supply of stone, filling all complete. Mesh size : 100×120,mesh Wire: 10
selvedge wire:7 binding wire: 12swg [2m×1m×1m]
Fabrication of Gabion boxes / mattresses with diapharagms including rolling, cutting and weaving as per specification, placing
and supply of stone, filling all complete. Mesh size : 100×120,mesh Wire: 10
selvedge wire:7 binding wire: 12swg [1m×1m×1m]
Fabrication of Gabion boxes / mattresses with diapharagms including rolling, cutting and weaving as
per specification, placing and supply of stone, filling all complete. Mesh size : 100×120,mesh Wire: 10 selvedge wire:7 binding
wire: 12swg [1m×1m×0.5m]
Rate ( NRs.)
Summary of Rates
S.N.
35
36
43
44
45
46
47
Norms No
24.01.02.m ,
24.02.01.m ,-.A
12.1A
15.12
2.1.I.i.A
28.14.C
2406(2,3)
Specification
Clause No.
- & 2607
1201
Description
Fabrication of Gabion boxes / mattresses with diapharagms including rolling, cutting and weaving as
per specification, placing and supply of stone, filling all complete. Mesh size : 100×120,mesh Wire: 10 selvedge wire:7 binding
wire: 12swg [1m×1m×0.3m]
Providing and laying RRM in cement mortar (1:4) including scaffolding, curing, preparation of mortar
etc., all complete, mortar 35% [2600] for side drains, retaining walls.
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density,
complete as per Drawing and Technical Specifications.
1507
Providing and installation of 150mmx150mm 1.5mm long delineators (road way indicators, hazard markers, object marker),
80-100cm high above ground level, painted black and white in 20 cm wide strips, buried or pressed into the ground and
conforming to the drawings and technical specifications.
201
Clearing and grubbing of forest including uprooting, carrying and disposing of vegetation, grass, bush, sapling and trees of
girth upto 300mm (measured at a height of 1m above the ground level).
2812
24.12.b
Providing , furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the engineers including preparation
of ground, fetching of sods and watering.
Laying of dry stone rip rap for scour protection and river training works with stone weighting not less than 75kg and packed
with stones 20-40kg.lead 30m with out using mechanical means.
Unit
Rate ( NRs.)
m3
8,905.97
m3
12,760.00
m3
2,370.85
Nos
1,776.67
m2
15.64
m2
889.13
m3
-
Summary of Rates
Specification
Clause No.
S.N.
Norms No
Description
48
24.03.01
2403(4)
Providing and laying Dry-stone soling in foundation work, lead 30m,lift 1.5m with stone size not less
than 0.01m3 including levelling etc. complete.
49
7.02
701
50
24.05(b.ii)
2403
Unit
Rate ( NRs.)
m3
-
Providing and laying RCC pipes having dia 900mm with or without collars,jointed with stiff mixture of
cement mortar in the porportion of 1:2(1cement:2fine sand), lead upto 100m
rm
-
Providing and installing of Rock Dowel including grouting using portable rock driller
rm
-