Storm water management plan for Colliery life
OPGOEDENHOOP, HENDRINA
STORM WATER MANAGEMENT PLAN
CONCEPTUAL PHASE
SEPTEMBER 2014
Prepared by:
For:
REVIEW AND ACCEPTANCE
NAME
ROLE
SIGNATURE
DATE
Louis Aucamp
Compiler
20/09/2014
Sakkie Prinsloo
Reviewer
20/09/2014
Dzivhuluwani Takalani
Recipient
REVISION HISTORY
REV
DATE
DESCRIPTION
AFFECTED PAGES
ORIGINATOR
0.0
07/09/2014
First draft for review
All
Louis Aucamp
0.1
19/09/2014
Final draft for review
All
Louis Aucamp
0.2
20/9/2014
Reviewed
All
Sakkie Prinsloo
ii
TABLE OF CONTENTS
1
INTRODUCTION ........................................................................................................................................ 1
2
SCOPE OF WORK ...................................................................................................................................... 1
3
PROJECT METHODOLOGY ......................................................................................................................... 1
4
OBJECTIVES .............................................................................................................................................. 3
5
TECHNICAL SITUATION ANALYSIS ............................................................................................................. 3
5.1
SITE DESCRIPTION AND RAINFALL DATA ................................................................................................. 3
5.1.1
The Site ........................................................................................................................................... 3
5.1.2
Wetland Assessment ....................................................................................................................... 5
5.1.3
Rainfall ............................................................................................................................................ 5
5.2
METHODOLOGY ...................................................................................................................................... 5
5.3
MINING LAND, PITS AND DUMPS (ANNEXURE B) ....................................................................................... 6
5.4
MAJOR CATCHMENTS (ANNEXURE D) ........................................................................................................ 7
5.4.1
Catchment A ................................................................................................................................... 7
5.4.2
Catchment B.................................................................................................................................... 7
5.4.3
Catchment C.................................................................................................................................... 7
5.4.4
Catchment D ................................................................................................................................... 7
5.4.5
Catchment E .................................................................................................................................... 7
5.4.6
Catchment F .................................................................................................................................... 7
5.4.7
Other catchments ........................................................................................................................... 7
5.4.8
Peak flows ....................................................................................................................................... 8
5.5
SUB-CATCHMENTS (ANNEXURE D) ............................................................................................................. 8
5.5.1
Office area ...................................................................................................................................... 8
5.5.2
ROM pad and weighbridge and haul roads .................................................................................... 8
5.5.3
Opencast pit area............................................................................................................................ 9
5.5.4
Waste dump .................................................................................................................................... 9
5.5.5
Workshop ........................................................................................................................................ 9
5.5.6
Sub-catchments: Peak flows and volumes ...................................................................................... 9
5.6
HYDROLOGICAL MODELLING .................................................................................................................. 9
5.7
PREVIOUS WORK AND INFORMATION.............................................................................................................. 10
6
REQUIRED INFRASTRUCTURE AND CONCEPTUAL DESIGN .....................................................................-
7
CATCHMENT D. ......................................................................................................................................... 10
CATCHMENT C ........................................................................................................................................... 10
CATCHMENT E ........................................................................................................................................... 11
OFFICE AREA ............................................................................................................................................. 11
ROM PAD, WEIGH BRIDGE AND HAUL ROADS ................................................................................................... 11
WASTE DUMP ............................................................................................................................................ 11
WORKSHOP AREA ....................................................................................................................................... 12
OPENCAST PIT STORM RUNOFF ...................................................................................................................... 12
POLLUTION CONTROL DAM FOR ROM PAD AND ASSOCIATED AREAS ...................................................................... 12
FEASIBILITY OF REQUIRED INFRASTRUCTURE ......................................................................................... 12
7.1
ISOLATE CLEAN WATER AREAS...................................................................................................................... 12
7.2
ISOLATE AND MANAGE “AFFECTED” WATER.................................................................................................... 13
7.2.1
Rom pad. Weigh bridge and haul roads ....................................................................................... 13
7.2.2
Waste Dumps ................................................................................................................................ 13
7.2.3
Opencast pit area.......................................................................................................................... 13
7.3
ISOLATE DIRTY WATER AND RE-USE .............................................................................................................. 13
7.3.1
Workshop Area ............................................................................................................................. 13
iii
7.4
FEASIBILITY OF THE SOLUTIONS...................................................................................................................... 13
8
CONCEPTUAL DESIGN AND REVIEW ....................................................................................................... 13
9
CONCEPTUAL OPERATIONAL, MANAGEMENT AND MONITORING SYSTEMS AND RESPONSIBILITIES ..... 14
9.1
WATER POLLUTION PREVENTION METHODS ................................................................................................... 14
9.1.1
Storage & handling of waste ........................................................................................................ 14
9.1.2
Storage and handling of hydrocarbons & explosives .................................................................... 15
9.1.3
Opencast pit area.......................................................................................................................... 15
9.1.4
Pollution control dam ................................................................................................................... 16
9.1.5
Transporting coal .......................................................................................................................... 16
9.2
GROUNDWATER MANAGEMENT ................................................................................................................... 16
9.3
MINIMISATION AND REUSE OF MINE WATER .................................................................................................. 16
9.4
EFFLUENT TREATMENT METHODS ................................................................................................................. 16
9.5
PROPOSED DISPOSAL OF EFFLUENT ............................................................................................................... 17
10
STORM WATER MANAGEMENT PLAN ................................................................................................ 17
10.1 ISOLATION OF CLEAN WATER AREAS .............................................................................................................. 18
10.1.1 Isolation of clean water from Catchment D .................................................................................. 18
10.1.2 Isolation of clean water from Catchment C .................................................................................. 18
10.1.3 Isolation of clean water from Catchment E .................................................................................. 18
10.1.4 Handling of clean water from the office area ............................................................................... 18
10.2 ISOLATE AND TREAT “AFFECTED” WATER ....................................................................................................... 18
10.2.1 Silt laden water from the weigh bridge, ROM pad and haul roads .............................................. 18
10.2.2 Waste Dumps ................................................................................................................................ 18
Construct a pollution control dam(s) with silt traps as detailed in section 6.6. .................................... 19
Provide regular clearance and maintenance of the facility. ................................................................. 19
10.2.3 Storm water runoff and flooding in the opencast pit.................................................................... 19
10.2.4 Pollution control dam for the ROM pad. Pit and workshop areas ................................................ 19
10.3 ISOLATE DIRTY WATER AND RE-USE .............................................................................................................. 19
10.3.1 Workshop Areas ............................................................................................................................ 19
10.4 MAINTENANCE AND OPERATING PROCEDURES ................................................................................... 19
10.4.1 Storm water Drainage System ...................................................................................................... 19
10.4.2 Settling Ponds ............................................................................................................................... 20
10.4.3 Return Water Sumps ..................................................................................................................... 20
10.4.4 Waste Dump Run-Off and Siltation ............................................................................................... 20
10.4.5 Pits ................................................................................................................................................ 20
10.5 MONITORING PROGRAMME................................................................................................................. 20
10.6 MANAGEMENT STRUCTURE ................................................................................................................. 20
11
MINE CLOSURE ................................................................................................................................... 21
12
RELEVANT DOCUMENTATION ............................................................................................................ 21
13
RECOMMENDATIONS ......................................................................................................................... 21
14
ANNEXURE A – WORKPLAN FOR OPGOEDENHOOP SWMP ................................................................. 22
15
ANNEXURE B – SITE PLAN ................................................................................................................... 25
16
ANNEXURE C – CALCULATION RESULTS AND DATA SETS .................................................................... 26
-
CATCHMENT A ........................................................................................................................................... 26
CATCHMENT B........................................................................................................................................... 27
CATCHMENT C ........................................................................................................................................... 28
CATCHMENT D .......................................................................................................................................... 31
CATCHMENT E ........................................................................................................................................... 34
CATCHMENT F – PIT AREA INITIAL AND FINAL ................................................................................................... 37
CATCHMENT OFFICE AREA ............................................................................................................................ 39
CATCHMENT ROM PAD, WEIGH BRIDGE AND HAUL ROAD AREAS ........................................................................... 40
CATCHMENT WASTE DUMP AREA ................................................................................................................... 41
iv
16.10 CATCHMENT WORKSHOP AREA...................................................................................................................... 42
17
ANNEXURE D – GENERAL MAPS SHOWING RUNOFF AND CATCHMENT AREAS .................................. 43
18
ANNEXURE E – VOLUME CALCULATIONS FOR THE SUB-CATCHMENTS ............................................... 44
19
ANNEXURE F – CONCEPTUAL DESIGN CALCULATIONS FOR SELECTED AREAS ...................................... 46
LIST OF TABLES
Table 1: Rainfall Station Data ................................................................................................................ 5
Table 2: Major Catchments Peak Flows (m 3/s)...................................................................................... 8
Table 3: Sub-Catchments, Peak Flows and Volumes ........................................................................... 9
v
1
INTRODUCTION
Chatam Construction and The Complete Back Office were appointed by NRR Mining and Consulting to
prepare a conceptual Storm Water Management Plan (SWMP)for the proposed coal mine on portion
5 of the farm Opgoedenhoop 205 IS in the district of Hendrina, Mpumalanga. The scope includes
review of and incorporation of previous water related studies that has been done for the property.
2
SCOPE OF WORK
The scope of work for the SWMP is listed below and reference is made in the paragraphs therafter to
the procedures which are to be applied in the process to compile the STORM WATER MANAGEMENT
PLAN:-
Project Methodology
Objectives
Technical Situation Analysis
Hydrological Modelling
Infrastructure Requirements
Maintenance and Operating Procedures
Relevant Documentation
The scope of work is conceptual in nature and will provide indicative recommendations and guidelines
rather than detailed prescriptions. Maintenance and operating issues will only be dealt with in the
context of the importance thereof for a sustainable SWMP, as the detail design of the infrastructure
will dictate the maintenance and operating procedures. Issues relating to the water balance and salt
balance, acid water drainage, permits and legal requirements are covered by other consultants and is
excluded from the scope of work for the SWMP.
3
PROJECT METHODOLOGY
The Department of Water Affairs Best Practice Guidelines for water resource protection in the South
African mining industry have been used in the compilation of this document, in particular G1: Storm
Water Management, A5: Water Management for Surface Mines and A6: Water Management for
Underground Mines. The procedure adopted for this study is that outlined in chapter 4 of the G1
guideline and the abbreviated flowchart shown hereafter in Figure 1.
1
Figure 1: Procedure to develop a conceptual Storm Water Management Plan (BPG1)
2
The work plan to achieve the deliverables according to the outlined procedure is included as Annexure
A. The work plan has been drawn up to cover all the eventualities but could only be developed to the
extent that information was available.
This document must be read in conjunction with the other reports on aspects of the water usage and
requirements prepared by other consultants.
For the purposes of this report, three types of run-off have been defined for the assessment i.e.:
Clean water – storm water run-off from natural veld.
Affected water – waste dump run-off containing suspended solids from ore dust and
waste rock.
Dirty water – polluted water containing diesel, oil or hydro carbons.
4
OBJECTIVES
The objectives of the conceptual Storm Water Management Plan are aligned with those propagated
in Best Practice Guidelines G1 namely:
Objective 1
Isolate clean water from dirty water and route it directly to the nearest natural watercourse.
Objective 2
Isolate run-off contaminated with suspended solids (moderately dirty water or “affected water”) from
clean water and treat appropriately.
Objective 3
Isolate dirty water, contaminated with oil, grease and solvents, from the clean water areas and treat
effectively so that it can be re-used in the process water for the mine as far as practically possible.
5
5.1
TECHNICAL SITUATION ANALYSIS
SITE DESCRIPTION AND RAINFALL DATA
5.1.1 The Site
The proposed Opgoedenhoop coal mine is situated in Mpumalanga to the east of Hendrina town on
Portion 5 of the Farm OP Goedenhoop 205 IS approximately 640 ha in size. The study area is situated
to the south of the R38 between Hendrina and Carolina and to the east of the N11 between Hendrina
and Ermelo and is located within a district utilised for the cultivation of commercial crops and livestock
grazing. The location of the area is depicted in Figure 2 on the next page and the site layout is included
as Annexure B.
The site falls within the drainage area of the Komati River. The farm land is traversed by an unnamed
stream that flows from the southern boundary in a North-Eastern direction where it joins with a
stream draining the adjacent property on the eastern side. The junction is approximately 600m from
the point where the combined streams leave the property on the north-eastern boundary. The northwestern boundary of the farm consist of higher ground which form the water shed between the
stream over the property and the adjacent property to the west. There is a small dam in the upper
reaches of the stream over the site.
3
Figure 2: Site location in Mpumalanga
4
5.1.2 Wetland Assessment
As part of the Environmental Assessment and Authorisation Process, a Wetland Ecological Assessment
was conducted by Scientific Aquatic Services, Report Reference: SAS 213318 of January 2014.
Their conclusion is quoted below for reference purposes:
The SWMP takes cognisance of the findings of the report, does not comment on the possible
regulatory requirements and presents recommendations as if permission for the establishment of the
mine will be given.
5.1.3 Rainfall
Six rainfall stations are situated around the site and are listed in Table 1 . The 24 hour rainfall for the
four listed return periods are shown in the table but calculations were also run for the 1:5 and 1:20
year return periods. The rainfall data was extracted from the DESIGN RAINFALL AND FLOOD
ESTIMATION IN SOUTH AFRICA, by J C Smithers and R E Schulze, Final Report to the Water Research
Commission, WRC Project No: K5/1060, December 2002
Table 1: Rainfall Station Data
Station No
Description
24 Hour Rainfall in millimetres
MAP
(mm)
1:2
1:10
1:50
1:100
--W
Morgenster
624
49.9
77.7
105.3
118
--W
Karina
663
48.3
81.5
119.5
138.6
--W*
Hendrina (Mun)
680
54.4
84.7
114.8
128.6
--W
Klipfontein
720
52.5
81.7
110.7
124.0
--W
Tevreden
693
51.3
79.8
108.2
121.2
--W
Schoonoord
692
54.3
84.6
114.7
128.5
*Values for this rain station was used in the Utility Programs for Drainage.
5.2
METHODOLOGY
Several methods of calculating rainfall runoff peak flows and volumes are available. In keeping with
the general practice the “rational method” has been adopted for most calculations. After carrying out
test runs using alternative methods it appears that this method is best for the catchments being
analysed for this report. The rural nature of the catchments making up the mining land is well suited
to the rational method. It is an accepted method for catchments up to 15km² areas, which covers all
the catchments.
The Utility Programs for Drainage developed by the University of Pretoria and distributed by Sinotech
5
cc have been created to carry out the calculation methods used in the South African National Road
Agency Limited (SANRAL) Drainage Manual. This software has been used to generate the calculation
results presented in the appendices. The methodology for the various calculations are well known and
fully documented in the above manual and are not be repeated here. The parameters chosen for the
applicable variables form part of the calculation printouts provided in Annexure C.
The major catchment have been broken down into 3 sub catchments B, C and D to determine the
various runoffs for diversion and possible storage. The positions of these catchments are shown on
the map of water sampling points. This, together with other run-off data compiled by Digby Wells and
Associates in April 2008 are presented in Annexure D. Sub-catchments for defined areas with different
drainage characteristics such as pit and dump areas and clean, dirty and affected water areas will be
discussed based on the block plan presented in Annexure B. . Flows for these sub-catchments have
been calculated based on the software program mentioned above and flow relationships documented
in the SANRAL manual.
Various rainfall input methods are available for run-off flows. The triangular hyetograph has been
used using the relationship i = (7, 5 + 0,034 MAP) R0,3 / (0, 24 + td) 0,89 for the inland region
Where
i
MAP
R
td
is the average rainfall intensity in mm/h over time td
is the mean annual precipitation in mm
is the recurrence interval in years
is the storm duration in hours.
For run-off volumes the South African SCS 24 hour (Type 3) rainfall data and the SCS standard unit
hydrograph has been used. The rainfall values are as tabulated in Table 1 and the run-off volumes in
Table 3.
Full data files and analysis files are provided in Annexure C to this report. A summary table of the main
peak flows and run-off volumes are included in the body of the report where relevant.
It should be noted that a complete, or exact correlation of flow results between different calculation
methods is not possible. The parameters for the various methods are not directly interchangeable and
so the flows do differ. In terms of this report the “Rational Method” results for the whole catchments
are intended for general use for broad planning purposes. For the detail design of a specific structure
or drain a more project specific calculation would need to be carried out and the use of more
sophisticated analysis programs such as SWMM, HEC-RAS and ISIS are recommended.
5.3
MINING LAND, PITS AND DUMPS (ANNEXURE B)
The Site Plan included in ANNEXURE B shows the mine property with streams as well as the main
infrastructure such as roads. It also shows the extent of the planned opencast pits and underground
workings. Block indications of the major infrastructure areas such as offices, workshop, ROM pad,
weighbridge and overburden and waste dumps are shown. In general the open areas outside the
mine pit boundaries and the office area are the clean water areas, while the workshop area comprise
the dirty area. The ROM pad, overburden and waste dumps, weighbridge and the in-pit areas are the
affected water areas. The outlets of the major catchment areas are depicted in Annexure D. Please
note that some of these areas depict the initial before scenario. The scenarios during the operation
of the mine are discussed in the following section.
6
5.4
MAJOR CATCHMENTS (ANNEXURE D)
The whole property has been evaluated in terms of where storm water run-off originates and where
it discharges into the streams, or where it exits the mine property. Six catchments have been defined
in this evaluation, working from the outlet of the total catchment flow outside the northern border of
the property to the upper stretch of the stream where the flow will have to be diverted around the
open cast pit and joined with the catchment from the eastern side of the property to exit at position
A. The four catchments that model the before scenario has been numbered A to D as shown in Figure
3 which is also included as Annexure D. The catchment on the western side that needs to be diverted
past the open pit is labelled E. The open cast pit area which receives storm water directly from
downpours are labelled F and is classified as an affected water area that is to be managed together
with the ROM area, weigh bridge and dump areas.
The following short descriptions summarise the main features of each catchment and indicates where
the run-off enters the system:
5.4.1 Catchment A
Catchment A is bounded on the south-west by the high ground area, in the north west by the high
ground inside the property boundary and in the south east by the division between the site and the
adjacent property which follows the border until about 600m from the north eastern boundary where
the valley from the adjacent property joins the main flow. The flow accumulates in the valley running
south west to north east. At point C the water from the adjacent property joins the stream and flows
out of the property. Catchment A will have to be apportioned into the areas C and D where the flow
will be diverted around the open pit, E, via a cut off berm and canal 1 on the north western side of the
pit. Flow on the pit boundary past the office and workshop areas and between the dump and pit edge
is also diverted via trench 1 to point A. The open cast pit area F is to be managed with a sump in the
deepest area of the pit and pumped out to the pollution control dam for the dump, ROM pad and
weighbridge areas.
5.4.2 Catchment B
This is the part of catchment A before the junction with C and will fall away as it will be divided into
two parts, catchment D portion to be diverted and part of catchment F in the pit area.
5.4.3 Catchment C
This catchment is formed by the divide on the south eastern border and consists of two valleys on the
adjacent property that drains into the mine property at Point C and is to be diverted with the water
from catchment D via Trench 2 past the open cast area. Catchment C contains 7 small dams.
5.4.4 Catchment D
This catchment is formed by the upper reaches of catchment A and B and will have to be diverted
around the open pit via Trench 2 and isolated from the shafts and adit of the underground works.
5.4.5 Catchment E
This catchment lies on the north west border of the property and is formed by the “portion of
catchment A that is cut off by the pit area. It will be drained by a cut off drain, Trench 1, on the edge
of the pit that will flow in a south westerly to north easterly direction.
5.4.6 Catchment F
This is the operational area of the pit and will be managed by sumps and pumping to the dump/ROM
pollution control dam.
5.4.7 Other catchments
The areas north west of the divide on the border on that side of the property drains into the adjacent
7
property and does not need to be managed as part of the SWMP except to ensure that the water stays
clean and is not channelled or affected in such a way that it can damage the adjacent property.
5.4.8 Peak flows
Table 2 presents the major estimated runoffs calculated according to the rational method for the
1:50 and 1:100 year return periods. Flows for 1:5 and 1:20 year return periods have also been
calculated and is included in the results and data sets in Annexure C. The results of runoff
calculations with other calculation methods are also included in Annexure C. The full alternative
methodology has not been applied to every catchment mostly due to size constraints where the
catchments are too small. For the open pit an initial estimate, based on the area shown in Annexure
D, and a final estimate based on the pit outline on Annexure B are supplied. The runoff for the pit is
based on storm water only and does not include for any ground water.
Table 2: Major Catchments Peak Flows (m3/s)
MAJOR CATCHMENTS
5.5
RETURN PERIOD (YEARS)
2
10
50
100
A
19.04
40.04
87.62
128.78
B
9.40
19.36
42.76
63.19
C
10.68
21.99
48.52
71.67
D
6.75
10.09
30.77
45.52
E
2.35
4.86
10.78
15.97
F initial
14.33
25.48
39.20
48.06
F final
26.75
36.28
72.49
88.55
SUB-CATCHMENTS (ANNEXURE D)
The sub-catchments are classified according to the quality of runoff as follows:
Clean water – storm water run-off from open areas and low volume office/industrial
areas: Office area
Affected water – waste dump run-off with suspended solids from ore dust and
waste rock: Storm water from the pit mining area, ROM pad and weighbridge, haul
roads and waste dump.
Dirty water – polluted water containing diesel, oil or hydro carbons: Workshop
The discretization of the sub-catchments endeavours to isolate and quantify these flows.
The following detail descriptions define the catchments and Table 3 provides flows and volumes for
the sub-catchments. Although labelled as a major catchment, the pit area has also been included as a
sub-catchment due to the classification of its runoff.
5.5.1 Office area
The office area is situated to the north west of the pit mining area and is estimated to cover an area
of 2.9 hectare. Runoff from this area is from roofs, parking areas and gardens. The runoff is clean
water and the drainage system will be channelled into the cut-off drains for drainage area E, Trench
1.
5.5.2 ROM pad and weighbridge and haul roads
The ROM pad and weighbridge cover an estimated area of 0.8 ha while the haul road length is
8
estimated at about 1000m by 40 m wide (including 2 way traffic and safety berms). The runoff from
these areas are classified as affected water and needs to be contained in pollution control dams with
a sediment settling facility before the water enter the dam. The water can be left to evaporate or can
be used on the mining area such as dust control and in wash bays.
5.5.3 Opencast pit area
The pit is estimated to cover an area starting from about 50 ha to about 110 ha. The storm water
should be managed as part of the mining operational plan. It is classified as affected water. If it is
collected in a sump and pumped out it can be combined with the ROM pad and weighbridge water in
a pollution control dam.
5.5.4 Waste dump
The waste dump is estimated to start at about 6 ha. The final size of the waste dump will depend on
the mining plan and the runoff will have to be controlled as it grows. The position of the waste dump
dictates that it will require a separate pollution control dam or dams. Settling ponds is required before
the water enters the dam to prevent silting up. The runoff is classified as affected water and can be
treated as for the ROM pad etc. water.
5.5.5 Workshop
The workshop area is estimated to cover an area of about 1 ha. The water from this area, that include
the re-fuelling and lubricating areas and wash bays, are classified as dirty water. The workshop runoff
must be collected in a closed system and cycled through an oil, diesel, hydrocarbon etc. removal
facility. After the oil etc. has been removed, the remaining water can be decanted into the affected
water system for the same treatment as the ROM pad/weighbridge water.
5.5.6 Sub-catchments: Peak flows and volumes
Table 3 provides a summary of the peak flows and run-off volumes for all the sub-catchments.
Volumes have been calculated by use of the SCS peak flow for the 24 hour storm period and the
intensities presented in Table 1. The results was calculate by using the TR 55 and TR 20 SCS models
from the NRCS. The results are tabulated in Annexure E.
Table 3: Sub-Catchments, Peak Flows and Volumes
2 Yr
10 Yr
50 Yr
100 Yr
Peak
Runoff
(m³/s)
Runoff Vol
(m3)
Peak
Runoff
(m³/s)
Runoff Vol
(m3)
Peak
Runoff
(m³/s)
Runoff Vol
(m3)
Peak
Runoff
(m³/s)
Runoff
Vol (m3)
Office
0.37
573
0.63
1 996
1.01
4 780
1.25
6 300
ROM etc.
0.17
14
0.23
86
0.47
203
0.58
255
Pit initial
14.33
156 142
25.48
307 746
39.20
474 523
48.06
555 621
Pit final
26.75
305 530
36.28
602 650
72.49
924 392
88.55
-
Waste
dump
1.39
1 364
2.40
6 658
3.85
14 704
4.74
19 730
Workshop
0.21
43
0.37
191
0.59
348
0.72
430
Node
5.6
HYDROLOGICAL MODELLING
Full data files and analysis files are provided in the appendices to this report as Annexure C. A summary
table of the main peak flows and run-off volumes are included in the body of the report.
9
5.7
PREVIOUS WORK AND INFORMATION
Three reports have been made available for review of previous work namely:
Water use license application Op Goeden Hoop Colliery, May 2009, prepared by Digby Wells
and Associates.
Report on investigation to determine the potential for acid mine drainage at the proposed Op
Goeden Hoop Colliery, September 2007, prepared by Digby Wells and Associates.
Wetland ecological assessment as part of the environmental assessment and authorisation
process for a proposed colliery on portion 5 of the farm Op Goedenhoop 205 JIS, Hendrina,
Mpumalanga, January 2014, prepared by Scientific Aquatic Services CC.
The reports have been reviewed and only the Water use license mentions runoff figures for the total
catchment as being 83 m3/s at the upper and 86 m3/s at the lower reaches. No indication of the return
period is given. The reports deal mainly with issues that although important for various other
important areas of the total water use and management, fall outside the scope of the SWMP. The
Water use licence does contain recommendations on storm water and effluent management that can
be incorporated in the SWMP as applicable.
6
REQUIRED INFRASTRUCTURE AND CONCEPTUAL DESIGN
Based on the hydrological analysis performed and documented in Section 5, the conceptual
infrastructure required for managing the storm runoff is presented in the following sections. Some
indications of size and dimensions will be presented where it is deemed appropriate as an indication
of the type of infrastructure required but mostly the design of the infrastructure should be conducted
during the pre-feasibility and feasibility phases. Where conceptual sizes are supplied it will be based
on the 1:50 years return flows.
6.1
CATCHMENT D.
The runoff from this catchment needs to be diverted around the open pit. The channel (Trench 2)
should run from about the position of the current dam on the site, along the contours to the south
eastern boundary and then continue along the boundary until it meets up with the channel of
catchment area C. The excavated material from the channel should be used to construct a berm on
the pit side of the channel so that runoffs from larger storm events cannot overtop the channel on
that side and drain into the pit area.
A natural grassed channel of trapezoidal shape with 1:2 side slopes is recommended. The design flow
is 30.77 m3/s. The channel should be 5 m wide and about 2 m deep (including freeboard). The length
is approximate 2 300 m with a slope of 1.5%. Detail of the design is presented in Annexure F. The
design appears to have super critical flow so energy dissipaters should be incorporated in the detail
design stages.
6.2
CATCHMENT C
The runoff from this catchment also needs to be diverted around the open pit. The channel (Trench
3) should run from about the link with the diversion from D, along the contours of the south eastern
boundary and link up with the main channel of catchment area D. The excavated material from the
channel should be used to construct a berm on the pit side of the channel so that runoffs from larger
storm events cannot overtop the channel on that side and drain into the pit area.
10
A natural grassed channel of trapezoidal shape with 1:2 side slopes is recommended. The design flow
is 79.92 m3/s. The channel should be 15 m wide and about 2 m deep (including freeboard). The length
is approximate 1 200 m with a slope of 1.0%. Detail of the design is presented in Annexure F. The
design appears to have super critical flow so energy dissipaters should be incorporated in the detail
design stages.
6.3
CATCHMENT E
The runoff from this catchment needs to be diverted around the open pit. The channel (Trench 1)
should run from about the high point at right angles to the current dam on the north western side of
the site, along the pit to the north eastern boundary and then continue until it meets up with the
natural channel of the waterway at Point A. The excavated material from the channel should be used
to construct a berm on the pit side of the channel so that runoffs from larger storm events cannot
overtop the channel on that side and drain into the pit area.
A natural grassed channel of trapezoidal shape with 1:2 side slopes is recommended. The channel
should start with dimensions to meet a design flow of 2 m3/s and be sized progressively bigger until
the final design flow of 10.78 m3/s can be accommodated. The channel should about 2 m wide and 1
m deep and finally be 5 m wide and about 1 m deep (all depths including freeboard). The length is
approximate 3 200 m with a slope of 2.0%. Detail of the design is presented in Annexure F. The design
appears to have super critical flow so energy dissipaters should be incorporated in the detail design
stages.
6.4
OFFICE AREA
The runoff from the office area should be collected in open V drains and discharged into catchment E
in such a way as not to cause erosion. Detail design and layout should be conducted during the follow
up phases. A typical size for the drains would be 1:2 side slopes and a depth of 300 to 400 mm and a
slope of 1%.
6.5
ROM PAD, WEIGH BRIDGE AND HAUL ROADS
The runoff from the Weigh Bridge and ROM pad must be conveyed in lined channels to the pollution
control dam. A possible position for the dam is shown on Annexure B. The channel should be a lined
V drain capable of conveying 0.5 m3/s. The drain should have side slopes of 1:2, a length of about 200
m and a depth of about 400 mm.
Runoff from the haul road should be captured in side channels and conveyed to the ROM pad, work
shop, waste dump or back into the pit as is convenient. The design forms part of the next phases.
6.6
WASTE DUMP
Channels to intercept the runoff from the waste dump must be constructed on all sides of the dump.
The channels can drain to a separate pollution control dam on the north eastern corner of the waste
dump. Channels to be lined and sized to convey a flow of about 3 m3/s. It is estimated that about
1 500 m of channels with slopes around 1% will be needed in the initial phase. The channel should be
of trapezoidal shape with side slopes of 1:2, a bottom width of 2 m and a depth of 0.8 m including
freeboard.
The initial pollution control dam (PCD) should be able to contain a minimum of 14 000 m3 of water
and be lined. A silt settling pond is required before the dam and must consist of 2 chambers so that
one can always be cleaned while the other is in operation. A possible dam size would be 50 m square
and 6 m deep. If smaller dams is desired, 2 or 3 PCDs can be constructed.
11
6.7
WORKSHOP AREA
The runoff from the separate areas of the workshop area such as refuelling area, wash bay, slab
around the workshop and the workshop itself should be contained in the area itself and conveyed to
a sump with oil separator. From the sumps, after oil separation, the water can be pumped to the
pollution control dam for the ROM pad. The sizing of the channels and runoff conveyance structures,
sumps etc. is a function of the total water usage of the area and is beyond the scope of this report.
6.8
OPENCAST PIT STORM RUNOFF
The management of the pit runoff is part of the mining operation plan. For a 1 in 50 year recurrence
period the volume of water can fluctuate between 500 000 and 950 000 m3 depending on the size of
the pit and the particular mining plan being followed at any stage. The size of sump provided will
depend on the mining philosophy which will also determine the tempo of pumping, size of pumps,
size of pipes and time period to remove a specified volume of water.
6.9
POLLUTION CONTROL DAM FOR ROM PAD AND ASSOCIATED AREAS
The size of this dam is unknown as it will depend on the mine operating philosophy regarding the inpit storm runoff. The minimum size should be able to handle about 5 000 m3. Two settling ponds
before the entrance to the dam will be required with the same operating philosophy as for the waste
dump dam.
7
FEASIBILITY OF REQUIRED INFRASTRUCTURE
The storm water problem areas have been identified and compliant solutions presented in section 6.
The compliant solutions to the problems is based on effective use of funds, limited land availability,
consideration of practical solutions and cognisance of the life of mine. The different storm water
problem areas were assessed in terms of the 3 objectives of this Storm Water Management Plan
namely:
Isolate clean and dirty water
Isolate run-off contaminated with suspended solids and treat appropriately
“affected water”
Isolate dirty water, contaminated with oil, grease etc. treat and re-use
The identification of problems and solutions thereto is based on the current understanding of the
scope and layout of the proposed Opgoedenhoop mine.
7.1
ISOLATE CLEAN WATER AREAS
The Hydrological Assessment has defined three catchments that drain the mine property. These
catchments and the majority of the land for all the catchments can be classified as clean water areas.
The run-off from these areas drains via local non-perennial streams and valleys directly over the
property and finally to the Komati River. Some of the clean water discharges onto adjacent properties
without causing any problems. Catchments C, D and E fall into the clean water category and thus
comply with the requirements of GN704 and the Water Act.
The isolation and diversion of the water from these catchments have been discussed in section 6.
12
7.2
ISOLATE AND MANAGE “AFFECTED” WATER
7.2.1 Rom pad. Weigh bridge and haul roads
Isolate and contain the 1:50 year run-off volume from these “affected” areas, remove suspended
solids and re-use the water for dust suppression or evaporate as discussed in section 6.
7.2.2 Waste Dumps
If storm water from the waste dump areas of the mine is not controlled it will flow into the adjacent
clean water area downstream of the dumps. Silt from these “affected” water areas will then be
deposited on the slopes below the dumps causing otherwise clean areas to fall within the “affected”
water category. Portions of catchment E are thus affected.
As recommended in section 6, provide cut-off berms along the base of the waste dump together with
pollution control dams with settling pond facilities and re-use the water for dust suppression or
evaporate.
7.2.3 Opencast pit area.
Large volumes of storm water accumulate in the mining pit after extreme storm events and would
affect the mining activities if not managed properly.
Storm water deposited in the pit needs to be managed and re-used according to the mining
operational plan. Excess water is to be contained, re-used as appropriate, evaporated or treated and
released.
7.3
ISOLATE DIRTY WATER AND RE-USE
7.3.1 Workshop Area
Dirty water containing oil and hydro carbons emanate mainly from the workshop area and its related
vehicle washing and refuelling facilities.
Dirty water from these areas should be contained as close as possible to the source and treated in
settling ponds with attached oil separators. Storm water from surrounding areas should not be
allowed to impact on these facilities. After treatment the water can be combined with water from the
affected areas and used as appropriately.
7.4
FEASIBILITY OF THE SOLUTIONS
The infrastructure required to deal with storm water management are presented in section 6 and is
based on general accepted practices in the mining industry and complies with the requirements of GN
704 and the Best Practise Guides issued by Department of Water Affairs.
8
CONCEPTUAL DESIGN AND REVIEW
The objectives applicable to developing a new mine have been stated in paragraph 4 and the feasibility
of their application to the proposed Opgoedenhoop mine have been assessed in section 7.
The conceptual design of storm water infrastructure should be based on the following principles:
Make maximum use of existing natural drainage systems.
Maintain existing natural drainage systems to optimise flow.
Maintain existing outlets to the local water resources.
13
9
Isolate dirty water areas and design them to have as small a footprint as possible.
Prevent storm water in-flow from adjacent areas where practical possible.
Maintain and separate the systems to reduce pollution where practically possible.
Re-use water for process or dust suppression where practically possible.
Monitor and apply silt control measures where required.
CONCEPTUAL OPERATIONAL, MANAGEMENT AND MONITORING
SYSTEMS AND RESPONSIBILITIES
This section of the document discusses and provides conceptual proposals for operating, managing
and monitoring the proposed Opgoedenhoop project. The detail design of the operational,
management and monitoring systems should conform to the mining plan and is beyond the scope of
this document.
The following sections have been extracted from the water use licence application prepared by Digby
Wells and Associates in May 2009 and as such remain their intellectual property.
Water will be used in all sections of Op Goeden Hoop Colliery. The following have been identified as
activities that may impact on the water resources at the above motioned colliery:
•
Opencast areas;
•
Dirty storm water runoff from the mine and administration areas;
•
The pollution control dam;
•
Coal handling facility.
A Crisis and Emergency Management Code of Practice will be set in place which will be applied to Op
Goeden Hoop Colliery ones mining commence. Possible environmental emergency situations
identified for the various operational areas of the project area include:
•
Failure of water storage facilities and pipelines;
•
Excessive leakages in main clean water pipeline;
•
Discharge of dirty water from failure or overtopping of pollution control dam.
The following sections describe the implementation of various water management methods and
measures including water pollution prevention, storm water, groundwater, the use of potable and
mine water and the disposal of effluent.
9.1
WATER POLLUTION PREVENTION METHODS
9.1.1 Storage & handling of waste
Sewage handling during construction will be by means of portable chemical latrines, until such time
as more permanent facilities have been constructed. Chemical latrines will be serviced by an outside
contractor in accordance with local by-laws.
Septic tanks will be used during the operational phase and will be monitored and maintained in order
to ensure that it does not by any means discharge contaminated water that may affect the water
resources.
Domestic and hazardous waste originating from temporary and permanent offices and stores will go
through a waste handling and separation system and will be disposed of in appropriately authorised
landfill facilities to minimise the risk of water pollution.
A waste management system will be implemented which will make sure that domestic and hazardous
14
waste, including sewage, generated during decommissioning and closure is disposed of in a manner
that will not cause water contamination.
9.1.2 Storage and handling of hydrocarbons & explosives
A hydrocarbon management system will be introduced. Chemicals and hydrocarbons capable of
causing water pollution shall be transported, loaded and unloaded, and stored in bunded facilities,
which will be constructed in accordance with applicable legislation and SANS codes. This will minimise
the potential of accidental spillage of hydrocarbons and subsequent contamination of water
resources.
Accidental hydrocarbon spillages will be contained and remediated in situ using appropriate microbial
technologies, to prevent leaching into the water systems. An emergency spill response plan will be
developed and shall form part of the environmental awareness training.
Spillages of ammonium nitrate based explosives during charging of holes, misfires and incomplete
combustion of explosives will be monitored and managed to minimise the potential of water pollution.
9.1.3
Opencast pit area
Groundwater within the pit areas shall be pumped out immediately to the pollution control
dam.
To reduce the effects of acid mine drainage (AMD) due to surface run-off from spoils, diversion
trenches will be maintained around spoils and all run-off from spoil piles will be directed into
dirty water systems.
The occurrence of AMD as a result of the opencast mining cannot be avoided altogether. The
following methods will be utilised to minimise the severity of AMD:
o
When replacing spoils and overburden, as part of continuous rehabilitation activities,
a level of compaction will be achieved through the movement of vehicles on replaced
material. This serves the purpose of reducing the amount of air trapped in fractures
within the spoils, which reduces the oxidation potential of the material.
o
When designing and mining opencast areas, the final decant point will, as far as
possible, be kept above the level of spoil replacement. This is done in an effort to
ensure that replaced spoils are completely flooded when groundwater levels recover
to reduce the contact of spoils with air, reducing exposure to oxygen. This minimises
the oxidation of pyritic material and limits the formation of AMD.
o
During rehabilitation, the contouring of the surface will be such so as to avoid ponding
of water on rehabilitated surface to reduce the infiltration of water into areas where
spoils have been replaced and which are prone to AMD.
Create free draining surface conditions as far as possible.
If and where there is the potential for AMD contaminated pit water to decant to surface water
features, appropriate freeboard will be maintained by means of pumping arrangements.
Water decanting from the opencast workings where all spoils cannot be flooded, will be
collected and treated prior to release, unless monitoring indicates that the water quality
meets the water management objectives for the catchments. If such water does not meet
quality objectives, it may also be pumped back to underground workings in order to make it
15
part of the inter mine flow.
A dense vegetative cover will be established and maintained on rehabilitated areas to assist
with the evapotranspiration of rain water in an effort to reduce the infiltration of water into
rehabilitated spoils.
9.1.4 Pollution control dam
The pollution control dams will be operated as storage and evaporation dams, with some of the water
used for dust suppression. The dam will be operated to ensure that the storage capacity is not
exceeded in normal rainfall events.
9.1.5 Transporting coal
Trucks transporting coal on access roads in the area and along the planned access road to the crushing
and washing plants will be covered. This will reduce any spillages of coal from access trucks, which
may affect surface water quality
9.2
GROUNDWATER MANAGEMENT
9.3
MINIMISATION AND REUSE OF MINE WATER
9.4
The removal of vegetation during topsoil and overburden stripping will be minimised as far as
possible to increase the recharge of rain water to aquifers.
The dewatering of aquifers during the operation of opencast is implicit in the types of mining
involved and cannot be prevented. Where such dewatering causes the drying up of boreholes
used for domestic, stock-watering and other uses, alternative supplies of water will be
provided on a case-by-case basis
Pollution control facilities will be maintained until closure and decanting from pits and
underground workings will be prevented as far as possible.
After mining has ceased underground workings will be flooded and water in the mine will
exclude oxygen from the underground workings and the pH of the mine water will be neutral
after the flooding phase. Most heavy metals are insoluble at a neutral pH. Manganese and
iron are the only ones that would be present at levels higher than the permissible limits,
considering the South African Drinking Water Standards.
Groundwater will continue to be monitored for a minimum of five years after closure and data
will be submitted to the authorities.
The amount of water used for dust suppression will be minimised by the use of road surface
sealants.
Groundwater will be used if additional water is required for the Op Goeden Hoop mining
operations. Only potable water will be used for the office buildings and change house.
However, if any additional water be required authorities will be informed accordingly.
The potable water system is primarily for domestic use. Domestic water after use can be
classified as industrial water and uses for various other purposes or pump to the pollution
control dam or septic tank system. However, the most fundamental principal will be to
prevent utilising freshwater in the mining processes and to increase the amount of water
recycled.
Other water use minimisation strategies that will be implemented at Op Goeden Hoop colliery
will include launching of an awareness campaign and fixing of leaking pipes, taps, etc.
EFFLUENT TREATMENT METHODS
Contaminated excess mine water arising from the opencast pit will be handled in the pollution control
dam.
16
9.5
PROPOSED DISPOSAL OF EFFLUENT
Polluted water resulting from the mining operation at Op Goeden Hoop (site runoff, undergroundwater, industrial water and opencast water) will also be stored in a pollution control dam and will be
used for dust suppression on access roads and other denuded areas. This water will be kept in the
pollution control dam where it will evaporate, a closed dirty water system, unless the storage capacity
of the dam is exceeded and the volume necessitates the discharge of effluent into the surface water
body. This, however, might only occur in rainfall events outside of the norm and will be treated as an
emergency incident.
The pollution control dam is not expected to discharge into the environment, unless unusually high
rainfall is experienced.
Water quality in the pollution control dams will have slightly higher sulphates and heavy metal
contents than the recommended DWAF guidelines.
10 STORM WATER MANAGEMENT PLAN
This Storm Water Management Plan describes the infrastructure to be established and the
management of storm water required to effectively deal with the storm water problems at the
proposed Opgoedenhoop mine while taking into account:
The terrain and topography of the mine
What is practical possible
The following general management principles are presented:
The removal of vegetation during the construction phase will be kept to a minimum,
which will decrease the erodibility of soils thus minimising the effects of silt loading
of surface water running over exposed soil.
The establishment of dirty water areas will be planned and monitored in order to
minimise the effects of reducing the catchment size so that surface water will be
able to flow into surface streams.
Dirty water areas such as stores and storage facilities will be constructed to have the
smallest possible footprint, thus reducing the reduction in catchment yield.
Storm water diversion and pollution control facilities will be constructed to divert
the flow of water and ensure the separation of clean and dirty water on site. All such
facilities will be constructed in such a manner as to handle a 1:50 year storm event.
Where a concentration of water occurs during rain event as a result of the
existence/operation of hard paved areas, energy diffusers will be installed to reduce
water velocity and to mitigate the effects of increased surface water volumes in such
areas.
Profiling the final topography by means of the establishment of drainage ridges or
canals in a manner which will ensure that areas which use to drain to the streams
continue too. An effort will be made to effect drainage into the tributaries as high up
their respective courses as is possible to attempt to maintain wetland integrity.
17
10.1 ISOLATION OF CLEAN WATER AREAS
10.1.1 Isolation of clean water from Catchment D
Problem:
The major portion of catchment D lies upstream of the opencast areas and therefore
this clean water flows into the pit where it will be contaminated and interfere with the mining
operation.
Proposed Plan
Construct a diversion channel around the pit area as described in section 6.1.
Isolate the shafts and adit of the underground mining operation with berms around
them to prevent the ingress of storm water.
10.1.2 Isolation of clean water from Catchment C
Problem:
The existing channel for catchment C joins the main water course in the area where
the opencast mining will take place and must be isolated.
Proposed plan:
Design and construct a diversion channel around the pit area as described in section
6.2 to also accommodate the extra flow from catchment D.
10.1.3 Isolation of clean water from Catchment E
Problem:
Catchment E drains towards the main water course in the area where the opencast
mining will take place and must be isolated.
Proposed plan:
Design and construct a diversion channel around the pit area as described in section
6.3.
10.1.4 Handling of clean water from the office area
Problem:
The office area will increase runoff from the area due to the increase in impervious
areas and will drain towards the pit area.
Proposed plan:
Design and construct collection drains as described in section 6.4 and direct into the
channel for catchment E.
10.2 ISOLATE AND TREAT “AFFECTED” WATER
10.2.1 Silt laden water from the weigh bridge, ROM pad and haul roads
Problem:
Silt will be washed down from the material spillages during the handling of the coal
and must be prevented from contaminating clean water
Proposed plan:
Design and construct lined channels and convey the runoff to the pollution control
dam as described in section 6.5.
Implement operational procedures to minimise the material spillage.
10.2.2 Waste Dumps
Problem:
Storm water from the waste dump area of the mine flows into the adjacent clean
water areas downstream of the dumps. Silt from these “affected” water areas is then deposited on
the slopes below the dumps causing otherwise clean areas to fall within the “affected” water category.
Portions of Catchments E and A are thus affected.
18
Proposed plan:
Construct cut –off berms around the waste dump as presented in section 6.6.
Construct a pollution control dam(s) with silt traps as detailed in section 6.6.
Provide regular clearance and maintenance of the facility.
10.2.3 Storm water runoff and flooding in the opencast pit
Problem:
Runoff from storm water falling directly on the mine pit cannot be diverted out of the
pit and interfere with mining operations. The volumes can be substantial.
Proposed plan:
Compile operational procedures for the mining on the strategy and philosophy of
dealing with the inflows.
Provide a sump and pumping equipment to deal with the inflow as described in
section 6.8.
10.2.4 Pollution control dam for the ROM pad. Pit and workshop areas
Problem:
The affected water from these areas must be treated in a pollution control dam with
silt traps but the size of the dam cannot be determined until the mining operation procedure for
dealing with inflows is known.
Proposed plan:
Compile operations procedures for the mine to be able to size the dam and facilities.
Maintenance and effective management of the pollution control structures will deal
with the problem effectively.
10.3 ISOLATE DIRTY WATER AND RE-USE
10.3.1 Workshop Areas
Problem:
Dirty water containing oil and hydro carbons emanate from the workshop areas and
the related vehicle washing and refuelling facilities.
Proposed plan:
Construct oil separation facilities and sumps as described in section 6.7.
Prepare operational procedures to manage oil pollution and prevention.
After oil separation decant the water to the pollution control dam as described in
section 6.7.
Perform regular cleaning and maintenance activities.
10.4 MAINTENANCE AND OPERATING PROCEDURES
10.4.1 Storm water Drainage System
The storm water systems on the mine will need regular maintenance to remain fully operational. This
requires that a visual inspection of the systems be carried out at least twice a year, once at the
beginning of the rainy season early in September, then early in the new year to confirm that it is still
working correctly. The visual inspection must include:
Surface water channels
Covered drains
Catch pits and Manholes
Inlets and outlets of culverts
Drainage pipes
Any blockages caused by siltation or debris needs to be cleared, especially in the larger open channels,
if growth of grass or reeds has taken hold in the deposited silt which can consolidate the blockage.
19
Minor siltation can usually be left as the first good rains will flush the system out. The follow up
inspection will verify this.
10.4.2 Settling Ponds
The level of silt deposit in the settling ponds needs to be monitored on a regular basis. The de-sludging
or removal of the silt must be part of the operational procedure of the plant. It must be taken to a
waste disposal area where it can dry out for possible later re-use.
10.4.3 Return Water Sumps
Although not directly related to storm water the operation of the pumps and return water sumps also
need to be monitored on a regular basis to keep the system running. Too much silt in the settling
ponds limits the through time of the return water and thus also the effectiveness of the settling
process.
10.4.4 Waste Dump Run-Off and Siltation
As detailed in paragraph 6.4 silt deposition from the waste dump run-off can be a major concern on
the mine. The maintenance and monitoring of the storm water berms as constructed is an on-going
task. The level of silt in the dams needs to be checked at regular intervals especially after large storms
to make sure they are carrying out their function of trapping the silt and that they still have some
capacity available. If capacity becomes limited, plans must be made to remove the silt. The overflows
need to be checked for stability and scour and also for evidence of silt passing through the dam, which
will show the effectiveness of the operation.
An assessment also needs to be made from time to time on the general dump run-off and siltation
occurring and whether new storm water berms need to be provided to control the situation. This
relates also to the dump stability, the amount of scour occurring on the dump face and whether the
dump is still active or consolidating. If the dump is not growing then siltation will become less and
cleaner run-off will result requiring less control and management.
10.4.5 Pits
The operating procedure for controlling storm water within the pit and the maintenance thereof is
very much related to the mining operation itself. The position of the sump to collect the storm water
will change as the pit excavation progresses. Pumping options should be in place to manage water
within the pit and maintain continuity of the mining operation.
10.5 MONITORING PROGRAMME
Monitoring of the environmental impact caused by the mining operation should be in accordance with
the Water Use License requirements. A water sampling procedure should be compiled. Both surface
water and ground water are to be monitored on a quarterly basis. The monitoring positions is to be
decided and the work carried out by the office of the Environmental Manager. External laboratories
should be used to analyse water samples and they are to be measured against S.A water quality
guidelines. The results will be included in the annual DWA report. Water consumption is also
monitored and used to compile the water balance.
10.6 MANAGEMENT STRUCTURE
A functional management structure need to be developed for the mine. Overall responsibility rests
with the General Manager and then the departmental managers
20
11 MINE CLOSURE
In terms of the Storm water Management Plan the cessation of operations should also bring an end
to the generation of dirty water or the risk of any pollution. When waste dump deposition stops,
siltation should get less and cleaner run-off from the dumps should ensue. Monitoring of this run-off
should show whether further monitoring after closure would be required.
12 RELEVANT DOCUMENTATION
The following reference documents have been used:
National Water Act, 1998 (Act 36 of 1998)
DWAF Regulation GN704
DWAF Operational Guideline No.M6.1 – Regulations on use of water for mining and
related activities – May 2000
DWAF Best Practice Guidelines
o
o
o
A5 – Water Management for Surface Mines
G1 – Storm Water Management
H3 – Water Re-Use and Reclamation
13 RECOMMENDATIONS
Maintain new constructed storm water facilities. (Housekeeping of the settling ponds, oil separators
and process water systems.)
Implement the proposed solutions.
Monitoring of the surface and underground water form an integral part of storm water management.
A comprehensive storm water design to be undertaken with the detail design of the mine
infrastructure.
The storm water management plan to be reviewed when the mine closure plan is implemented.
_______________________
S PRINSLOO
Reviewer
20 September 2014
L AUCAMP
Compiler
20 September 2014
21
14 ANNEXURE A – WORKPLAN FOR OPGOEDENHOOP SWMP
1. Prepare base plans and gather existing information
Review drawings prepared for previous WULA applications
and Storm Water Management Plans
Review WULA application prepared by Digby Wells and
Associates in 2009 and extract information that has not been
changed for further use.
Review the Wetland Assessment, Acid Based activity and
Ground water monitoring reports prepared by Scientific
Aquatic Services and Digby Wells and Associates
respectively for Information and recommendations that can
be utilised going forward.
Review the Infrastructure Block Plan according to the latest
‘Google’ aerial photography
Review drawings created for the reports mentioned above
and obtain permission for use of copy right/intellectual
property in new reports
Obtain and collate information regarding current EIA, WULA
and water balance investigations conducted by other parties
and integrate
Deliverable:
Set of existing drawings and information to help define
objectives of the Conceptual Storm Water Management Plan
and to include in the Storm Water Management Plan Report
2. Data and Information evaluation
Confirm clean and dirty water areas on the mine using the
latest info and make allowance for changes in the following
phases
Review proposed designs of storm water infrastructure and
update with any improvements added since the previous
reports as mentioned above.
Confirm delineation of sub-catchments taking into account
changes that have taken place on the mine design and
conceptual layouts.
Incorporate information into reports and drawings where
changes have taken place.
Deliverable:
3.
Inputs into drawings and reports by other consultants
showing existing and proposed infrastructure and catchment
delineation to be used for Technical situation analysis and
evaluation.
Conceptual Design and Verification of Data
Liaise with the Mining Consultant and through them with the
other “water” and EIA consultants to verify all information
compiled in sections 1 and 2 above.
Prepare high level reviews of climate, topography, land use
and proposed alternative uses of different areas as proposed
in previous studies and current studies by other consultants
Prepare conceptual design standards for run-off, demarcation
of clean and dirty areas, sizes of pollution control dams,
22
canals and cut-off structures, oil and other pollutant control
measures and management philosophies.
Deliverables:
4.
Design standards to be used for conceptual design and
management strategies for further investigations
Define infrastructure requirements
Define physical structures that is required to manage the
storm water run-off
Define the control and pollution management requirements.
Deliverables:
5.
Guidelines for conceptual design and inputs to the follow-up
more detail design studies
Undertake Conceptual Design
Measure areas, lengths and slopes of the main catchments
for use in Hydrological Analysis software to obtain peak runoffs.
Use various Method to calculate flows for the main
catchments of the mining land.
Calculate indicative sizes for diversion canals around the
mining area, cut off berms and canals.
Indicate sizing of pollution control dams and control measures
based on the available information
Deliverables:
6.
Input variables to the conceptual Storm Water Management
Plan
Define conceptual operational, management, monitoring
procedures and systems
Define minimum operational requirements and systems.
Provide inputs for design of monitoring procedures and
systems
Deliverable:
7.
Minimum management, operational and monitoring
requirements for a conceptual Storm Water management
Plan.
Design of Storm water System
Collate all drawings, other information and calculations to
prepare a basic storm water concept for the mine which will
address the following issues:
o Delineation of clean and dirty water areas
23
o
Provide input on flow routing of clean water to bypass
mining operations and plant and workshop
infrastructure to natural water courses
o Assess methods to deal with dirty water areas in the
plant and
o Propose high level infrastructure changes required by
the conceptual storm water design
o Provide input on the design and size of drainage
structures such as settling ponds and pollution control
dams etc.
Deliverable:
All conceptual info, calculations, designs and systems that go
to make up the conceptual Storm Water Management Plan.
24
15 ANNEXURE B – SITE PLAN
25
16 ANNEXURE C – CALCULATION RESULTS AND DATA SETS
16.1 CATCHMENT A
26
16.2 CATCHMENT B
27
16.3 CATCHMENT C
28
29
30
16.4 CATCHMENT D
31
32
33
16.5 CATCHMENT E
34
35
36
16.6 CATCHMENT F – PIT AREA INITIAL AND FINAL
37
38
16.7 CATCHMENT OFFICE AREA
39
16.8 CATCHMENT ROM PAD, WEIGH BRIDGE AND HAUL ROAD AREAS
40
16.9 CATCHMENT WASTE DUMP AREA
41
16.10 CATCHMENT WORKSHOP AREA
42
17 ANNEXURE D – GENERAL MAPS SHOWING RUNOFF AND CATCHMENT AREAS
43
18 ANNEXURE E – VOLUME CALCULATIONS FOR THE SUB-CATCHMENTS
Calculated from SCS standard unit hydrograph with TR 55
and TR 20
Opgoedenhoop
Volumes for the sub catchments
1. Office
return period
yr
Peak flow
Time of
hydrograph
Time of
hydrograph
hr
seconds
Volume V m3
2. ROM pad, weighbridge
return period
yr
Peak flow
Time of
hydrograph
hr
Time of
hydrograph
seconds
Volume V m3
2
0.36
10
0.57
50
0.77
100
0.87
0.884
1.945
3.449
4.023
3182.4
7002
12416.4
14482.8
572.832
1995.57
-
-
2
0.06
10
0.12
50
0.17
100
0.2
0.133
0.398
0.663
0.708
478.8
1432.8
2386.8
2548.8
14.364
85.968
202.878
254.88
2
0.49
10
0.94
50
1.4
100
1.61
1.547
3.935
5.835
6.808
5569.2
14166
21006
24508.8
-
6658.02
14704.2
-
2
0.09
10
0.16
50
0.23
100
0.27
0.265
0.663
0.84
0.884
3. Waste dump
return period
yr
Peak flow
Time of
hydrograph
Time of
hydrograph
hr
seconds
Volume V m3
4. Workshop
return period
yr
Peak flow
Time of
hydrograph
hr
44
Time of
hydrograph
seconds
Volume V m3
954
2386.8
3024
3182.4
42.93
190.944
347.76
429.624
2
5.59
10
9.84
50
14.03
-
15.518
17.375
18.79
19.365
55864.8
62550
67644
69714
-
307746
-
-
2
10.49
10
18.47
50
26.34
-
16.181
18.127
19.497
19.939
58251.6
65257.2
70189.2
71780.4
-
-
-
-
-
-
-
-
5. Pit initial
return period
yr
Peak flow
Time of
hydrograph
Time of
hydrograph
hr
seconds
Volume V m3
6. Pit final
return period
yr
Peak flow
Time of
hydrograph
Time of
hydrograph
hr
seconds
Volume V m3
Summary Volumes m3
return period
yr
1. Office
2. ROM pad, weighbridge
3. Waste dump
4. Workshop
5. Pit initial
6. Pit final
45
19 ANNEXURE F – CONCEPTUAL DESIGN CALCULATIONS FOR SELECTED AREAS
Normal Flow Analysis - Trapezoidal Channel
Opgoedenhoop
Project:
Project:
Channel
ID:
Area D diversion channel
Channel ID:
Design Information (Input)
Channel Invert Slope
So
=
0.0150
Manning's n
n=
0.0260
Bottom Width
16.4042
Right Side Slope
B=
Z1
=
Z2
=
Freeboard Height
F=
3.28
Design Water Depth
Y=
3.94
Left Side Slope
ft/ft
0.02
m/m
0.03
ft
5.00
m
2.0000
ft/ft
2.00
m/m
2.0000
ft/ft
2.00
m/m
ft
1.00
m
ft
1.20
m
Normal Flow Condition (Calculated)
Q
=
Fr
=
Discharge
Froude Number
-
Flow Velocity
V=
13.98
Flow Area
A=
Top Width
Wetted Perimeter
Hydraulic Radius
Hydraulic Depth
Specific Energy
Centroid of Flow Area
Specific Force
46
cfs
37.82
m3/s
1.43
4.26
m/s
95.58
fps
sq
ft
8.88
m2
T=
32.15
ft
9.80
m
P=
R
=
D
=
Es
=
Yo
=
Fs
=
34.01
ft
10.37
m
2.81
ft
0.86
m
2.97
ft
0.91
m
6.97
ft
2.12
m
1.75
ft
0.53
m
46.67
kip
207.62
kN
Normal Flow Analysis - Trapezoidal Channel
Opgoedenhoop
Project:
Project:
Channel
ID:
Area C diversion channel
Channel ID:
Design Information (Input)
Channel Invert Slope
So
=
0.0100
Manning's n
n=
0.0260
Bottom Width
49.2126
Right Side Slope
B=
Z1
=
Z2
=
Freeboard Height
F=
3.28
Design Water Depth
Y=
3.94
Left Side Slope
ft/ft
0.01
m/m
0.03
ft
15.00
m
2.0000
ft/ft
2.00
m/m
2.0000
ft/ft
2.00
m/m
ft
1.00
m
ft
1.20
m
Normal Flow Condition (Calculated)
Q
=
Fr
=
Discharge
Froude Number
-
Flow Velocity
V=
12.87
Flow Area
A=
224.75
Top Width
T=
Wetted Perimeter
P=
R
=
D
=
Es
=
Yo
=
Fs
=
Hydraulic Radius
Hydraulic Depth
Specific Energy
Centroid of Flow Area
Specific Force
47
cfs
81.86
m3/s
1.22
fps
sq
ft
3.92
m/s
20.88
m2
64.96
ft
19.80
m
66.82
ft
20.37
m
3.36
ft
1.03
m
3.46
ft
1.05
m
6.51
ft
1.98
m
1.88
ft
0.57
m
98.48
kip
438.05
kN
Normal Flow Analysis - Trapezoidal Channel
Opgoedenhoop
Project:
Project:
Channel
ID:
Area E diversion channel start
Channel ID:
Design Information (Input)
Channel Invert Slope
So
=
0.0200
Manning's n
n=
0.0260
Bottom Width
6.5617
ft
2.00
m
2.0000
ft/ft
2.00
m/m
Right Side Slope
B=
Z1
=
Z2
=
2.0000
ft/ft
2.00
m/m
Freeboard Height
F=
1.64
ft
0.50
m
Design Water Depth
Y=
1.64
ft
0.50
m
144.61
cfs
4.09
m3/s
Froude Number
Q=
Fr
=
Flow Velocity
V=
8.96
Flow Area
A=
Top Width
Left Side Slope
ft/ft
0.02
m/m
0.03
Normal Flow Condition (Calculated)
Discharge
1.42
1.42
2.73
m/s
16.15
fps
sq
ft
1.50
m2
T=
13.12
ft
4.00
m
Wetted Perimeter
P=
13.90
ft
4.24
m
Hydraulic Radius
R=
1.16
ft
0.35
m
Hydraulic Depth
D=
Es
=
Yo
=
Fs
=
1.23
ft
0.38
m
2.89
ft
0.88
m
0.73
ft
0.22
m
3.25
kip
14.44
kN
Specific Energy
Centroid of Flow Area
Specific Force
48
Normal Flow Analysis - Trapezoidal Channel
Opgoedenhoop
Project:
Project:
Channel
ID:
Area E diversion channel end
Channel ID:
Design Information (Input)
Channel Invert Slope
So
=
0.0200
Manning's n
n=
0.0260
Bottom Width
16.4042
Right Side Slope
B=
Z1
=
Z2
=
Freeboard Height
F=
1.64
Design Water Depth
Y=
1.97
441.80
Froude Number
Q=
Fr
=
Flow Velocity
V=
11.03
Flow Area
A=
Top Width
Left Side Slope
ft/ft
0.02
m/m
0.03
ft
5.00
m
2.0000
ft/ft
2.00
m/m
2.0000
ft/ft
2.00
m/m
ft
0.50
m
ft
0.60
m
Normal Flow Condition (Calculated)
Discharge
cfs
1.51
12.51
m3/s
1.51
3.36
m/s
40.04
fps
sq
ft
3.72
m2
T=
24.28
ft
7.40
m
Wetted Perimeter
P=
25.21
ft
7.68
m
Hydraulic Radius
R=
1.59
ft
0.48
m
Hydraulic Depth
D=
Es
=
Yo
=
Fs
=
1.65
ft
0.50
m
3.86
ft
1.18
m
0.92
ft
0.28
m
52.29
kN
Specific Energy
Centroid of Flow Area
Specific Force
49
11.75
kip