REPUBLIC OF KENYA
MINISTRY OF LANDS, PUBLIC WORKS, HOUSING AND URBAN
DEVELOPMENT.
State Department For Public Works
Electrical Engineering Directorate
MINUTES OF THE HANDOVER SITE MEETING HELD ON MONDAY 12TH JUNE, 2024 AT
UTALII HOTEL, RUARAKA, NAIROBI KENYA.
CLIENT:
Kenya Utalii College (KUC)
PROJECT:
Proposed Supply, Installation, Testing And
Commissioning of 1 No. Passenger Lift.
PROJECT NUMBER:
W.P ITEM NO. D1202 NB/NB/2202 JOB. NO. 11145A
PROJECT MANAGER:
Works Secretary
CONTRACTOR:
M/s Top Choice Surveillance Ltd,
P.O. Box 1218 – 00618,
NAIROBI.
CONTRACT DATA
Commencement Date:
Contract Period:
Completion Date:
Site Possession Date:
-14th June, 2023 (As per Contract Agreement)
- 52 (Fifty-two) Weeks
- 13th June, 2024.
- 3rdAugust, 2023.
COST DATA
Contract Sum:
Amount Certified to Date:
% of Amount Certified:
-Kshs. 6,763,789.00 (Inclusive of VAT)
-Kshs. 6,113,789.00
-90.39%
PROGRESS
Contract Period:
Contract Period Elapsed:
% of Works physically done:
% of Contract Period elapsed:
- 52 (Fifty-two) weeks
- 52 (Fifty- two) weeks
- 100%
- 100%
1
ATTENDANCE
Present-.
NAME
Eng. Stephen C. Gitonga
Eng. Samuel Ndirangu
Anthony Mbehelo
Peter Muindi
Peter Ngugi
William Ohowa
Rosalind Gicheru
Judy Nyakundi
Joshua Ambwere
John K. Ndung’u
Patricia W. Gitau
Charles Obure
Lydia Wanyonyi
Dennis Kuria
Peter Ndegwa
Mbati Kamuyu
Irene Chepkangor’
Jeniffer Maina
Jane Kawira
Patrick Ngaara
Najai Osemo
Absent with Apology
1) Omondi Justin
ITEM
Min 1.00
ORGANIZATION
SDPW
SDPW
KUC
KUC
KUC
KUC
KUC
KUC
KUC
TOP CHOICE
KUC
TOP CHOICE
TOP CHOICE
SDPW
KUC
KUC
KUC
KUC
KUC
KUC
KUC
KUC
DESIGNATION
P.M.R (Chairing)
P. E. E.
Client (C. E. O.)
Client
Client
Client
Client
Client
Client
Contractor
Client
Contractor
Contractor
E. E. Intern
Client
Client
Client
Client
Client
Client
Client
Client
AGENDA
CELL-
-
ACTION /NOTE
INTRODUCTION
1.01 The Chair (P. M. R.) called the meeting to order at 1100hrs. A All
ceremony to officially commission the lift for daily hotel operations
followed after the brief meeting. The chair then called back the
meeting for further deliberations.
1.02 The agenda adopted for the meeting was as follows;
• Reading and Confirmation of minutes
• Matters Arising
• Reports
o Client
o Contractor
o Project Manager
• A.O.B
2
All
ITEM
Min 2.00
AGENDA
READING AND CONFIRMATION OF MINUTES
ACTION /NOTE
2.01 The minutes of the previous meeting were read and confirmed as a Info
true record of the meeting. The minutes were proposed by Judy
Nyakundi and seconded by Charles Obure.
Min 3.00 MATTERS ARISING
3.01 The water pipe running through the machine room has not been re- Client
routed.
3.02 The Contractor reported that they had carried out another training Contractor
as instructed by the PM. However, the Contractor was instructed by
the PM to provide them with a copy of the contents of training.
3.03 The PM reported that additional works were awaiting Client’s Client
response.
Min 4.00 REPORTS
4.01 CLIENT’S REPORT
4.01.01 Informed the meeting that the arrival sound volume of the lift was
high and needed to be reduced.
Contractor
4.01.02 Informed the meeting that there is need to adjust the lift car floor Contractor
level to align with the second floor level.
4.01.03 Requested whether it was possible to introduce advertisement Info
screens in the lift car. Upon which the Contractor informed the
meeting that once the Client procures the advertisement screens they
would know how to install and supply the power needed.
4.01.04 Requested whether it was possible to introduce advertisement in the Info
background music.
4.01.05 Reported that they were happy with the delivery of the project Info
within time.
4.01.06 They indicated that this was a milestone within the institution that Info
will go along way in delivery of services to their customers.
3
ITEM
AGENDA
ACTION /NOTE
4.01.07 Thanked all participants for timely delivery of the project i.e. Project Info
Manager’s team, Contractor’s and of the Client representatives.
4.01.08 Promised to pay the Contractor on receipt of the Voucher as per the Client
contract requirements.
4.02 CONTRACTOR’S REPORT
4.02.01 Promised to follow up on the Client’s request for background Info
advertisement with the manufacturer to find out the possibility of
changing the lift song to background advertisement.
4.02.02 Informed the meeting that they had applied for 2nd payment.
Info
4.02.03 Informed the meeting that they would deliver the hand over Contractor
documents by 13th June, 2024 to the PM for onward forwarding to
the relevant parties.
4.03 PMR’S REPORT
4.03.01 Thanked all i.e. Contractor’s and Client’s team for teamwork during Info
the implementation of the project.
4.03.02 Reported that the commissioning document would be shared with PMR
the Client once it is finalized.
4.03.03 Informed the meeting that the handover and practical completion Info
date was 12th June, 2024 and that the defects liability period will run
for one year from 13th June,-nd payment certificate already processed and would be delivered to Info
the Client on 12th June,- Still awaiting response on painting and waterproofing works from Client
the Client.
4.03.06 Promised to issue a maintenance tender document to the Client for PMR
their use.
4.03.07 Advised the Client the need to urgently re-route the water pipe.
4
Client
ITEM
Min 5.00
AGENDA
ACTION /NOTE
A.O.B.
5.01.01 The Contractor informed the meeting that he would recall the Info
performance bond.
5.01.02 There being no other business the meeting was adjourned at 1220hrs. Info
Minutes Compiled by: Dennis Kuria
Minutes Checked by;
Eng. Samuel Ndirangu
Date:
Date:
Signature:
Signature:
Minutes Approved for Circulation;
Name:
Date:
Signature:
5
DISTRIBUTION LIST
❖ The Principal
1
Kenya Utalii College
❖ Works Secretary
1
❖ Chief Engineer (Electrical)
1
❖ M/s Top Choice Surveillance Ltd
P.O. Box 1218 – 00618,
NAIROBI
1
❖ All present
9
TOTAL
13
6