NOTES
general
This drawing is to be read in conjuction with engineers' drawings
All dimensions are in mm unless otherwise specified.
drawings are not to be scaled. Only figured dimensions to
to be used. The contractor must check & verify all the
dimensions before commencement of the work.
construction
All slabs at ground level to be layed over 1000 gauge
polythene sheeting on 50mm thick murram blinding,on
well compacted hardcore. All soils under slabs & around
external foundation to be poised for the termites control.
structural
All black cotton soil to be removed from below all
building & paved surfaces. All paved surfaces to be
clear of black cotton soil to a distance of 500m
outside the edge of the surface.
For all R.C works, refer to SE's details.
Foundation depths to be determined on site to the SE
approval. All walls less than 200mm thick to be reinforced
with hoop iron at every alternate course.
All adjacent R.C work and masonry walls to be tied
with strap irons at every course.
WC
WC
mechanical
D2
All plumbing & drainage work to comply with P.H specifications.
All surface ducts to be accessible from all floors.
S.V.P denotes soil vent pipe and to be provided at the head of
the drainage. Drains passing beneath buildings and driveways
to be encased in 150mm concrete sorround. All underground
foul & waste drain pipes shall be of PVC. to comply with BS5255.
All inspection chambers covers and framing shall be cast iron
to comply with BS.497 Table 2 Grade A.
The storm water drain pipes to comply with BS. 556.
Minimum slope in the drain pipes to be 1%
No chases for pipes will be allowed in the slabs.
Sleeves will be allowed with written approval from the SE
No cutting of concrete without express approval of the Architect.
or SE. All testing of pipes must be cordinated with electrical
& any conflicts must be clarified before works begins.
P.V denotes permanent vents.
GENTS
400x400mm non-slip
ceramic tiles
Continous Urinal Trough
150mm thick wall at 2,200mm height
D2
WC
LADIES
electrical
400x400mm non-slip
ceramic tiles
All conduits must be laid before plastering.
Ceiling height - 2,800mm
fire fighting
Provide a 1130 litres reserve tank with a booster pump
Dry risers
Provide a 1x30m hydraulic Hose-real, on every floor.
\Provide manual/ electric break glass fire alarm system.
Provide 4x9kg litres water CO2 fire extingushers on every floor
WHB
WHB
revisions
D3
D3
LOBBY
LOBBY
STORE
Metal grille internally
inlcusive of the ceiling
Ceiling height - 2,600mm
LOBBY
Ceiling height - 2,600mm
Terrazzo flooring
W3
D1
W3
D1
SERVICE DUCT
D1
LEC. PREP ROOM
SECRETARY
D1
Carpet tiles 400x400mm
W4
KITCH.
CLASS 03
D1
CLASS 01
STAFF ROOM
Ceiling height - 3,300mm
Tile flooring
Wood parquet floor
granite top
CLASS 02
DIRECTOR'S OFFICE
Carpet tiles 400x400mm
200mm thick masonary walling
Ceiling height - 3,300mm
D1
Terrazzo flooring
Dry wall in gypsum
W2
W2
W2
W2
W1
W1
project
PROPOSED INTERIOR PARTITIONING
WORKS KENYA FILM SCHOOL AT
KASARANI STADIUM COMPLEX
MAIN SECTION POWER, TV, DATA AND FIRE LAYOUT
KASARANI, NAIROBI
drawing title
client ministry/department
MAIN SECTION - PROPOSED LAYOUT
MINISTRY OF YOUTH AFFAIRS, THE
ARTS AND SPORTS
client signature
1
scale
2
3
project job no.
drawing no.
name
S. Architect
KAFUNA
Drawn by
KAFUNA
PSA. Architect
Arch. J Murigu
signed
date
February, 2024
APPROVED Arch. L Mochama
CHIEF ARCHITECT
MINISTRY LANDS, PUBLIC WORKS,
HOUSING , AND URBAN
DEVELOPMENT
STATE DEPARTMENT OF PUBLIC WORKS
ARCHITECTURAL DEPARTMENT
FOR THE GOVERNMENT OF THE
REPUBLIC OF KENYA
GSPublisherVersion-