NOTES
general
This drawing is to be read in conjuction with engineers' drawings
All dimensions are in mm unless otherwise specified.
drawings are not to be scaled. Only figured dimensions to
to be used. The contractor must check & verify all the
dimensions before commencement of the work.
construction
All slabs at ground level to be layed over 1000 gauge
polythene sheeting on 50mm thick murram blinding,on
well compacted hardcore. All soils under slabs & around
external foundation to be poised for the termites control.
structural
All black cotton soil to be removed from below all
building & paved surfaces. All paved surfaces to be
clear of black cotton soil to a distance of 500m
outside the edge of the surface.
For all R.C works, refer to SE's details.
Foundation depths to be determined on site to the SE
approval. All walls less than 200mm thick to be reinforced
with hoop iron at every alternate course.
All adjacent R.C work and masonry walls to be tied
with strap irons at every course.
mechanical
A
All plumbing & drainage work to comply with P.H specifications.
All surface ducts to be accessible from all floors.
S.V.P denotes soil vent pipe and to be provided at the head of
the drainage. Drains passing beneath buildings and driveways
to be encased in 150mm concrete sorround. All underground
foul & waste drain pipes shall be of PVC. to comply with BS5255.
All inspection chambers covers and framing shall be cast iron
to comply with BS.497 Table 2 Grade A.
The storm water drain pipes to comply with BS. 556.
Minimum slope in the drain pipes to be 1%
No chases for pipes will be allowed in the slabs.
Sleeves will be allowed with written approval from the SE
No cutting of concrete without express approval of the Architect.
or SE. All testing of pipes must be cordinated with electrical
& any conflicts must be clarified before works begins.
P.V denotes permanent vents.
D
electrical
All conduits must be laid before plastering.
fire fighting
Provide a 1130 litres reserve tank with a booster pump
Dry risers
Provide a 1x30m hydraulic Hose-real, on every floor.
\Provide manual/ electric break glass fire alarm system.
Provide 4x9kg litres water CO2 fire extingushers on every floor
D1
D1
revisions
1
1
RECORDING ROOM
Ceiling height - 3,000mm
Suspended Hard wood flooring
LECTURE ROOM
Ceiling height - 5,500mm
Gym mats flooring (Inter-locking)
SOUND ROOM
Ceiling height - 3,000mm
Gym mats flooring
3,000mm high gypsum parition
3,000mm high sound proofed gypsum parition
D1
2
D1
CAMERA STORE
Ceiling height - 3,000mm
HALLWAY
Gym mat flooring
Metal grill internally inlcusive of the ceiling
D2
Ceiling height - 2,800mm
Cement screed flooring
LA
ND
IN
G
Gym mats flooring
D1
3
project
STORE
PROPOSED INTERIOR PARTITIONING
WORKS FOR KENYA FILM SCHOOL
AT KASARANI STADIUM COMPLEX
drawing title
LA
ND
I
NG
2.340mm
client ministry/department
A
B
C
D
E
F
MINISTRY OF YOUTH AFFAIRS,
THE ARTS AND SPORTS
client signature
1
scale
2
SECTION 02 - PROPOSED DRAWING
3
project job no.
drawing no.
name
S. Architect
Kafuna
Drawn by
Kafuna
PSA. Architect
APPROVED
signed
date
February, 2024
Arch. J Murigu
Arch. L Mochama
SECTION 02 - DATA, POWER, FIRE, CCTV AND ACCESS CONTROL LAYOUT
CHIEF ARCHITECT
MINISTRY LANDS, PUBLIC WORKS,
HOUSING , AND URBAN
DEVELOPMENT
STATE DEPARTMENT OF PUBLIC WORKS
ARCHITECTURAL DEPARTMENT
FOR THE GOVERNMENT OF THE
REPUBLIC OF KENYA
GSPublisherVersion-