From: Project Electrical Engineer
To:
Ref: WP. ITEM NO. D1203 NB/NB/2301 JOB NO. 11216B
Through: Team Leader (Group – E4)
Date:
Chief Engineer- Electrical
11TH September, 2024
PROPOSED REFURBISHMENT OF CABINET SECRETARY’S OFFICE AT NSSF BUILDING
BLOCK “A” 20TH FLOOR FOR STATE DEPARTMENT FOR WILDLIFE.
1. PROJECT DETAILS
CLIENT: MINISTRY OF TOURISM AND WILDLIFE.
STATE DEPARTMENT FOR WILDLIFE.
W.P. ITEM NO: WP. ITEM NO. D1203 NB/NB/2301 JOB NO. 11216B
MAIN
CONTRACTOR:M/s.
CRINON CONSTRUCTION
P.O BOX-.
NAIROBI.
2. PROJECT DATA
Commencement Date------- 24/06/2024
Completion Date ------------- 24/10/2024
Contract Period----------------16 Weeks
Contract Sum (Electrical) ----------- Kshs. 3,401,850.00/-
COMPANY
LIMITED
INTRODUCTION
The project involves the partitioning, refurbishment and furnishing of Offices for the State Department for Wildlife
at NSSF building Block A 20th Floor. The contract is being undertaken as a domestic contract and the Electrical
services in this project include;
a.
b.
c.
d.
e.
Lighting and power outlet points,
Fire Detection and Alarm System.
CCTV Camera System
Structured Cabling works
Access control system works
PROGRESS OF WORKS
•
•
•
•
•
•
•
•
•
•
•
•
The project is 10% done.
Wiring for lighting points is 80% done.
Installation of light luminaires is 0% done.
Wiring for sockets is 80% done.
Installation of wall sockets is 0% done.
Switch installation is 0% done.
Fire detection and alarm system works are 0% done.
CCTV wiring is 100% done.
CCTV Installation is 0% done.
Structured cabling works are 80% done.
Access control wiring is 80% done.
Access control system is 0% done.
Pending Works and Corrections__________________________________________________________
•
•
•
•
•
•
The contractor to fast provision of samples for approval for all works.
The contractor to ensure only approved items are installed.
The ICT Technician to ensure all data points for structured cabling, CCTV and Access Control are
terminated at the security room where the data cabinet is to be installed.
The Electrical Technician to install the light fittings as was agreed.
The Electrical Technician to mount the Distribution board and Fire Alarm panel as was agreed at the
reception area.
The Electrical Technician to install the CS Office, boardroom corridor and reception artwork lighting
points as was agreed.
SITE PHOTOS
Wiring for Air conditioning
Corridor Ceiling layout
Wiring for Access control and lighting switch
Lift Lobby ceiling layout
Report prepared by:
Report checked by:
……………………
……………………
D. Kuria.
Eng. S. Ndirangu
Ass. P.E.E.
P. E. E.