Change Management Plan
Change Management
Change
Management Plan
Pickup
Page 1 of 14
Change Management
VERSION HISTORY
Version
Date
#
1.0
01/15/2022
Revision
Approved
Approval
Date
By
Date
//
//
01/20/2022
Reason
Initial draft of the
Change
Management Plan
1.1
02/01/2022
//
//
02/05/2022
Incorporated
feedback from
project team
1.2
03/10/2022
//
//
03/15/2022
Added section on
Training and
Development
1.3
04/05/2022
//
//
04/10/2022
Updated
Appendices and
added Risk
Management section
1.4
05/20/2022
//
//
05/25/2022
Clarified roles and
responsibilities in
Section 3
Page 2 of 14
Change Management
TABLE OF CONTENTS
1 INTRODUCTION ................................................................................................................4
1.1
Purpose of The Change Management Plan ..............................................................4
2 CHANGE MANAGEMENT PROCESS .............................................................................4
2.1
Change Request Process Flow Requirements ..........................................................4
2.2
Change Request Form and Change Management Log .............................................5
2.3
Evaluating and Authorizing Change Requests ........................................................7
3 RESPONSIBILITIES ...........................................................................................................9
APPENDIX A: CHANGE MANAGEMENT PLAN APPROVAL ....................................... 10
APPENDIX B: REFERENCES .............................................................................................. 11
APPENDIX C: KEY TERMS................................................................................................. 12
APPENDIX D: CHANGE REQUEST FORM EXAMPLE .................................................. 13
APPENDIX E: CHANGE MANAGEMENT LOG TEMPLATE ......................................... 14
Page 3 of 14
Change Management
INTRODUCTION
1.1
PURPOSE OF THE CHANGE MANAGEMENT PLAN
The purpose of this Change Management Plan is to establish a systematic approach for
managing changes in the development and deployment of the E-commerce Platform. It
aims to minimize risks, ensure effective communication, and maintain control over
changes to achieve successful project delivery.
The plan is tailored to minimize disruptions, assess impact on functionality, and engage
stakeholders for the successful implementation of changes in the project.
CHANGE MANAGEMENT PROCESS
The Change Management process establishes an orderly and effective procedure for
tracking the submission, coordination, review, evaluation, categorization, and approval for
release of all changes to the project’s baselines.
1.2
CHANGE REQUEST PROCESS FLOW REQUIREMENTS
Step
Description
Request for
Stakeholders or project team members initiate a change request,
Change
outlining details such as the reasons for the change and potential
benefits.
Register &
The change management team registers the request and conducts a
Evaluate the
preliminary evaluation to assess completeness and alignment with
Change
organizational objectives.
Evaluate & Send
A detailed evaluation is performed, considering the impact on scope,
Changes to the
schedule, budget, and resources. The Change Review Committee
Review
receives a comprehensive report with recommendations.
Committee
Accept
The Change Review Committee makes a decision to accept or reject the
proposed
change.
If
accepted,
formal
approval
is
granted,
communicated to stakeholders, and the change status is updated.
Update Plan &
The project or implementation plan is updated to include the approved
Implement
change. The change is executed according to the updated plan, and
communication channels inform stakeholders of the progress.
Page 4 of 14
Change Management
1.3
CHANGE MANAGEMENT PROCESS FLOW
Step
Description
Start
End
Prepared
Proactive identification and assessment of
Change Request
Impact
Impact
potential effects of a proposed change.
Analysis
Analysis
Review Impact
Thorough review of the prepared impact
Analysis
analysis by the Change Control Board or
Impact Analysis
Approval
Approval
Impleme
relevant stakeholders.
Implement
Execution of planned modifications or
Change
additions to the system, process, or product.
Test Change
Rigorous testing to validate the effectiveness
ntation
Implementation
Testing
Testing
Post-
and reliability of the implemented change.
Review
Comprehensive assessment of the overall
impact and success of the implemented
Impleme
change, informing continuous improvement.
ntation
Review
Page 5 of 14
Change Management
Figure 1. Change Management Process Flows
Page 6 of 14
Change Management
1.4
1.5
CHANGE REQUEST FORM AND CHANGE MANAGEMENT LOG
Element
Description
Date
-
CR#
CR-PICKUP-001
Title
Payment Gateway Integration
Description
Integrate additional payment gateway for user convenience.
Submitter
Sarah
CR Impact
Payment Gateway Integration
Module
Payment Module
Version
1.4
Priority
High
EVALUATING AND AUTHORIZING CHANGE REQUESTS
Change requests are evaluated using the following priority criteria:
Priority
Description
High
Change requests critical to the success of the E-commerce Platform.
Significant impact on objectives, timelines, or deliverables.
Medium
Change requests with a noticeable impact. Affects project timelines
or deliverables to a moderate extent.
Low
Change requests with a relatively minor impact. Enhancements but
not critical to immediate project success.
Change requests are evaluated and assigned one or more of the following change types:
Type
Description
Scope
Changes affecting the overall scope of the Pickup project. Includes
features, functionalities, and project goals.
Time
Changes impacting the project timeline, such as adjustments to
deadlines, milestones, or development phases.
Duration
Changes affecting the overall duration of the Pickup project,
including extensions or compressions of the timeline.
Cost
Changes influencing the financial resources allocated for the Ecommerce Platform project.
Page 7 of 14
Change Management
Resources
Changes related to personnel, technology, and tools necessary for
the development, testing, and deployment of the project.
Deliverables
Changes impacting tangible project outputs, such as software
modules, documentation, or user-facing features.
Product
Changes affecting the end result or output of the Pickup project,
including its core functionality and features.
Processes
Changes
involving
adjustments
to
project
workflows,
methodologies, or procedures during the development
and
deployment.
Quality
Changes impacting the level of excellence or adherence to
predefined standards in the design and functionality of the platform
Change requests are evaluated and assigned one of the following status types:
Status
Description
Open
Change requests entered or open but not yet approved or assigned.
Work in
Change requests approved, assigned, and work is progressing.
Progress
In Review
Change requests where work is completed and in the final review
prior to testing.
Testing
Change requests where work has been reviewed and is currently
being tested.
Closed
Change requests where work is complete, has passed all tests, and
updates have been released.
Page 8 of 14
Change Management
3 RESPONSIBILITIES
Role
Project
Name
//
Authority
Description
High
Overall project oversight, strategic
Manager
decision-making, and alignment of
changes with project goals.
Business
//
Medium
Analyst
Evaluate changes from a business
perspective, ensuring alignment with
user requirements.
Technical Lead
//
Medium
Assess technical feasibility and impact
of proposed changes on the Ecommerce Platform.
System
//
High
Architecture
Review changes for alignment with
system architecture, scalability, and
long-term technical vision.
Page 9 of 14
Change Management
Appendix A: Change Management Plan Approval
The undersigned acknowledge they have reviewed the Pickup Change Management Plan
and agree with the approach it presents. Changes to this Change Management Plan will
be coordinated with and approved by the undersigned or their designated representatives.
Signature:
Date:
Title:
Role:
Signature:
Date:
Title:
Role:
Signature:
Date:
Title:
Role:
Page 10 of 14
Change Management
Appendix B: References
The following table summarizes the documents referenced in this document.
Document Name &
Description
Location
Change Management
Detailed strategy for managing
URL or Network path
Plan v2.1
changes throughout the project
where document is located
Version
lifecycle.
Project Plan v1.0
Change Request Form
Comprehensive plan outlining project
URL or Network path
objectives, milestones, and resources.
where document is located
A Change Request Form is a concise
Click Here
document proposing, justifying, and
assessing project changes for approval
and implementation.
Change Log Template
A Change Log Template is a
structured document capturing details
of project changes, including date,
description, and impact, for effective
tracking and communication.
Page 11 of 14
Click Here
Change Management
Appendix C: Key Terms
This table provides definitions for terms relevant to this document.
Term
Definition
E-commerce
An online platform that facilitates electronic transactions, allowing
Platform
users to explore, book, and pay for automotive services.
Scope
The extent of what the E-commerce Platform project will accomplish,
including features, services, and goals.
System
The high-level design and structure of the E-commerce Platform,
Architecture
including components, modules, and their interactions.
Gateway
The incorporation of a payment gateway into the E-commerce
Integration
Platform, allowing secure and seamless processing of online
transactions.
Page 12 of 14
Change Management
Appendix D: Change Request Form Example
Complete template link is mentioned in the table in Appendix B.
Page 13 of 14
Change Management
Appendix E: Change Management Log Template
Complete template link provided in the table of the Appendix B.
Page 14 of 14