Project Report
PROJECT REPORT FOR INVESTMENT IN INJECTION
MOLDING AND BLOW MOLDING MACHINES
Chaminda Rajanayake
1st July 2025
Project for Investment in IM & BM Machines
Profit & Loss Account / Year 1
3 Machine + 1 Shift
1st Month
Sales
Less - Direct Cost
2nd Month
3rd Month
4th Month
5th Month
6th Month
7th Month
8th Month
9th Month
10th Month
11th Month
12th Month
YTD
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
296,997,854
RM+Energy
Polythene
Transport
SSCL
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(15,580,259)
(581,621)
(445,497)
(525,934)
(186,963,109)
(6,979,450)
(5,345,961)
(6,311,204)
Gross Profit
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
7,616,511
91,398,130
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(457,583)
(90,573)
(462,481)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(6,000,000)
(26,085,000)
(2,400,000)
(4,200,000)
(850,000)
(5,491,000)
(1,086,875)
(5,549,774)
(300,000)
(300,000)
(300,000)
(960,000)
(1,200,000)
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
3,056,290
36,675,480
Machine Maintenance Cost
Salary + Labour
Staff Welfare
Electricity Taken Above
Rent
Insurance
Depreciation-Prov'n
Gratuity-Prov'n
Loan Interest
Bank Charges
Printing & Stationary
Telephone Cost
Water Bill
Fact/Office Maintenance
Net Profit
Page 1 of 11
Cash Flow / Year 1
3 Machine + 1 Shift
1st Month
2nd Month
121,790
3rd Month
2,511,070
4th Month
4,900,349
5th Month
7,289,629
6th Month
9,678,908
7th Month
12,068,188
8th Month
14,457,468
9th Month
16,846,747
10th Month
19,236,027
11th Month
21,625,307
12th Month
24,014,586
72,910,000
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
24,749,821
272,248,033
72,910,000
-
RM+Energy
Polythene
Transport
SSCL
Machine Maintenance Cost
Salary + Labour
Staff Welfare
Electricity Taken Above
Rent
Insurance
Bank Charges
Printing & Stationary
Telephone Cost
Water Bill
Fact/Office Maintenance
(15,580,259)
(581,621)
(445,497)
(500,000)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(15,580,259)
(581,621)
(445,497)
(525,934)
(500,000)
(2,173,750)
(200,000)
(350,000)
(70,833)
(25,000)
(25,000)
(25,000)
(80,000)
(100,000)
(186,963,109)
(6,979,450)
(5,345,961)
(5,785,271)
(6,000,000)
(23,911,250)
(2,400,000)
(4,200,000)
(850,000)
(300,000)
(300,000)
(275,000)
(880,000)
(1,200,000)
Capital & Loan Payments
Loan Monthly Installment
Investment in Machines/Plant
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(1,677,648)
(54,910,000)
(18,454,127)
(54,910,000)
121,790
2,389,280
2,389,280
2,389,280
2,389,280
2,389,280
2,389,280
2,389,280
2,389,280
2,389,280
2,389,280
2,389,280
26,403,866
121,790
2,511,070
4,900,349
7,289,629
9,678,908
12,068,188
14,457,468
16,846,747
19,236,027
21,625,307
24,014,586
26,403,866
26,403,866
O/P Balance
Inflows
Sales Collection
Bank Loan
YTD
-
Outflows
Operational Expenses
Less - Direct Cost
Net Inflow/(OutFlow)
Closing Balance
Page 2 of 11
IM Machine 1 - 2nd Hand - 480 ton
IM Machine 2 - 2nd Hand - 250 Ton
BM Machine 1 - 2nd Hand - 5Ltr
Molds
20L / 10L
4L / 1L
IM 20L (Lid + Cont) - Single Cavility
IM 10L (Lid + Cont) - Single Cavility
IM 4L (Lid + Cont) - Single Cavility
IM 1L (Lid + Cont) - 2 Cavility
BM 5L - Single Cavity
BM 1L - Single Cavity
Insert Mold for BM Cans - 8 Cavity
BM Lid Mold - 4 Cavity
Cooling Tower / New
Chiller / Recondition
Compressure
Crusher
Gantry set up
$
$
$
$
Cost/LKR
6,000,000
3,500,000
4,500,000
25,000
25,000
22,000
18,000
7,550,000
7,550,000
6,644,000
5,436,000
600,000
400,000
450,000
LKR 1.5 Million
1 Unit for IM 2 Machines + BM 1 Machine
1 Unit for IM 2 Machines + BM 1 Machine
1 Unit for IM 2 Machines + BM 1 Machine
2 Units for IM & BM
Setup Development Cost
Cost
6,000,000
3,500,000
4,500,000
Wiring / water Lines etc
Lid Can be Outsourced
900,000
900,000
2,000,000
1,500,000
2,000,000
900,000
900,000
2,000,000
1,500,000
2,000,000
3,000,000
3,000,000
Computers and Accessories
Furniture and Fittings
480,000
1,500,000
Requirement for Machines
54,910,000
Intial Working Capital Requirement
Total Loan Requirement
18,000,000
72,910,000
Workforce
Machine Operators
Superwiser
Helpers / Packing
Stores
QC
Maintenance
Office Staff
Managers / Directors
Security
Monthly Capacity
20L-1,000 Pcs Per 1 Shift / 10L-1,000 Pcs per Shift
4L-1,400 Pcs Per 1 Shift / 1L-1,500 Pcs per Shift
5L-1,200 Pcs Per 1 Shift / 1L-1,400 Pcs per Shift
3 for one sfift / 6 for 2 shifts
1 for one sfift / 2 for 2 shifts
Only Day time - 10 Employees
2
1
1
3 (Acc + HR + IT)
3
2
Basic +
Allowance
45,000
70,000
40,000
50,000
50,000
50,000
50,000
250,000
45,000
EPF+ETF
6,750
10,500
6,000
7,500
7,500
7,500
7,500
37,500
6,750
Depreciation
10 Years
457,583
Other
1,500
1,500
1,500
1,500
1,500
1,500
1,500
25,000
1,500
Total Cost
Per Head
53,250
82,000
47,500
59,000
59,000
59,000
59,000
312,500
53,250
Gratuity Prov'n
Maintenance Cost
Electricity
Monthly RS 150,000 per One Machine 450,000
Per KG (Over RS 40-50) - Little high since no power Bank
Strengths
Access to Market
Procurement/Access to Best Import Suppliers
Technical Know How
Page 3 of 11
I Shift Cost
2 Shift Cost
159,750
82,000
475,000
118,000
59,000
59,000
177,000
937,500
106,500
319,500
164,000
475,000
118,000
59,000
59,000
177,000
937,500
106,500
2,173,750
90,573
2,415,500
100,646
Monthly
1 Shift
2 Shift
Capacity Capacity Total Qty
Pcs
Pcs
1 Shift
IM Machine 1 - 480 Ton
20L
1,000
1,000
12,500
10L
1,000
1,000
12,500
Monthly
Total Qty
Monthly
Total Qty
2 Shift
Target
Unit Cont: Weight
Total RM
Main
Selling
with 2%
Weight/ RM/Virgin
Price/A Wastage /
KG
Weight
VG
Gram
25,000
25,000
12,500
12,500
700
485
930
600
11,625
7,500
IM Machine 2 - 250 Ton
4L
1,400
1L
1,500
1,400
1,500
17,500
18,750
35,000
37,500
17,500
18,750
220
70
308
96
5,390
1,800
11,393
7,350
5,282
1,764
BM Machine 1 - 5 Ltr
5L-Blow
1,200
1L-Blow
1,400
1,200
1,400
15,000
17,500
30,000
35,000
15,000
17,500
190
110
220
110
3,300
1,925
3,234
1,887
Monthly Gross Income
Less - Polythene Cost (Direct)
Less - Transport Cost (Direct)
Less - SSCL
Gross Net
Master
Batch
Weight
Main
Master Handle
RM/Virgi
Batch
Cost per
n
Price/KG
Unit
Price/KG
-
403
403
800
800
403
403
800
800
66
39
406
406
800
800
Lid &
Energy
Insert
Cost
Cost per
per KG
unit
38.5
33.5
LKR
9,169,562
(581,621)
(445,497)
(525,934)
7,616,511
Machine Maintenance Cost500,000
Salary + Labour
2,173,750
Staff Welfare
200,000
Electricity Taken Above
Rent
350,000
Insurance
70,833
Depreciation-Prov'n
457,583 Nominal Cost
Gratuity-Prov'n
90,573 Nominal Cost
Loan Interest
462,481
Bank Charges
25,000
Printing & Stationary
25,000
Telephone Cost
25,000
Water Bill
80,000
Fact/Office Maintenance 100,000
(4,560,221)
Net Profit Per Month
3,056,290
Page 4 of 11
40
40
40
40
12.0
12.0
50
50
Main
RM/Virgin
TTL Value
4,591,178
2,962,050
2,128,727
710,892
1,313,004
765,919
12,471,769
Master
Handle Cost
Batch TTL
TTL Value
Value
186,000
120,000
86,240
28,800
52,800
30,800
504,640
Lid &
Insert
Cost
Value
481,250
418,750
900,000
180,000
210,000
390,000
Energy Cost
Value
Total Direct
Cost Per
Month
465,000
300,000
215,600
72,000
165,000
96,250
1,313,850
5,723,428
3,800,800
2,430,567
811,692
1,710,804
1,102,969
15,580,259
Total Sales
Value per
Month
8,750,000
6,062,452
3,850,000
1,312,452
2,849,962
1,924,955
24,749,821
Net Value
3,026,573
2,261,652
1,419,433
500,760
1,139,158
821,986
9,169,562
Loan No
Loan
72,910,000.00
Interest rate
No of years
Discounting rate
Installment
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
Month
13.50%
0.1325
0.01125
5
-
-
-,677,647.87
-
72,910,-,052,-,185,-,308,-,422,-,525,-,618,-,701,-,774,-,836,-,888,-,929,-,959,-,979,-,987,-,984,-,970,-,945,-,908,-,859,-,799,-,726,-,642,-,545,-,436,-,315,-,181,-,034,-,874,-,701,-,515,-,316,-,103,-,876,-,636,-,382,-,114,-,831,-,534,-,222,-,896,-,555,-,198,-,827,-,439,-,037,-,618,-,184,-,733,-,266,-,783,-,283,-,766,-,232,422.04
9,681,138.92
8,112,403.86
6,526,020.53
4,921,790.39
3,299,512.66
1,658,984.30
Monthly Average Interest
Interest
820,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,-,663.57
Capital
857,-,-,-,-,-,-,-,-,-,-,-,-,-,630.06
1,002,785.90
1,014,067.24
1,025,475.50
1,037,012.10
1,048,678.48
1,060,476.11
1,072,406.47
1,084,471.04
1,096,671.34
1,109,008.90
1,121,485.25
1,134,101.95
1,146,860.60
1,159,762.78
1,172,810.11
1,186,004.23
1,199,346.78
1,212,839.43
1,226,483.87
1,240,281.81
1,254,234.98
1,268,345.13
1,282,614.01
1,297,043.42
1,311,635.16
1,326,391.05
1,341,312.95
1,356,402.72
1,371,662.25
1,387,093.45
1,402,698.25
1,418,478.61
1,434,436.49
1,450,573.91
1,466,892.86
1,483,395.41
1,500,083.60
1,516,959.55
1,534,025.34
1,551,283.13
1,568,735.06
1,586,383.33
1,604,230.14
1,622,277.73
1,640,528.36
1,658,984.30
Instalment
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
1,677,647.87
27,748,872.39
72,910,000.00
100,658,872.39
462,481.21
Page 5 of 11
Balance
72,052,-,185,-,308,-,422,-,525,-,618,-,701,-,774,-,836,-,888,-,929,-,959,-,979,-,987,-,984,-,970,-,945,-,908,-,859,-,799,-,726,-,642,-,545,-,436,-,315,-,181,-,034,-,874,-,701,-,515,-,316,-,103,-,876,-,636,-,382,-,114,-,831,-,534,-,222,-,896,-,555,-,198,-,827,-,439,-,037,-,618,-,184,-,733,-,266,-,783,-,283,-,766,-,232,422.04
9,681,138.92
8,112,403.86
6,526,020.53
4,921,790.39
3,299,512.66
1,658,984.30
(0.00)
Estimated Cost for - 1L-2 Cavity - IM - UNP White with 100% V
Weight- (g)
Cost Componant
PPCP Virgin
Master Batch - White
PPCP Virgin
Master Batch - White
Provision for Wastages
Cont:
73
Lid
21
2%
1.88
Direct Material
RM%
Direct Labour
Energy cost
Transport Cost
Polythene
Other Direct OH
Total Direct Cost
Unit Selling Price at 30% GP
Price per kg-
-
-
SCCL 2.125%
Direct Labour-Cont:
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Cont:
Machine
Packing HelpersOpperator-1
1 Nos
26,-,876.00
4,001.25
3,-,-,194.20
3,000.00
3,000.00
3,-,-,-
Direct Labour-Lid
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Lid
Machine
Packing HelpersOpperator-1
1 Nos
26,-,876.00
4,001.25
3,-,-,194.20
3,000.00
3,000.00
3,-,-,-
Direct Energy-Cost
Per KG Electricity conversion cost - AVG
Total Energy Cost per unit
Cont: - IM-
-%
-%
21.59
Total
1.29
Total
0.94
Lid-IM
Cost per unit-
Transport Cost
Medium size Lorry cost
No. of Cont: per load
Transport cost per unit
Polythene Cost
HDPE 1 Kg - Cost
1 bag Weight - g
1 bag Cost
Nos Pcs per Bag
Polythene Cost per pcs
Value-RS
15,000
4,800
3.13
Cont:
Lid-
Total-
1.35
Page 6 of 11
100%
2%
100%
2%
PPCP Virgin
MB-White
PPCP Virgin
MB-White
39.34
57%-
-
Before SSCL Price
After SSCL Price
GP Margin
GP-LKR
-
SCCL 2.125%-%
20.86 GP-LKR
Estimated Cost for - 4L, 2 Caivity - IM - UNP White with Virgin
Weight- (g)
Cost Componant
PPCP Virgin
Master Batch - White
PPCP Virgin
Master Batch - White
PPCP Virgin
Master Batch - White
Provision for Wastages
Cont:
200
Lid
82
Handle
19.5
2%
6.03
Direct Material
RM%
Direct Labour
Energy cost
Transport Cost
Polythene
Other Direct OH
Total Direct Cost
Unit Selling Price at 30% GP
Price per kg-
-
-
SCCL 2.125%
Direct Labour-Cont:
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Cont:
Machine
Packing HelpersOpperator-1
1 Nos
26,-,876.00
4,001.25
3,-,-,194.20
3,000.00
3,000.00
3,-,-,-
Direct Labour-Lid
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Lid
Machine
Packing HelpersOpperator-1
1 Nos
26,-,876.00
4,001.25
3,-,-,194.20
3,000.00
3,000.00
3,-,-,-
Direct Labour-Handle
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Handle
Machine
Packing Helpers1 Nos
Opperator-1
26,-,876.00
4,001.25
3,-,-,194.20
3,000.00
3,000.00
3,-,-,-
Direct Energy-Cost
Per KG Electricity conversion cost - AVG
Total Energy Cost per unit
Cont: - IM-
Lid-IM-
Transport Cost
Medium size Lorry cost
No. of Cont: per load
Transport cost per unit
Polythene Cost
HDPE 1 Kg - Cost
1 bag Weight - g
1 bag Cost
Nos Pcs per Bag
Polythene Cost per pcs
Value-RS-%
3.14
2%-%
1.29
2%
7.70
100%
0.31
2%-% RM %
-%
64.85
Before SSCL Price
After SSCL Price
GP Margin
GP-LKR
1.43
Total
1.01
Total
0.94
12.30
15,000
2,750
5.45
Cont:
Lid-
Total-
-%-
-
Total
Handle-IM-
PPCP Virgin
MB-White
PPCP Virgin
MB-White
PPCP Virgin
MB-White
1.99
Page 7 of 11
-
SCCL 2.125%-%
69.39 GP-LKR
Estimated Cost for - 10 Ltr - IM - UNP White with Virgin
Weight- (g)
Cost Componant
PPCP Virgin
Master Batch - White
PPCP Virgin
Master Batch - White
Provision for Wastages
Handle
Cont:
435
Lid
153
2%
11.76
Direct Material
RM%
Direct Labour
Energy cost
Transport Cost
Polythene
Other Direct OH
Total Cost
Unit Selling Price at 30% GP
Price per kg-
-
-
SCCL 2.125%
Direct Labour-Cont:
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Cont:
Machine
Packing
Opperator-1
Helpers- 2 Nos
26,-,752.00
4,001.25
7,-,-,388.40
3,000.00
3,000.00
6,-,-,-
Direct Labour-Lid
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Lid
Machine
Packing
Opperator-1
Helpers- 1 Nos
26,-,876.00
4,001.25
3,-,-,194.20
3,000.00
3,000.00
3,-,-,-
-
Direct Energy-Cost
Per KG Electricity conversion cost - AVG
Total Energy Cost per unit
Cont: - IM-
-%
6.82
2%-%
2.40
2%-% RM %
-%
143.13
3.88
Lid-
1.65
Total-
-%-
-
Before SSCL Price
After SSCL Price
GP Margin
GP-LKR
-
SCCL 2.125%-%
151.25 GP-LKR
with Handle fixing Cost
Total
15,000
1,-
Cont:
PPCP Virgin
MB-White
PPCP Virgin
MB-White
Total
Lid-IM
Cost per unit-
Transport Cost
Medium size Lorry cost
No. of Cont: per load
Transport cost per unit
Polythene Cost
HDPE 1 Kg - Cost
1 bag Weight - g
1 bag Cost
Nos Pcs per Bag
Polythene Cost per pcs
Value-RS
4.85
Page 8 of 11
Lid Packing by MO
Estimated Cost for - 20 Ltr - IM - UNP White with Virgin
Weight- (g)
Cost Componant
PPCP Virgin
Master Batch - White
PPCP Virgin
Master Batch - White
Provision for Wastages
Handle Cost
Cont:
710
Lid
200
2%
18.20
Direct Material
RM%
Direct Labour
Energy cost
Transport Cost
Polythene
Other Direct OH
Total Direct Cost
Unit Selling Price at 30% GP
Price per kg-
-
-
SCCL 2.125%
Direct Labour-Cont:
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Cont:
Machine
Packing
Opperator-1
Helpers- 2 Nos
26,-,752.00
4,001.25
7,-,-,388.40
3,000.00
3,000.00
6,-,-,-
Direct Labour-Lid
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Lid
Machine
Packing
Opperator-1
Helpers- 1 Nos
26,-,876.00
4,001.25
3,-,-,194.20
3,000.00
3,000.00
3,-,-,-
-
Direct Energy-Cost
Per KG Electricity conversion cost - AVG
Total Energy Cost per unit
Cont: - IM-
-%
11.14
2%-%
3.14
2%-% RM %
-%
213.18
Lid-
-
-
Before SSCL Price
After SSCL Price
GP Margin
GP-LKR
-
SCCL 2.125%-%
204.33 GP-LKR
with Handle fixing Cost
1.88
Lid Packing by MO
Total
Total-
-%
4.76
15,-
Cont:
PPCP Virgin
MB-White
PPCP Virgin
MB-White
Total
Lid-IM
Cost per unit-
Transport Cost
Medium size Lorry cost
No. of Cont: per load
Transport cost per unit
Polythene Cost
HDPE 1 Kg - Cost
1 bag Weight - g
1 bag Cost
Nos Pcs per Bag
Polythene Cost per pcs
Value-RS
5.54
Page 9 of 11
Estimated Cost for 5 Ltr SQ Can -220g - General
Cost Componant
HDPE
Master Batch
LDPE
Provision for Wastages
LID - Outsourced
Weight- (g)
Can
220
Insert
2%
5
4.50
Direct Material
RM%
Direct Labour
Energy cost
Transport
Polythene
Lid Transport Cost
Other OH
Total Cost
Unit Selling Price at 30% GP
Price per kg-
-
-
SSCL 2.125%
Direct Labour-Can
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Can
Machine
Opperator-1
26,675.00
4,-,003.75
3,000.00
3,-,-
Packing
Helpers-5 Nos
124,-,-,971.00
Direct Labour-Insert
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Unit
Machine
Opperator-1
26,675.00
4,-,003.75
3,000.00
3,-,-,600
0.13
Packing
Helpers-1 Nos
24,876.00
3,-,194.20
Direct Energy-Cost
Per KG Electricity conversion cost - AVG
Total Energy Cost per unit
Transport
Lorry cost - Large
No. of Blow Can per load
Transport cost per Container
Polythene Cost
LDPE 1 Kg Virgin - Cost
1 bag Cost
Nos Pcs per Bag
Polythene Cost per pcs
Can -Blow-
15,-,-
3,-,-,000
0.18
Value-RS
89.28 HDPE $ 1,010 @-%
-%
57.71
Total
6.60
Total
0.31
Insert-IM
Cost per unit-
15,000
2,300
6.52
75.00 g
-
Page 10 of 11
-%-
-
Before SSCL Price
After SSCL Price
GP %
GP-LKR
-
SSCL 2.125%-%
60.71 GP-LKR
Estimated Cost for 1 Ltr Round Can 110g - General
Cost Componant
HDPE
Master Batch
LDPE
Provision for Wastages
LID - Outsourced
Weight- (g)
Can
110
Insert
2%
5
2.30
Direct Material
RM%
Direct Labour
Energy cost
Transport
Polythene
Lid Transport Cost
Other OH
Total Cost
Unit Selling Price at 30% GP
Price per kg-
-
-
SSCL 2.125%
Direct Labour-Can
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Can
Machine
Opperator-1
26,675.00
4,-,003.75
3,000.00
3,-,-
Packing
Helpers-4 Nos
99,-,-,776.80
Direct Labour-Insert
Basic Salary - Average
EPF + ETF
Overtime
Night Allowance
Attendance Allowance
Total monthly cost
Per Hour cost
Hourly rate / Pcs
Cost per Unit
Machine
Opperator-1
26,675.00
4,-,003.75
3,000.00
3,-,-,600
0.13
Packing
Helpers-1 Nos
24,876.00
3,-,194.20
Direct Energy-Cost
Per KG Electricity conversion cost - AVG
Total Energy Cost per unit
Transport
Lorry cost - Large
No. of Blow Can per load
Transport cost per Container
Polythene Cost
LDPE 1 Kg - Cost
1 bag Cost
Nos Pcs per Bag
Polythene Cost per pcs
Can -Blow-
12,-,-
3,-,-,000
0.18
Price
Value-RS
IM-20L
IM-10L
IM-4L
IM-1L
BM-5L
BM-1L
44.64 HDPE $ 1,010 @-%
-%
31.92
57.46
53%-
-
Before SSCL Price
After SSCL Price
GP %
GP-LKR
-
SSCL 2.125%-%
40.88 GP-LKR
Total
6.90
Total
0.31
Insert-IM
Cost per unit-
15,000
8,500
1.76
91.80 g
-
Page 11 of 11
-
Margin
Monthly Qty
-
12,500
12,500
17,500
18,750
15,000
17,500
93,750
TTL Margin
2,554,179
1,890,627
1,214,333
391,152
910,655
715,420
7,676,366
7,616,511 As per Capacity Plan
59,855 Diff-LKR