STORYBOARD Creation - Build and Edit
COURSE STORYBOARD
November 22, 2020
Qualification:
National Course Code:
Certificate IV in Building and Construction
CPC40110
Course Number:
Course Title:
Demolition
Course Outline:
Introduction
Module 1:
Demolition and Deconstruction
Lesson 1: Concept Definition
A. Demolition VS Deconstruction
B. Tools and Equipment
Lesson 2: Preliminary Planning and Work Assessment
A. Preliminary Planning
B. Pre-Work Inspections
C. Waste Management Planning
D. Assessing and Documenting the Job
Module 2:
Demolition Work Procedures
Introduction
Lesson 1: Working Safely
Lesson 2: Demolishing Structure I
Lesson 3: Demolishing Structure II
Lesson 4: Recycling and Cleaning Up
Summary
Assessment
Module 2: Demolition Work Procedures
Lesson 1: Dealing with Problems and Working Safely
Slide Title/ Slide
Screenshot
On-Screen Visuals
On-Screen Text
Module 2: Demolition
Background image:
Lesson 1: Working Safely
Work Procedures
Hamed (seen holding
hand tools/equipment
for demolition work)
Lesson 2: Demolishing
Structure I
Narration
This is Module 2: Demolition Work Procedures.
Module 1 provided you with the information on work planning and work
assessment prior to demolition work.
In this module, we will extensively review work demolition procedures.
Lesson 3: Demolishing
Structure II
Lesson 4: Recycling and Cleaning
Up
An introduction provides you of the problems to be expected during
demolition.
Lesson 1 itemizes essential tips on working safely during demolition.
Lessons 2 and 3 covers the various demolition work procedures you are
expected to encounter in the field.
Finally, lesson 4 talks about recycling and cleaning up after the demolition
work.
Ready to learn more about demolition work procedures?
Let’s get to it!
Component Type/
Notes to Developers
Background image is
static.
Texts to appear in sync
with the narration.
Welcome back everyone… We now continue with Module 2: Demolition Work
Procedures.
In Module 1 we provided you with the information for work planning and work
assessment before demolition work can start.
In this module we’ll focus on demolition procedures, there are 4 lessons in
this module
In the introduction we’ll look at the problems to be expected during
demolition. In lesson 1 we’ll, closely focus essential tips on working safely
during demolition and in lesson 2 and 3 we’ll cover the various demolition
work procedures you are expected to encounter at the site, and finally, in
lesson 4 we’ll talk about recycling and cleaning up after the demolition work.
Let’s get to it!
Introduction
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
The actual demolition of a part or all of The actual demolition of a part or all of a building is usually a reversal of the
a building is usually a reversal of the construction steps.
construction steps.
This means that the construction steps for that building must be identified
This means that the construction before work on its demolition can begin.
steps for that building must be
identified before work on its Usually, the fasteners holding materials in place need to be removed first.
demolition can begin.
Once this is done, the materials can be removed and stacked as planned.
Remember that we’ve indicated before that actual demolition is a top down
process which is the opposite of construction which is bottom up! However,
it is useful to understand the construction process steps for that building and
they must be identified before work on its demolition can begin.
Usually, demolition starts when the fasteners holding materials in place are
loosened and then safely removed. Once this is done, the materials can be
removed and stacked as planned.
Background image is
static.
Texts to appear in sync
with the narration.
●
Introduction
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
●
●
An essential start to demolition
work is to secure the site with a
fence or barricade to keep
unwanted people out of the
danger area.
An essential start to demolition work is to secure the site with a fence or
barricade to keep unwanted people out of the danger area. On-site workers
need to have completed relevant safety training. Allowing people to enter
the area without completing safety training increases the risk of accidents
occurring on-site .
Background image is
static.
Texts to appear in sync
with the narration.
On-site workers need to have Site protection and barricades may need to include the arc where structures
completed
relevant
safety may fall, where the chimney may fall on to a nearby footpath.
training.
An easy-to-access site can lead to problems from unauthorised people
Allowing people to enter the area entering the site and being injured.
without completing safety training
increases the risk of accidents Before work has begun the site needs to be made secure with a fence or
occurring on-site.
barricade to keep unwanted people out of the danger area and off site, onsite protection and barricades may also be needed to cover the areas where
building materials such as bricks or bigger pieces like chimneys’ may fall into
walkways and footpaths.
An unsecure site that is easy-to-access can lead to problems from
unauthorised people entering the site and being injured.
All site workers must have completed all required safety training to gain
access to the site, those that have not completed their safety training should
not be allowed access to the site due to the increased risk of accidents.
Introduction
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
Image:
Problem to be
demolition work:
●
expected
Structural Instability
in
Problems are to be expected during demolition work.
Always have on hand an experienced person to foresee problems and put
into effect alternative safe methods to ensure the overall safety of the job.
One possible source of danger is the structural instability created during the
deconstruction process.
Background image is
static.
Texts to appear in sync
with the narration.
Additional image to
appear in sync with the
narration.
As parts of a building are removed, the remainder of the structure may
become unstable.
This problem can be exacerbated if the building has been weakened by
events such as termite attack, weathering or previous alterations.
This image is an example of a building made structurally unstable by termite
attacks.
Building made
structurally unstable by
termite attack (Refer to
the courseware for
actual photos)
You’re always going to have problems on a demolition work site, so expect
them.
It’s always a good idea to have an experienced worker to help spot problems
and look out for safety hazards and violations to ensure the overall safety of
the job.
Remember your basically knocking a building down so you’ll always have a
problem with instability of the building as you take parts away. This problem
can be even bigger if the building has been weakened by termite attack,
weathering or previous alterations and of course gravity. So, make sure that
your team is aware of these potential problems.
This image is an example of a building made structurally unstable by termite
attacks.
Introduction
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
Image:
Problem to be
demolition work:
●
expected
in
Structural Instability
Sometimes temporary supporting
structures may need to be put in place
Sometimes temporary supporting structures may need to be put in place to
hold the main building while other parts are removed.
As much as possible, consider the need for this during the pre-planning
stage.
Background image is
static.
Texts to appear in sync
with the narration.
Additional image to
appear in sync with the
narration.
to hold the main building while other Always think about how you are going to access the work area safely and
parts are removed.
how you can safeguard against things falling onto people and people falling
off work areas.
Now that we have outlined some of the problems that are to be expected,
let’s talk about some absolute must do’s on working safely when engaging
in demolition work.
Building with scaffolding
(Refer to the
courseware for actual
photos)
Next stop is lesson 1!
Often you’ll need temporary supports to support the building as you take
parts of it away, this is something you should have considered during the preplanning stage along with how you are going to access the work area safely
and how you can safeguard against things falling onto people and people
falling off work areas.
Now that we have outlined some of the problems that are to be expected,
let’s talk about some absolute must do’s on working safely when engaging
in demolition work.
We now move on to lesson 1!
Module 2: Demolition Work Procedures
Lesson 1: Working Safely
LEARNING INTERACTION: TABS
SLIDE TITLE: WORKING SAFELY
Tab Title
On-Screen Visuals
Introduction tab +
Number of Tabs: 6
On-Screen Text
Narration
Component Type/
Notes to Developers
WORKING SAFELY
Hamed with colleagues
in a demolition site
Absolute MUST DO’s
When N/A
Engaging in Demolition Work.
Images should be
reflective of the onscreen text.
Safety Tip # 1
Image:
Working Safely
Images should be
reflective of the onscreen text.
Old building showing
service lines: cables for
landline or electricity
Safety Tip # 2
Image:
Timber with nails on it.
Safety Tip # 3
Image:
Tradies working on a
demolition site
N/A
Tip#1: Ensure all services are
disconnected and then assume they
are live until you have checked their
disconnection.
Working Safely
N/A
Images should be
reflective of the onscreen text.
N/A
Images should be
reflective of the onscreen text.
Tip#2: Don’t put a piece of timber
down if it still has nails sticking out of
it. At least, bend them over first.
Working Safely
Tip#3: Always know where your coworkers are as you proceed with the
job, so that you don’t inadvertently
knock something down on them.
Safety Tip # 4
Image:
Tradie checking on the
stability of a building
structure
Working Safely
Image:
Tradies wearing PPEs
while engaging in
demolition work
Working Safely
N/A
Images should be
reflective of the onscreen text.
N/A
Images should be
reflective of the onscreen text.
Tip#4: If in doubt about the stability of
something,
check
with
an
experienced person. You don’t want a
building collapsing on to you because
you knocked out an important part of
that building!
Safety Tip # 5
Safety Tip # 6
Tip#5: Remember that damage being
caused now (e.g. from breathing in
asbestos) may not become obvious
until years later.
Image:
Working Safely
Tradie climbing up a
ladder, both hands free
of any materials
Tip#6: Always have three points of
contact on a ladder at any time. This
means you should not carry large,
heavy materials up and down ladders.
Module 2: Demolition Work Procedures
Lesson 2: Demolishing Structure 1
N/A
Images should be
reflective of the onscreen text.
Slide Title/ Slide
Screenshot
On-Screen Visuals
Module 2: Demolition
N/A
On-Screen Text
Lesson 2: Demolishing Structure I
Work Procedures
Narration
Let’s move on to lesson 2: Demolishing Structures I!
Component Type/
Notes to Developers
Texts to appear in sync
with the narration
In this lesson, we will review the following procedures on demolition work:
1. Making a New Door or
Window Opening
2. Supporting Walls
3. Removing an Internal LoadBearing Wall
1. Making a New Door or Window Opening
2. Supporting Walls and,
3. Removing an Internal Load-Bearing Wall
Let’s go over each item more extensively!
We now move on to lesson 2: Demolishing Structures 1
In this lesson, we’ll review the following procedures of demolition work:
1. Making a New Door or Window Opening
2. Supporting Walls and,
3. Removing an Internal Load-Bearing Wall
Let’s look at each one!
Lesson 2:
Demolishing
Structure I
Procedure 1: Making a New Door or Structures within a building, such as doors, windows and load-bearing walls, Texts to appear in sync
Window Opening
need to be handled with care when being demolished. Remember that these with the narration.
structures will need to be supported during the demolition process.
Image is static.
●
Load Distribution with
Stretcher Bond
Masonry
It is necessary to support the Procedure 1: Making a New Door or Window Opening
wall above the new opening.
When it is decided that a new door or window needs to be set into a wall, it
may be necessary to support the wall above the new opening.
(Refer to the courseware
for actual photos)
●
Masonry walls don't have This is more important if the wall is masonry, because masonry don’t have
much strength if the lower much strength if the lower material is removed. Masonry walls are supported
materials are removed.
on a line down from the opening following the vertical and horizontal joints.
The image shows how the load is transferred.
●
Masonry walls are supported
on a line down from the
Doors, windows and load-bearing walls all play a part in supporting the
opening following the vertical
building and need to be handled with care when being demolished.
and horizontal joints.
Remember that these pieces will need to be supported during the demolition
process.
Procedure 1 focuses on making a new door or window opening
It’s been decided that a new door or window needs to be set into a wall, your
first thought must be ‘does’ the wall above the new opening need to be
supported?
This is even more important if the wall is masonry as masonry becomes weak
if the lower material is removed. Masonry walls are supported on a line down
from the opening following the vertical and horizontal joints.
The image shows how the load is transferred.
Lesson 2:
Demolishing
Structure I
Image:
Procedure 1: Making a New Door or Masonry walls can be supported by cutting out some masonry over the Texts to appear in sync
with the narration.
Window Opening
proposed opening and inserting a lintel of steel or masonry. Before inserting
the new lintel, support the opening by making a hole above where the new Image is static.
lintel will go and insert a support into the opening to hold up the masonry.
● Masonry walls can be
supported by cutting out
This allows the opening to be removed and the new lintel to be installed.
some masonry over the
proposed
opening
and
inserting a lintel of steel or
masonry.
(Refer to the
courseware for the
actual photo)
Pack the lintel tightly into position on supports cut into the side of the new
opening and allow it to set before removing the lower wall to reveal the new
opening.
When the lintel is set and fully load-bearing, remove the needle and repair
the hole.
Take a look at this image.
An opening made in a masonry wall. The opening battened out for fibrecement sheet lining (a lintel bar was placed over the opening).
Masonry walls can be supported by cutting out some of the masonry over the
proposed opening and inserting a lintel of steel or masonry. Before inserting
the new lintel, support the opening by making a hole above it where the new
lintel will go and insert a support into the opening to hold up the masonry.
This allows the opening to be removed and the new lintel to be installed.
Pack the lintel tightly into position on supports cut into the side of the new
opening and allow it to set before removing the lower wall to reveal the new
opening.
When the lintel is set and fully load-bearing, remove the needle and repair
the hole.
Look at this image.
An opening made in a masonry wall. The opening battened out for fibrecement sheet lining (a lintel bar was placed over the opening).
Lesson 2:
Demolishing
Structure I
Image:
Procedure 1: Making a New Door or
Window Opening
This image shows a partially completed work of an opening made in a
masonry wall.
Texts to appear in sync
with the narration.
Image is static.
The second image shows the finished result viewed from the opposite side.
This image shows a partially completed work of an opening made in a
masonry wall.
The second image shows the finished result viewed from the opposite side.
Formatted: Indent: Left: 0"
(Refer to the
courseware for the
actual photo)
Lesson 2:
Demolishing
Structure I
Background image:
Tradies doing
restoration jobs on a
wall.
Procedure 2: Supporting the Walls
●
●
Walls can be supported by
attaching a long piece of
material to the walls and then
bracing the material to a solid
position.
Supporting the walls
Texts to appear in sync
with the narration.
Walls can be supported by attaching a long piece of material to the walls and
then bracing the material to a solid position.
Image is static.
Restoration jobs will often require the removal of the main building with the
facade of the original building being left in place.
Restoration jobs will often This may involve using steel or timber supports to hold up the structure
require the removal of the temporarily while the rest of the building is constructed.
main building with the facade
of the original building being When supporting the walls, they can be supported by attaching a long piece
left in place.
of material to the walls and then bracing the material to a solid position.
Restoration jobs will often require the removal of the main building with the
facade of the original building being left in place.
This may involve using steel or timber supports to hold up the structure
temporarily while the rest of the building is being constructed.
Lesson 2:
Demolishing
Structure I
Background image:
Tradies doing
restoration jobs on a
ceiling.
Procedure 3: Removing an Internal
Load-Bearing Wall
●
●
Removing an internal load-bearing wall
Texts to appear in sync
with the narration.
When an internal load-bearing wall needs to be removed, the ceiling will need
Image is static.
When an internal load- temporary or permanent support.
bearing wall needs to be
removed, the ceiling will need An engineer may need to be consulted and an inspection of the roof space
temporary or permanent necessary to determine the building’s ceiling type and roof structure.
support.
If the building has trusses, then the roof and ceiling may be supported on the
If the building has trusses, outside walls only, making it easier to alter the internal walls.
then the roof and ceiling may
be supported on the outside When an internal load-bearing wall needs to be removed, the ceiling will need
walls only, making it easier to temporary or permanent support.
alter the internal walls.
An engineer may need to be consulted and an inspection of the roof space
necessary to determine the building’s ceiling type and roof structure.
If the building has trusses, then the roof and ceiling may be supported on the
outside walls only, making it easier to alter the internal walls.
Formatted: Indent: Left: 0", First line: 0", Space After:
0 pt
Lesson 2:
Demolishing
Structure I
Background image:
Tradies doing
restoration jobs on a
ceiling.
Procedure 3: Removing an Internal
Load-Bearing Wall
●
●
A low roof may present
problems when fitting any
extra beams into the space.
Cable
supports
and
engineered beams may be
suitable alternatives.
The type of internal support needed will depend on how much room is
available in the rood space.
A low roof may present problems when fitting any extra beams into the space.
Cable supports and engineered beams may be suitable alternatives.
Texts to appear in sync
with the narration.
Image is static.
When there is plenty of room, it may be easy to install a beam over some
other internal walls.
Every building is different and sometimes an engineer will need to design a
When there is plenty of room, solution for your structural alterations.
it may be easy to install a
beam over some other The type of internal support needed will depend on how much room is
internal walls.
available in the roof space.
A low roof may present problems when fitting any extra beams into the space.
Cable supports and engineered beams may be suitable alternatives.
When there is plenty of room, it may be easy to install a beam over some of
the internal walls.
Every building is different and sometimes an engineer will need to design a
solution for your structural alterations.
Let’s review!
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
Lesson 2: Demolishing Structure I
Time to review what we have learned!
Texts to appear in sync
with the narration.
This is lesson 2: Demolishing Structures I.
1. Making a New Door or
Window Opening
Image is static.
Here, we covered three procedures in demolition work:
2. Supporting Walls
3. Removing an Internal LoadBearing Wall
1. Making a New Door or Window Opening
2. Supporting Walls and,
3. Removing an Internal Load-Bearing Wall
We emphasized the importance of handling buildings to be demolished with
care, that these structures need to be supported during the demolition
process.
Masonry walls can be supported by cutting out some masonry over the
proposed opening and inserting a lintel of steel or masonry.
Walls can be supported by attaching a long piece of material to the walls and
then bracing the material to a solid position.
If the building has trusses, then the roof and ceiling may be supported on the
outside walls only, making it easier to alter the internal walls.
Procedures in demolishing structures will be continued in lesson 3!
Now it’s time to review what we have learnt in lesson 2: Demolishing
Structures 1.
In this lesson we’ve covered three procedures that can be carried out in
demolition work:
1. Making a New Door or Window Opening
2. Supporting Walls and,
3. Removing an Internal Load-Bearing Wall
We’ve highlighted the importance of handling buildings to be demolished with
care and that these buildings need to be supported during the demolition
process. For example, masonry walls can be supported by cutting out some
masonry over the proposed opening and inserting a lintel of steel or masonry.
Walls can also be supported by attaching a long piece of metal or wood to
the walls and then bracing the material to a solid position.
If the building has trusses, then the roof and ceiling may be supported on the
outside walls only, making it easier to alter the internal walls.
Procedures in demolishing structures will be continued in lesson 3!
Module 2: Demolition Work Procedures
Lesson 3: Demolishing Structure II
Slide Title/ Slide
Screenshot
On-Screen Visuals
Module 2: Demolition
N/A
On-Screen Text
Lesson 3: Demolishing Structure II
Work Procedures
1. Preventing Wall Collapse
2. Adding Extra Weight to an
Internal Wall
3. Supporting the Ceiling
Framing
4. Understanding the Properties
of Materials
5. Using Tools to Break Up the
Materials and,
6. Removing, Sorting and
Storing Materials
Narration
You are now in Lesson 3: Demolishing Structure II
This lesson is the continuation of the discussion on the procedures on
demolishing structure.
Specifically, we will focus on the following procedures:
1.
2.
3.
4.
5.
6.
Preventing Wall Collapse
Adding Extra Weight to an Internal Wall
Supporting the Ceiling Framing
Understanding the Properties of Materials
Using Tools to Break Up the Materials and,
Removing, Sorting and Storing Materials
Component Type/
Notes to Developers
Texts to appear in sync
with the narration
Let’s start!
We now turn to Lesson 3: Demolishing Structure II
In this lesson we’ll continue the discussion on the procedures on
demolishing buildings.
We’ll focus on the following procedures:
1.
2.
3.
4.
5.
6.
Preventing Wall Collapse
Adding Extra Weight to an Internal Wall
Supporting the Ceiling Framing
Understanding the Properties of Materials
Using Tools to Break Up the Materials and,
Removing, Sorting and Storing Materials
Let’s start!
Lesson 3:
Demolishing
Structure II
Procedure # 4: Preventing Wall
Collapse
How to avoid wall collapse through
careful planning:
Mark out for Opening
and Needle Prop
Procedure # 4: Preventing Wall Collapse
The images show how wall collapse can be avoided with careful planning.
Note the staggered breaking away of the unsupported bricks at the top of the
opening. One needle pin and two props through the centre of the opening
may have stopped this collapse.
Procedure # 4: Preventing Wall Collapse
The images shows how wall collapse can be avoided with careful preplanning before you start the job.
Note the staggered breaking away of the unsupported bricks at the top of the
opening. One needle pin and two props through the centre of the opening
could have stopped the wall from collapsing.
Needle Prop in Place to
Take Weight Above
Show the images one by
one at the end of the
narration.
Texts to appear in sync
with narration
Opening
Formatted: Complex Script Font: +Body CS (Cordia
New)
Lintel in Place Ready for
Bricks
Completed Opening
(Refer to the
courseware for the
actual photos)
Lesson 3:
Demolishing
Structure II
N/A
Procedure # 4: Preventing Wall
Collapse
From time to time, accidents occur involving walls collapsing.
Your state or territory publishes alerts about these accidents and what you
can do to avoid similar problems during demolition.
Texts to appear in sync
with narration
How to avoid accidents involving
walls collapsing:
Here are some suggestions for avoiding such accidents.
■
Ensure workers are competent and are supervised by competent
1. Ensure workers are competent
personnel.
and
are
supervised
by ■
Ensure the demolition procedure and plan are appropriate for and
competent personnel.
specific to the job.
■
When taking down entire masonry wall sections, never take down
2. Ensure the demolition procedure
multiple rows of bricks at once and never start at the bottom, so as to
and plan are appropriate for and
avoid weakening walls.
specific to the job.
Without preplanning your immediate job will run into problems and the wall
3. When taking down entire may well collapse, so it’s important to take little time to plan how you’re going
masonry wall sections, never to complete the job to avoid what could be a major problem.
take down multiple rows of bricks
at once and never start at the Your state or territory publishes alerts about these types of accidents and
bottom, so as to avoid what you can do to avoid similar problems during demolition.
weakening walls.
Here are some suggestions for avoiding such accidents, they are.
•
•
•
N/A
Lesson 3:
Demolishing
Structure II
Ensure your workers are competent and are supervised by a
competent person that understands what to do.
Ensure the demolition procedure and plan are appropriate to
complete the job safely.
When you’re taking down entire masonry wall sections, it’s best to
never take down multiple rows of bricks at once or start at the bottom,
this way you’ll avoid weakening walls that have the potential to
collapse.
Texts to appear in sync
with narration
Procedure # 4: Preventing Wall
Collapse
■
How to avoid accidents involving
walls collapsing:
Always finish removing an entire row before starting on the next one.
• When removing masonry for an opening, always support the
masonry above the opening with an appropriate method before you
start to cut the opening.
•
•
4. Always finish removing an entire
row before starting on the next
one.
Always finish removing an entire row before starting on the next one.
When removing masonry at an opening, always support the masonry
above the opening with the right type of support before you start to
cut the opening.
■
5. When removing masonry for an ■
opening, always support the ■
masonry above the opening.
■
Use exclusion zones to keep unwanted people out of the worksite.
Don’t leave a wall standing if it is not supported against collapse.
6. Use exclusion zones to keep ■
unwanted people out of the
worksite.
■
Use keep out or keep away signs to keep unwanted people out of the
worksite.
Never leave a wall standing if it is not supported against collapse.
7. Don’t leave a wall standing if it is
not supported against collapse.
Lesson 3:
Demolishing
Structure II
Image:
Option 1:
3D demonstration of the
procedure based on the
narration
Option 2: Image
representing the
narration
Procedure # 5: Adding
Weight to an Internal Wall
Extra Procedure # 5: Adding Extra Weight to an Internal Wall
If an internal timber wall is going to
take extra weight for which it was not
originally designed, cut out some of
the top plate and punch a post into the
wall space between the studs.
If an internal timber wall is going to take extra weight for which it was not
originally designed, cut out some of the top plate and punch a post into the
wall space between the studs.
3D demonstration should
move in sync with the
narration.
The noggins will knock out of the way and the post can be seated on the
bottom plate. Some damage may be done to the wall surface as the noggin
is moved, but this can be repaired later.
If you are doing alterations that involve this type of work, then you will have
bigger repairs to do than just fixing a few holes in a wall!
Any point load support will need to be continued under the wall bottom plate
and floor. More beams can be added under the floor, spanning some piers
or additional footings and a new pier may need to be installed.
Procedure # 5: Adding Extra Weight to an Internal Wall
Formatted: Font: Not Bold, Not Italic, Complex Script
Font: Bold, Italic
If an internal timber wall is going to take extra weight for which it was not
originally designed, it will need strengthening and you should cut out some
of the top plate and punch a post into the wall space between the studs to
support it.
The noggins can be knocked out of the way and the post can be seated on
the bottom plate. Some damage may be done to the wall surface as the
noggin is moved, but this can be repaired later.
If you are doing alterations that involve this type of work, then you will have
bigger repairs to do than just fixing a few holes in a wall!
Look for any points where load support will be needed, often support can be
continued under the wall bottom plate and floor. Also, more beams can be
added under the floor, spanning some piers or additional footings and a new
pier may need to be installed.
Lesson 3:
Demolishing
Structure II
N/A
Procedure # 6: Supporting the
Ceiling Framing
●
Procedure # 6: Supporting the Ceiling Framing
For temporary support of ceiling framing, use large, flat materials that are
For temporary support of ceiling propped from the floor and span over a large ceiling area.
framing, use large, flat materials
that are propped from the floor The load should be directly on to the ceiling framing and not just on the ceiling
and span over a large ceiling lining.
area.
●
Make sure the floor can support the load until the new permanent support is
The load should be directly on installed. If the floor isn’t strong enough to support any additional loads, then
to the ceiling framing and not back propping may be needed.
just on the ceiling lining.
Procedure # 6: Supporting the Ceiling Framing
Texts to appear in sync
with narration
●
Make sure the floor can For temporary support of the ceiling framing use large, flat materials that are
support the load until the new propped up from the floor and can reach over a large area of ceiling.
permanent
support
is
installed.
The load should be directly supported by the ceiling framing and not just on
the ceiling lining.
Make sure the floor can support the load until the new permanent support is
installed. If the floor isn’t strong enough to support any additional loads, then
back propping may be needed.
Lesson 3:
Demolishing
Structure II
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
Procedure # 7: Understanding the
Properties of Materials
Procedure # 7: Understanding the Properties of Materials
Background image is
static.
It is useful to understand the Rather than randomly cutting into part of the building, it is better to remove
properties of the materials that you materials piece by piece to reveal what is inside.
may be demolishing.
Texts to appear in sync
with the narration.
Examples would be:
It is useful to understand the properties of the materials that you may be
demolishing.
●
Plasterboard has a cardboard For example:
coating on either side which,
when cut, will become brittle and
● Plasterboard has a cardboard coating on either side which, when cut,
will snap easily.
will become brittle and will snap easily.
●
Masonry is brittle in any direction
and all the way through. It can be
chipped away slowly or quickly.
●
Masonry is brittle in any direction and all the way through. It can be
chipped away slowly or quickly. The cracking will usually follow the
mortar, which is normally softer.
●
Timber has a grain structure and
is easily worked with as long as
you remember that timber is
weak along the grain and strong
across the grain.
●
Timber has a grain structure and is easily worked with as long as you
remember that timber is weak along the grain and strong across the
grain.
When demolishing timber, use this characteristic to your advantage by
cutting across the timber and splitting along the grain. Sometimes it is
possible to cut across the grain with a saw (power or hand, often using the
end part of the handsaw blade) or by chiselling across the grain and chipping
material out with the chisel.
Procedure # 7: Understanding the Properties of Materials
It’s not a good idea to cut into the building where you think you should
because it looks easy, it’s much safer to remove materials piece by piece so
you know what’s hidden behind them.
Having a good understanding of the properties of the materials that you may
be demolishing is always useful and will save you time. So good planning
and tool selection is important. For example, what tools would you select to
use with these types of materials…
●
Plasterboard has a cardboard coating on either side which, when cut,
will become brittle and will snap easily.
●
Masonry is brittle in any direction and all the way through. It can be
chipped away slowly or quickly. The cracking will usually follow the
mortar, which is normally softer.
●
Timber has a grain structure and is easily worked with as long as you
remember that timber is weak along the grain and strong across the
grain.
When demolishing timber decide which way, the grain runs to make it easier
to remove. Sometimes it is possible to cut across the grain with a power or
hand saw, or by using a chisel across the grain and chipping material out
with the chisel until you’ve completed the job.
Lesson 3:
Demolishing
Structure II
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
Procedure # 8: Using Tools to
Break up the Material
●
●
●
●
Procedure # 8: Using Tools to Break up the Material
Background image is
static.
Small demolition hammers (used for small jobs) and jackhammers (for large
jobs) produce a lot of force when used correctly and are very useful in
demolition work.
Texts to appear in sync
with the narration.
Small demolition hammers
(used for small jobs) and
jackhammers (for large jobs)
These tools use either air power or electrical power and can have differentproduce a lot of force when used
shaped bits attached.
correctly and are very useful in
demolition work.
Some smaller machines will drill and hammer and can break up material
more easily. However, they can shake the operator around a lot, so you
Smaller machines will drill and
should read and adhere to the operating instructions and take regular breaks.
hammer and can break up
material more easily.
Some large hand-operated machines can demolish a lot of material easily.
Depending on the amount of room you have to work in, it is often better to
Large hand-operated machines
get a machine that is larger than you need and not work it as hard, than to
can demolish a lot of material
get a machine that is too small which has to work too hard. You will tire
easily.
yourself out faster with an undersized machine.
A large sledgehammer and a
A large sledgehammer and a crowbar can be used to break up concrete.
crowbar can be used to break up
Place the crowbar under the concrete path and,using a piece of material to
concrete.
lever the crowbar up on, lift the path off the ground and have someone hit the
concrete with the sledgehammer. Hitting the concrete at its weakest point will
give the best result. Repeat the process until the concrete is small enough to
take away as a clean hard fill.
Procedure # 8: Using Tools to Break up the Material
Tool selection is very important and the rule of thumb is that small tools like
demolition hammers are used for small jobs and larger tools like
jackhammers are used for large jobs. Both small and big tools in the right
hands can produce a lot of force and are very useful in demolition work.
Many tools that are air or electrically powered can be used for many different
jobs as they come with a selection of different-shaped bits and attachments.
Some smaller machines will drill and hammer and can break up material
more easily. But, they can also shake the operator around a lot, so you should
read and follow the operating instructions and take regular breaks.
If you have plenty of space to use a large hand-operated machine which can
demolish a lot of material easily, it’s often better to get a machine that is larger
than you need to do the job and not work it as hard as a smaller machine
would have to work. Having the right tool will help you make the job easier
and won’t tire you out as quickly as using a tool that is too small for the job.
For example, a large sledgehammer and a crowbar can be used to break up
concrete. Place the crowbar under the concrete path and use a piece of
material to lever the crowbar up on, lift the path off the ground and have your
mate hit the concrete with the sledgehammer. Hitting the concrete at its
weakest point will give the best result. Repeat the process until the concrete
is small enough to take away as a clean hard fill.
Lesson 3:
Demolishing
Structure II
Background image:
Hamed storing
demolished materials
Procedure # 9: Removing, Sorting Procedure # 9: Removing, Sorting and Storing Materials
and Storing Materials
Background image is
static.
If required (as part of the plan), remove and sort all fixtures and fittings within Texts to appear in sync
If required, remove and sort all the demolition area inside the building.
with the narration.
fixtures and fittings within the
demolition area inside the building.
This will include removing materials listed on the pre-work audit which may
include sinks, stoves, cabinetry, internal doors and anything that may be able
to be resold or recycled.
This will include removing materials Procedure # 9: Removing, Sorting and Storing Materials
listed on the pre-work audit which may
include sinks, stoves, cabinetry, If required (as part of the plan), remove and sort all fixtures and fittings within
internal doors and anything that may the demolition area inside the building.
be able to be resold or recycled.
This will include removing materials listed on the pre-work audit which may
include sinks, stoves, cabinetry, internal doors and anything that may be able
to be resold or recycled.
Lesson 3:
Demolishing
Structure II
Background image:
Lesson 3:
Demolishing
Structure II
Background image:
Hamed storing
demolished materials
Hamed storing
demolished materials
Procedure # 9: Removing, Sorting Procedure # 9: Removing, Sorting and Storing Materials
and Storing Materials
Background image is
static.
If required (as part of the plan), remove and sort all fixtures and fittings within Texts to appear in sync
If required (as part of the plan), the demolition area inside the building.
with the narration.
remove and sort all fixtures and
fittings within the demolition area This will include removing materials listed on the pre-work audit which may
inside the building.
include sinks, stoves, cabinetry, internal doors and anything that may be able
to be resold or recycled.
This will include removing materials
listed on the pre-work audit which may
include sinks, stoves, cabinetry,
internal doors and anything that may
be able to be resold or recycled.
Key Points to Remember when Key points to remember when removing, sorting and re-using material.
Removing, Sorting and Re-using
Materials:
■
Remove and sort outside material such as stormwater materials,
windows and external doors, keeping it separate from inside material.
1. Remove and sort outside
Inside material is normally more fragile. (Be aware of hazardous
material such as stormwater
materials such as lead.)
materials,
windows
and
external doors, keeping it ■
Follow your state/territory codes of removal of any hazardous materials.
separate from inside material.
This could involve sealing the area with a PVA/water mixture and
allowing that to dry before commencing work, so that hazardous fibres
and dust are coated and held in place. (On older buildings, this could be
Background image is
static.
Texts to appear in sync
with the narration.
2. Follow your state/territory
codes of removal of any
hazardous materials.
3. Remove and sort roof
covering
materials
by
removing the fasteners and ■
then passing the roofing
down to the ground.
wall cladding/lining or roof coverings.) Asbestos lining/cladding can be
removed (check your state or territory’s regulations about dealing with
asbestos) by releasing the fasteners and then talking down the sheeting.
Don’t use grinders or power tools that create dust and don’t water blast
the product.
Remove and sort roof covering materials by removing the fasteners and
then passing the roofing down to the ground. Avoid throwing or dropping
the material because of the dangers associated with this and the
creation of dust. Lower the material to the ground with ropes or pulley
systems if someone experienced in this work is supervising the process.
Key points to remember when removing, sorting and re-using material.
•
Remove and sort outside material such as stormwater materials,
windows and external doors, keeping these materials separate from
inside material. Inside material is normally more fragile. (Be aware of
hazardous materials such as lead.)
•
Follow your state/territory codes of removal of any hazardous
materials. This could involve sealing the area with a PVA/water
mixture and allowing that to dry before commencing work, so that
hazardous fibres and dust are coated and held in place. (In older
buildings, this could be wall cladding/lining or roof coverings.)
Asbestos lining/cladding can be removed (check your state or
territory’s regulations about dealing with asbestos) by releasing the
fasteners and then taking down the sheeting. Don’t use grinders or
power tools that create dust and don’t water blast the product. And
make sure your wearing the right PPE!
•
Remove and sort roof covering materials by removing the fasteners
and then passing the roofing down to the ground. Avoid throwing or
dropping the material because of the dangers associated with this
and the creation of dust. Lower the material to the ground with ropes
or pulley systems and make sure that someone experienced in this
work is supervising the process.
Lesson 3:
Demolishing
Structure II
Background image:
Hamed storing
demolished materials
Key Points to Remember when Key points to remember when removing, sorting and re-using material.
Removing, Sorting and Re-using
Materials:
■
4. Remove and sort the roof
framing structure, rafters or
trusses.
5. Remove and sort the wall
framing wall by wall.
■
■
6. Consider taking down timber
walls by cutting angled sawcuts through them so they ■
come apart easily.
7. Remove floor framing joist by
joist and then bearer by
bearer, using one joist as a
lever to pry the other joist of
the bearer.
Background image is
static.
Texts to appear in sync
Remove and sort the roof framing structure, rafters or trusses. At this with the narration.
stage the building could become unstable, so temporary bracing may be
necessary, just as it was when the building was when the building was
constructed originally.
Remove and sort the wall framing wall by wall.
Consider taking down timber walls by cutting angled saw-cuts through
them so they come apart easily.
Remove floor framing joist by joist and then bearer by bearer, using one
joist as a lever to pry the other joist of the bearer. Prying, rather than
hitting with a sledgehammer, will create less dust and less danger to the
workers.
•
Remove and sort the roof framing structure, rafters or trusses. At this
stage the building could become unstable, so temporary bracing may
be necessary just like it was done when the building was constructed
originally.
•
Remove and sort the wall framing wall by wall.
•
Consider taking down timber walls by cutting angled saw-cuts
through them so they come apart easily.
•
Remove floor framing joist by joist and then bearer by bearer, using
one joist as a lever to pry the other joist off the bearer. Prying, rather
than hitting with a sledgehammer, will create less dust and be a safer
way to do this job.
Lesson 3:
Demolishing
Structure II
Background image:
Hamed storing
demolished materials
Key Points to Remember when Key points to remember when removing, sorting and re-using material.
Removing, Sorting and Re-using
Materials:
■
8. Brickwork
usually
only
requires loosening with a
sledgehammer and it can
then be taken down piece by
piece.
9. Concrete removal will depend
on things like the size of the ■
job and reinforcing.
Background image is
static.
Texts to appear in sync
Brickwork usually only requires loosening with a sledgehammer and it with the narration.
can then be taken down piece by piece. If removing walls by machine,
then remove other materials off the brickwork first, allowing the machine
to collect only those bricks that can be recycled or used as clean hard
fill or cleaned and re-laid. Safe support of brickwork requires knowing
how brickwork performs as a building material. It is heavy and can cause
injury when falling, so be careful.
Concrete removal will depend on things like the size of the job and
reinforcing. Concrete is usually easy to dispose of because it is
considered clean hard fill that is inert. One of the biggest dangers here
is with manual handling. Because concrete can be heavy, take care
when handling it manually.
•
Brickwork can be difficult to demolish so loosening the easy points
first and then using a sledgehammer for the heavy work will help you
to take the brickwork down piece by piece. If removing walls by
machine, then remove other materials off the brickwork first, allowing
the machine to collect only those bricks that can be recycled or used
as clean hard fill or cleaned and re-laid. Safe support of brickwork
requires knowing how brickwork performs as a building material.
Bricks are heavy and can cause injury when falling, so be careful and
wear your hardhat.
•
Concrete removal will depend on the size of the job and how the
concrete has been reinforced. However, concrete is usually easy to
dispose of because it is considered clean hard fill that is inert. One
of the biggest dangers here is with manual handling because
concrete can be heavy, so take care when you’re lifting it by hand.
Lesson 3:
Demolishing
Structure II
Background image:
Hamed working on a
demolition area,
covered with dust.
Effective Ways to Suppress Dust:
1. Hose down the area and keep
it damp.
Dust is a major cause of problems on a demolition site but it can be controlled Background image is
static.
in many ways. Some effective ways to suppress dust include:
Texts to appear in sync
Hose down the area and keep it damp (be aware of any associated with the narration.
electrical and slipping hazards)
2. Seal off the area from dust
■
Seal off the area from dust escape with plastic where possible, although
escape with plastic where
this is difficult for large areas
possible.
■
Use wet hessian sheeting where possible to suppress dust and prevent
it from escaping
3. Use wet hessian sheeting.
Spray dusty areas with a weak glue mixture to assist in holding the dust in
place without the hazards created by wet surfaces. One of the major
4. Spray dusty areas with a
problems on a demolition site is dust but it can be controlled. For example,
weak glue mixture to assist in
some of the effective ways to help stop dust is to:
holding the dust in place.
■
•
Hose down the area with water and keep it damp but be aware of
any electrical and slipping hazards.
• You can seal off the work area to stop dust escaping by using plastic
sheets where possible, although this can be difficult for large areas
• If available use wet hessian sheeting where possible to stop dust
escaping
■• Spray dusty areas with a weak glue mixture to assist in holding the
dust in place without the hazards created by watered surfaces.
Formatted: List Paragraph, Bulleted + Level: 1 +
Aligned at: 0.25" + Indent at: 0.5"
Formatted: Font color: Red
Let’s summarize!
Lesson 3: Demolishing Structure II
Let’s recap what we have learned!
Background image is
static.
In this lesson, we discussed the nitty gritty details of demolishing work
procedures. This is to ensure that health and safety of the workers are top in
mind and that efficiency in work is always considered.
Texts to appear in sync
with the narration.
Background image:
Hamed (seen holding
hand tools/equipment
for demolition work)
1. Preventing Wall Collapse
2. Adding Extra Weight to an
Internal Wall
3. Supporting the Ceiling
Framing
4. Understanding the Properties
of Materials
5. Using Tools to Break Up the
Materials and,6. Removing,
Sorting and Storing Materials
We reviewed the following work procedures in detail:
1.
2.
3.
4.
5.
Preventing Wall Collapse
Adding Extra Weight to an Internal Wall
Supporting the Ceiling Framing
Understanding the Properties of Materials
Using Tools to Break Up the Materials and,6. Removing, Sorting
and Storing Materials
We also touched on some key points and tips that will be helpful for you when
you will be engaged in demolition work.
Let’s recap on what we’ve learnt this lesson!
We’ve looked at the details of demolishing work procedures with importance
being placed on health and safety to ensure the workers are kept safe and
can work efficiently. We also reviewed the following work procedures in some
detail:
1.
2.
3.
4.
5.
Preventing Wall Collapse
Adding Extra Weight to an Internal Wall
Supporting the Ceiling Framing
Understanding the Properties of Materials
Using Tools to Break Up the Materials and 6. Removing, Sorting
and Storing Materials
Finally, we touched on some key points and tips that would be helpful in
demolition work.
Module 2: Demolition Work Procedures
Lesson 4: Recycling and Cleaning Up
Slide Title/ Slide
Screenshot
Module 2: Demolition
Work Procedures
On-Screen Visuals
Background image:
Hamed storing
demolished materials
On-Screen Text
Lesson 2: Recycling and Cleaning
Up
Narration
Welcome
to
lesson
3:
Recycling
Component Type/
Notes to Developers
and
Cleaning
Up!
This is the last lesson to Module 2: Demolition Work Procedures.
This is a brief lesson providing pointers in recycling and cleaning up after
demolition work.
Background image is
static.
Texts to appear in sync
with the narration.
Let’s get to it!
We now turn to Lesson 3: Recycling and Cleaning Up!
This is the last lesson in Module 2: Demolition Work Procedures.
This is a brief but important lesson providing pointers in recycling and
cleaning up after demolition work.
Let’s get to it!
Lesson 2: Recycling
and Cleaning Up
Infographic showing the
5 pointers
Pointers in Recycling and Cleaning
Up:
Ease of clean-up will depend on how well you have demolished the building.
Infographic is static.
Here are some pointers in recycling and cleaning up after demolition:
1. If the demolished material has
been stacked and sorted, it will be
easier to remove from the site.
2. When removing asbestos, there
needs to be a pallet under the
plastic so the plastic-wrapped
asbestos isn’t disturbed.
1. If the demolished material has been stacked and sorted, it will be
easier to remove from the site. Companies specialising in removing
materials are more willing to collect it if it is sorted into categories.
Some material may not need removing - for example, plasterboard
may be rotary-hoed into the ground.
2. When removing asbestos, there needs to be a pallet under the
plastic so the plastic-wrapped asbestos isn’t disturbed. Of course,
check with your local authority and always use licensed contractors
for asbestos removal.
Any easy clean-up will depend on how well you have demolished the
building!
Here are some pointers in recycling and cleaning up after a demolition:
1. If the demolished material has been stacked and sorted properly, it
will be easier to remove from the site. You might consider using a
company that specialize in removing materials, if you’ve stacked and
sorted properly these types of companies are more willing to collect.
Texts to appear in sync
with the narration.
Some material may not need removing - for example, plasterboard
may be rotary-hoed into the ground.
2. When removing asbestos take special care, there needs to be a
pallet under the plastic so the plastic-wrapped asbestos isn’t
disturbed. Of course, check with your local authority and always use
licensed contractors for asbestos removal.
Lesson 2: Recycling
and Cleaning Up
Infographic showing the
5 pointers
Pointers in Recycling and Cleaning
Up:
1.3. After removal of the sorted
material occurs, re-levelling of the
site or preparation for any new
ground work can commence.
2.4. If only part of a building is
demolished, it may be necessary
to cover the remainder of the
building.
3.5. Don’t
use
the
hazardous
materials for anything else once
they are removed.
More pointers in recycling and cleaning up:
3. After removal of the sorted material occurs, re-levelling of the site or
preparation for any new ground work can commence, for example,
new footings may need to be tied into the existing footings in
accordance with the tying-in details provided by an engineer. This
work is much easier when the site is clear and services are made
good or stopped off correctly.
4. If only part of a building is demolished it may be necessary to cover
the remainder of the building. Use tarpaulins or some old roof
sheeting or wall cladding to cover areas that need to be kept dry.
5. Don’t use the hazardous materials for anything else once they are
removed. Secure them according to the regulations in your state or
territory and dispose of them at approved disposal places.
Other tips in the recycling and cleaning up stage are:
3.
After you’ve removed all of the sorted material you can look to relevelling the site or prepare any new ground work that needs doing,
for example, new footings may need to be tied into the existing
footings in accordance with the tying-in details provided by the
engineer. This work is much easier when the site is clear and
services are made good or stopped off correctly.
Infographic is static.
Texts to appear in sync
with the narration.
4. If only part of a building was demolished you’ll have to cover the
exposed part of the building. Use tarpaulins or old roof sheeting or
wall cladding to cover the areas that need to be kept dry.
5. Don’t use hazardous materials for anything else once they’ve been
removed. Just secure them according to the regulations in your state
or territory and dispose of them at an approved disposal centre.
Let’s sum it up!
Background image:
Hamed storing
demolished materials
Lesson 4: Recycling and Cleaning
Up
Pointers:
1. Stack and sort demolished
material for easier removal
from the site.
2. Procedure
on
removing
asbestos
3. Re-levelling of the sire or
preparation for new ground
work can start after removal
of the demolished materials
4. Cover the part of the building
that is not part of the
demolition
5. Don’t
use
hazardous
materials for anything.
In this lesson, we reviewed the 5 points in recycling and cleaning up after
demolition work has been done. These are:
1. Stack and sort demolished material for easier removal from the site.
2. Procedure on removing asbestos
3. Re-levelling of the sire or preparation for new ground work can start
after removal of the demolished materials
4. Cover the part of the building that is not part of the demolition
5. Don’t use hazardous materials for anything.
This ends module 2: Demolition Work Procedures.
To process the information, take a look at the summary of this course.
In this lesson, we reviewed the 5 points in the recycling and cleaning up after
demolition work has been finished. These are:
1. Stack and sort demolished material for easier removal from the site.
2. Procedure on removing asbestos
3. Re-levelling of the site or preparation for new ground work can start
after removal of the demolished materials
4. Cover the part of the building that is not part of the demolition
5. Don’t use hazardous materials for anything else.
To process the information, take a look at the summary of this course.
Background image is
static.
Texts to appear in sync
with the narration.
This is the last lesson for this module 2 and ends our journey with Demolition
Work Procedures.
We hope that you enjoyed learning with us and look forward to seeing you
again. Thank you!